Critical reasoning, Project Management

Assignment Help:
Ask question #MinimA new client of theirs named “ S&Y ” has started handing good amount of projects
to them. It is estimated that in the upcoming year this crucial client will be giving
them immense projects to finish within given deadlines. The estimates of the
number of projects the client will be handling out to “ Radiance On Axe ” from the
start of 2019 are :
1
st Quarter - 1000 projects per month
2
nd Quarter - 13500 projects per month
3
rd Quarter - 22500 projects per month
The operations team (Ops) is responsible for the completion of projects that are
given by the clients. Current employees(operators) working in the operations
team(Ops) for “ Radiance On Axe ” is 107 ,out of which operators working at night
shift totals 58 and at day shift totals 49. The following data shows how many projects the operations team/ the total
operators have completed each month:
June - 2360 projects per month
July - 2660 projects per month
August - 2420 projects per month
The average time to complete a project is 4 hours. Operators work for 12 hours a day
for 4 days per week but projects are worked on every single day. The work flow is
balanced such that “ Radiance On Axe ” can keep their operation running 7 days a
week. Now with all the data and information given you are to find out :
A) The average projects the operators are currently doing in a month, followed by
average projects each operator is doing in a month and a day as well. ( Show all the
steps clearly )
B) Projection of the total number of projects each operators can do within their
working hours per day. Taking lunch time of 30 minutes, slack time of 1 hour 30
minutes into account. ( Show all the steps clearly )
For the following questions please assume additional 30% of current volume for regular projects + “S&Y” projects ( cases for 1000 projects per month by Q1 2019, 13,500 projects per month by Q2
2019, 22,500 projects per month by Q3 2019). C) Project the total number of operators needed to handle the upcoming projects in
2019 for Q1, Q2, Q3. ( Show all the steps clearly )
C) Project the total number of operators we can allocate to each shift assuming
most of the work is focused on night shift. ( Show all the steps clearly )
D) When facing issues from clients that needs to be resolved what is the best
possible method of solving issue based on your knowledge of escalating issues : - A tiered escalation process is necessary, or
- Would you rum 100 words accepted#

Related Discussions:- Critical reasoning

Explain constant power and constant impedance, Study of the Load impact on ...

Study of the Load impact on power flow with (constant power, constant impedance, constant current, induction motor) and use the PowerWorld simulator.

Commercial project negociation, I want to make a report on this topic by to...

I want to make a report on this topic by tomorrow morniing

Basic process involved in project closure , Basic process involved in proje...

Basic process involved in project closure  The end deliverables becomes the focus of the closure plan, that is,  to ensure a high level of end user satisfaction. Hence processe

Find critical path and project duration, 1. Explain the concept involved in...

1. Explain the concept involved in operations strategy and the emerging trends in the area of Operations Management. 2. Draw the network. Find critical path and project duration

Design changes during production, Even when the design has been released...

Even when the design has been released for production it cannot be considered to be absolutely final requiring no further changes. Certain problems may be faced during produ

Process of delivering a presentation, Question : The process of deliver...

Question : The process of delivering a presentation is a systematic one that involves thorough planning as well as preparation and one of the main phases is preparing the prese

Attractiveness of the industry in which ff currently operate, The Board of ...

The Board of FF Supermarket is examining the company's current market position. As part of the review, the Board has asked for an analysis of industry competition to be undertaken

Project integration management, You work for Point-Of-Sale Solutions (POSS)...

You work for Point-Of-Sale Solutions (POSS), an international point of sale company, which has decided to provide an Internet enabled menu ordering system delivered on the iPad as

What are the principal stages of a project life cycle, Question 1: (a) ...

Question 1: (a) What are the principal stages of a project life cycle? (b) Describe fully the steps involved in the project planning process. Question 2: "Effective

Allocation of resources, Explain how resource allocation can impact an orga...

Explain how resource allocation can impact an organisation?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd