Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Job order costing, the folloeing job order cost sheets were purchased for t...

the folloeing job order cost sheets were purchased for three jobs that were in production during january job 97 job 98 job 99 material

Cost acunting, Weston Corporation manufactures a product that is available ...

Weston Corporation manufactures a product that is available in both a deluxe and a regular model. The company has made the regular model for years; the deluxe model was introduced

Pv ratio, Do I use the contribution per unit and the total sales for the de...

Do I use the contribution per unit and the total sales for the department in order to calculate the p/v ratio for a department

What would be the cost transferred to the blending dept., Walter manufactur...

Walter manufactures a silicone paste wax that goes through three processing departments: cracking, blending, and packing. All raw materials are introduced at the start of work in t

Interpret the data and make recommendations based on, FDP Company produces ...

FDP Company produces a variety of home security. Gary Price, the company’s president, is concerned with the fourth quarter market demand for the company’s products. Unless someth

What was the cost of goods manufactured for the period, A company started w...

A company started with $0 in direct materials, purchased $5,000 of materials, and ended with $300 in materials. Direct labor equaled $4,000. The applied overhead for the period was

Cost sheet, what is a cost sheet? what are its advantages?

what is a cost sheet? what are its advantages?

Marginal cost, Marginal Cost Marginal cost is the change in a firm's co...

Marginal Cost Marginal cost is the change in a firm's cost of production. It is related to a unit change in its output, or the added cost of producing the next unit. The margin

Operating costing, meaning and definition of operating costing

meaning and definition of operating costing

Absorption costing, Absorption Costing The process described in this s...

Absorption Costing The process described in this section by that net overheads are absorbed into production naturally enough is identified as absorption costing.  The absorpti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd