Critical reasoning, Project Management

Assignment Help:
Ask question #MinimA new client of theirs named “ S&Y ” has started handing good amount of projects
to them. It is estimated that in the upcoming year this crucial client will be giving
them immense projects to finish within given deadlines. The estimates of the
number of projects the client will be handling out to “ Radiance On Axe ” from the
start of 2019 are :
1
st Quarter - 1000 projects per month
2
nd Quarter - 13500 projects per month
3
rd Quarter - 22500 projects per month
The operations team (Ops) is responsible for the completion of projects that are
given by the clients. Current employees(operators) working in the operations
team(Ops) for “ Radiance On Axe ” is 107 ,out of which operators working at night
shift totals 58 and at day shift totals 49. The following data shows how many projects the operations team/ the total
operators have completed each month:
June - 2360 projects per month
July - 2660 projects per month
August - 2420 projects per month
The average time to complete a project is 4 hours. Operators work for 12 hours a day
for 4 days per week but projects are worked on every single day. The work flow is
balanced such that “ Radiance On Axe ” can keep their operation running 7 days a
week. Now with all the data and information given you are to find out :
A) The average projects the operators are currently doing in a month, followed by
average projects each operator is doing in a month and a day as well. ( Show all the
steps clearly )
B) Projection of the total number of projects each operators can do within their
working hours per day. Taking lunch time of 30 minutes, slack time of 1 hour 30
minutes into account. ( Show all the steps clearly )
For the following questions please assume additional 30% of current volume for regular projects + “S&Y” projects ( cases for 1000 projects per month by Q1 2019, 13,500 projects per month by Q2
2019, 22,500 projects per month by Q3 2019). C) Project the total number of operators needed to handle the upcoming projects in
2019 for Q1, Q2, Q3. ( Show all the steps clearly )
C) Project the total number of operators we can allocate to each shift assuming
most of the work is focused on night shift. ( Show all the steps clearly )
D) When facing issues from clients that needs to be resolved what is the best
possible method of solving issue based on your knowledge of escalating issues : - A tiered escalation process is necessary, or
- Would you rum 100 words accepted#

Related Discussions:- Critical reasoning

Second elaboration iteration, Perform a status assessment of the second Ela...

Perform a status assessment of the second Elaboration iteration. DO NOT GENERALISE. Assess each activity separately against the outcomes specified for the activity. Generate a deta

How is risk management assist in project management software, How is risk m...

How is risk management assist in project management software? Risk management: Project management software will assist manage the sheer complexity of managing funds and tools,

Name an approach to systems implementation, Name an approach to systems imp...

Name an approach to systems implementation?  Matrix operation.

Tool of total quality improvement, Question: As the Managing Director o...

Question: As the Managing Director of your organization, you have been analyzing other institutions that you regard as competitors. Extrapolating your current position up to t

Relationship-reporting arrangements of manager with sponsor, What type of r...

What type of relationship and reporting arrangements must the project manager have with the sponsor? The sponsor of a project shows the management of the organisation which com

PERT Network Analysis, Solve the following CPM/PERT Network Analysis proble...

Solve the following CPM/PERT Network Analysis problem: Given the following network and activity time estimates, determine (ES, LS, EF, LF) earliest and latest activity times, slac

Differences between wbs and product breakdown structure, a) Draw a work bre...

a) Draw a work breakdown structure (WBS) diagram for the project, to show all the planned tasks. This WBS should contain at least two levels. b) Explain the main differences bet

Factors affecting process design - degree of automation, Factors affecting ...

Factors affecting Process Design - Degree of Automation The degree of automation  to be  adopted and  integrated into the  production  system is a key issue in process design,

Process selection - tqm, Once the process capabilities of available proc...

Once the process capabilities of available processes are known the process selection is then just a question of matching the process capability with the tolerance specified

Employee involvement and error-free process, Elements of total quality mana...

Elements of total quality management: Employee involvement: Employee involvement  and team building helps in fostering collaboration, trust, open, honest communication

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd