Question:

Spencerville Products is expanding its operations west of the Mississippi.  Its first step is to build a manufacturing facility in Denver to satisfy demand on the West Coast.  Spencerville has an option to build either a large facility that has an annual output of 500,000 units per year or a smaller facility with an output of 250,000 units per year.  It must build one of these two facilities - it does not have any other options.

The expected demand for the company's products is shown as either high or moderate in the table below:

Demand Level                        Annual Demand (units/year)                       Probability

High                                        450,000                                                    0.4

Moderate                                 150,000                                                    0.6

The small facility has a profit of $5.00 per unit.  The large facility has a profit of $4.00/unit.

a) What size facility should Spencerville Products build based on expected values and using a decision tree approach?  You must also provide the decision tree using the appropriate decision tree symbols.

b)  Suppose that the company is not certain about the 450,000 projection for the High Demand scenario.  It could be higher than this projection.  How sensitive is the selection in a) to the High Demand projection.  In other words, at what annual demand for the High Demand scenario would the company be indifferent between the two size facilities?

 


Related Discussions:- Decision tree approach

Research an issue related to computer networks, Assignments should be submi...

Assignments should be submitted via FLO by the above deadline. Penalties for late submission are as set out in the topic SAM on FLO. Extensions can be granted in line with standard

Operation research, Discuss the methodology of operation research

Discuss the methodology of operation research

Find the maximum and minimum values, Problems based on solution of a given ...

Problems based on solution of a given LPP when it has multiple optimal solution: 1.    Find the maximum and minimum values of 5x+2y, subject to the constraints -2x-3y ≤ -6

Two sample tests- hypothesis testing, Two Sample Tests In some  situat...

Two Sample Tests In some  situation the researchers may be taking  statistical decisions based on two samples. Each  of the  two  samples may  represent a particular under con

Application Areas of Linear Programming, what is meant by Application Areas...

what is meant by Application Areas of Linear Programming?

Decision making - operation research, Decision making is not only the h...

Decision making is not only the headache of management rather all of us make decisions. We daily decide about minor issues. The essential characteristics of all decisions

Assignment, discuss about assignment and steps involved in it

discuss about assignment and steps involved in it

Linear Programming Problem using Simple method, Solve the following Linear ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Inherent limitation concerning mathematical expressions, Operation reac Inv...

Operation reac Involves the use of mathematical models, equations and similar other mathematical expressions. Assumptions are always incorporated in the derivation of an equa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd