Cost variance and schedule variance, Cost Accounting

Assignment Help:

(i) In terms of cashflow, which month will be the most costly for your project?

(ii) If the 3rd and 4th months are more expensive by 25% each because the outsourced labour took longer than expected, what is the effect on the final predicted project cost? What action do you think you could take in these circumstances? 

3(c) Assume you have completed three months of the project. The Budget at Completion (BAC) was $250,000 for this six-month project. Also assume the following:

Planned Value (PV) = $150,000

Earned Value (EV) = $140,000

Actual Cost (AC) = $125,000  

2343_Cost variance and schedule variance.png

Use this information to answer the following questions.

(i) What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project?

(ii) Use the CPI to calculate the estimate at completion (EAC) for this project. Use the SPI to estimate how long it will take to finish this project. Sketch an earned value chart using the above information, including the EAC point. Use the chart below (Figure 7-5, p.289 in Schwalbe 5ed) as an example of what your Earned Value Chart should look like. Comment on your chart.

(iii) How is the project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget? Should you alert POSS senior management and ask for assistance?


Related Discussions:- Cost variance and schedule variance

Types of cost, i want to know the different types of costs.

i want to know the different types of costs.

Total variable overheads variances, Total Variable Overheads Variances ...

Total Variable Overheads Variances  If Variable Overhead Expenditure Variance =  Shs.1, 330 Variable Overhead Efficiency Variance = Shs.320 Then total variable overheads

Price to set on the job, Bakeson Bearings Ltd is preparing to submit a bid ...

Bakeson Bearings Ltd is preparing to submit a bid for a bearings order.  Janet Lake,  CEO of the Manufacturing Division, has asked Jason Docker, the management accountant, to prepa

Managerial accounting, Classic Coolers manufactures portable coolers adorne...

Classic Coolers manufactures portable coolers adorned with college logos. During the first quarter of the year, the company had the following costs: Direct materials used $55,500 D

Cost drivers and predictors, why is determining the cost to manufacture a p...

why is determining the cost to manufacture a product quite a different activity from determining how to control such cost?

Business process mapping, Using some variation of business process mapping,...

Using some variation of business process mapping, graph out the mango concentrate supply chain focusing on when cost is added to the supply chain. (i.e. Display/draw the process

Methods of costing, METHODS OF COSTING : 1. Job costing :  Job costing ...

METHODS OF COSTING : 1. Job costing :  Job costing is the essential costing technique appropriate to those industries somewhere the work consist of separate contracts, or batch

Compute the sales activity variance for each product, The next year's budge...

The next year's budget for Benny, Inc., is given below: Product 1-2 Sales $945,000-688500 Variable costs 459,900-297,000 Fixed costs 300,000-3

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd