Q. Corrosion protection of lifting anchors in precast concrete?

Corrosion of lifting anchors in precast concrete units has to be prevented since the corroded lifting units cause an increase in steel volume leading to spalling of nearby surface concrete. Subsequently steel reinforcement of the precast concrete units can be exposed and this in turns results in the corrosion of steel reinforcement and reduction in the load carrying capacity of precast units. To combat the potential corrosion problem, lifting anchors could be covered with a layer of mortar to hide them from possible external corrosion agents. Otherwise galvanized or stainless steel lifting anchors can be considered in aggressive environment.


Related Discussions:- Corrosion protection of lifting anchors in precast concrete

Road drainage and maintenance, Road Drainage and Maintenance: The life...

Road Drainage and Maintenance: The life of a road depends upon how well and quickly the water is drained away from its various components. Similarly, regular and periodic insp

Find the normal stress, Find the normal stress: Figure 1 shows the pro...

Find the normal stress: Figure 1 shows the projection of a rectangular prism ABCD, formed by adhesive bonding of two triangular prisms ABC and ACD. The state of stress in the

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

Define the thiem equations for confined aquifers, Define the Thiem Equation...

Define the Thiem Equations for Confined Aquifers   Using natural log:  Q = 2ΠKm(h 2 - h 1 )/ln(r 2 /r 1 )      m = aquifer thickness (ft) Using log 10 :   Q = 2Km(h 2 - h

Linear programming, what are the advantages of linear programming?

what are the advantages of linear programming?

Problems formed while design of pre-stressed concrete, Determine the proble...

Determine the problems formed while design of pre-stressed concrete Two types of problems are encountered by  the engineer engaged in the design of pre-stressed concrete membe

Sub-base for concrete carriageway - non-strength provider, Sub-base for con...

Sub-base for concrete carriageway - non-strength provider Essentially sub-base for a concrete carriageway is provided for the below reasons: (i)  It provides aneven and smo

Computation of settlement, Q. Computation of Settlement? The settlement...

Q. Computation of Settlement? The settlement  in any soil mass under an applied stress is given by s = s i + s c + s s where, S  =  total settlement, S i =  imm

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd