2. Draw the network diagram for the following problem and indicate a sequence of plans that the company should want to consider in making a time-cost tradeoff. The company is not interested in reducing the project duration below 29 days. Start with the plan that has the longest duration.



Activity
Preceding Activity
Time(days)

Regular Crash

Program Program
Cost ($)

Regular Crash

Program Program

A
-
10 9
5,000 5,200

B
-
14 11
3,500 3,950

C
A
8 7
4,000 4,100

D
A
7 2
2,100 3,600

E
B
5 3
2,500 3,000

F
B
10 7
2,250 3,750

G
C
9 9
5,000 5,000

H
D, E
11 9
3,850 5,250

I
G, H
5 3
2,375 3,575


Related Discussions:- CPM @ pert

Information system project management, Hi there, i am looking an expert to ...

Hi there, i am looking an expert to make my assignments for this subject and i do have other subjects as well. Let me know how you can go through my assignment.

Explain value added analysis and top management styles, 1. Explain Value Ad...

1. Explain Value Added Analysis along with the major factors included in Management Accounting Analysis. 2 Identify the several top management styles and define their implicatio

Explain the growth, Explain the growth, index, sectoral, gilt and money mar...

Explain the growth, index, sectoral, gilt and money market methods? (i) What are the key variations among the open ended and close ended methods? What are the plus and minuses

Describe breadth indicators and market sentiment indicators, Describe bread...

Describe breadth indicators and market sentiment indicators? 1. Distinguish among technical and fundamental analysis. As well explain essential concepts underlying chart analys

Case study, Please help me with these problems Merry -Go -Around (MGR) ...

Please help me with these problems Merry -Go -Around (MGR) a clothing retailer located primarily in shopping malls, was founded in 1968. By the early 1990s, the company had gon

What are the objectives of budgetary control, What are the Objectives of bu...

What are the Objectives of budgetary control 1) Planning : planning is an important managerial function. it helps to decide in advance, what to do how to do it when to do it a

Multi-collinearity, Multi-collinearity Multiple regression analysis is ...

Multi-collinearity Multiple regression analysis is based on the assumption that the independent variables are not correlated with each other, whenever the independent variables

Standard costing .., the applicability of standard costing in modern manufa...

the applicability of standard costing in modern manufacturing environments in volatile environments

Monitoring receivables, A firm requires continuously monitoring and control...

A firm requires continuously monitoring and controlling its receivables to make sure that the dues are paid on the due date and no dues stay outstanding for a long period of time.

EOQ, a annual sales are 585000 unit. the purchase price per unit is $2. the...

a annual sales are 585000 unit. the purchase price per unit is $2. the carrying cost is 26% of purchase price of goods safty stock is 100000 units on hand two weeks are required fo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd