Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Applications of funds, Requirement for additional Funds A business would...

Requirement for additional Funds A business would require additional capital for two purposes: 1. Financing additional fixed assets, and

Calculate average cost to manufacture, Sony manufactures battery for Iphone...

Sony manufactures battery for Iphone 6+. The average costs to manufacture batteries are $4 for 10,000 ad $2.67 for 30,000. Assuming the total cost function is linear, what will be

debt service fund and special revenue fund, For your assignment, discuss w...

For your assignment, discuss when the government and nonprofit organizations would use each of the following funds: Capital projects fund Debt service fund Special r

Budget, budget preparation

budget preparation

Calculate the manufacturing cost per unit, the following activities relatin...

the following activities relating to indirect production costs: Activity Activity Costs Cost Drivers Machine Setup $180,000 1,500 setup hours Materials Handling $50,000 12,500 poun

#title.materials costing and accounting., material ledger card.following t...

material ledger card.following transactions affecting material No115-8 occurred during march 1992. march 1 balanced on hand 500 [email protected] per gallon maech 2 received 1200 gall

Calculate break-even level of sales volume and revenue, Q. Calculate break-...

Q. Calculate break-even level of sales volume and revenue? Z-Boxes sell for £299 and their variable production cost is £99. Research and development, and fixed production overh

Compute the equivalent units of production for materials, Clopack Company m...

Clopack Company manufactures one product that goes through one processing department called Mixing. All raw materials are introduced at the start of work in the Mixing Department.

Overapplied or underapplied overhead: manufacturer, Budgeted direct labour ...

Budgeted direct labour cost 75000 hours @ $16 per hour Budgeted manufacturing overhead 80 000 hours @ $17.50 per hour Actual direct labour cost $997 500 Budgeted manufa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd