Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Calculate the monetary of the inventory, Learning Objective: After completi...

Learning Objective: After completing the project, the student will have gained familiarity, understanding and mastery of programming a realistic but simple application in Assembly

What was the cost of goods manufactured for the period, A company started w...

A company started with $0 in direct materials, purchased $5,000 of materials, and ended with $300 in materials. Direct labor equaled $4,000. The applied overhead for the period was

Cost drivers and predictors, why is determining the cost to manufacture a p...

why is determining the cost to manufacture a product quite a different activity from determining how to control such cost?

What are fixed costs, The costs that are fixed irrespective of manufacture ...

The costs that are fixed irrespective of manufacture are fixed costs. EX: Rent, Depreciation. Fix cost is those cost who not alter in any time whether the production done or not

Standard costing, What are the benefitss and drawbacks of standard costing?...

What are the benefitss and drawbacks of standard costing?

Differential costing, What do you mean by differential costing ? How it dif...

What do you mean by differential costing ? How it differ from marginal costing ? explain its practical application with examples?

Tax depreciation affect the cash flows statement?, What type of activity co...

What type of activity could a company engage in to improve their cash flows in their Cash Flows Statement? Is this ethical? Could borrowing money make the cash from operations be

What is cost accounting, This can be explained as the process of accumulati...

This can be explained as the process of accumulating, calculating, analyzing, interpreting and reporting cost information that is both helpful and relevant to the internal and exte

Calculate average cost to manufacture, Sony manufactures battery for Iphone...

Sony manufactures battery for Iphone 6+. The average costs to manufacture batteries are $4 for 10,000 ad $2.67 for 30,000. Assuming the total cost function is linear, what will be

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd