construction material, Civil Engineering

Assignment Help:
4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Accuracy and range - angle measurement, Accuracy and Range - Angle measurem...

Accuracy and Range - Angle measurement: Accuracy and Range:-Angle measurement:-Most modern total station instruments measure angles by means of electro-optical scanning of ext

Optical square, Using an optical square how would you perform a rectangular...

Using an optical square how would you perform a rectangular tie?

Determine the required area of steel, A rectangular concrete beam is subjec...

A rectangular concrete beam is subjected to a factored moment (Mu) of 345 kip*ft.  The beam has the following properties: f'c = 5500 psi fy = 60,000 psi h = 39 in

Calculate the amount of import or export, Calculate the Amount of Import or...

Calculate the Amount of Import or Export For the project site shown in Figure, the amount of import or export to bring the entire site to elevation 90-ft is most nearly:

Simple stresses and strains, SIMPLE STRESSES AND STRAINS: The concepts...

SIMPLE STRESSES AND STRAINS: The concepts of strain, stress, elastic modulus & the basic concepts in application to analysis of deformation and stresses in simple solids. Any

Theorem of three moments, Theorem of three moments: You have been intr...

Theorem of three moments: You have been introduced to the analysis of one of the important class of structures, namely Statically Indeterminate Structures. You have been intro

Compute the degree of saturation, The maximum dry density and optimum moist...

The maximum dry density and optimum moisture content of a soil from standard proctor's test are 18 kN/m 3 and 16% respectively. Compute the degree of saturation of the sample,

Construction - concrete pavement, Construction: Construction is usual...

Construction: Construction is usually done by one of the three methods: (a) Manual method, providing steel or wooden forms, pouring concrete and compacting by means of nee

M.o.c, lime saturation factor meaning with simple english

lime saturation factor meaning with simple english

Calculate the diameter of the stockpile, 1. On a 5-acre level terrain build...

1. On a 5-acre level terrain building site, an earthwork contractor has instructed her crew to strip and grub the topsoil of a 60,000-ft 2 proposed building pad to a minus 2-ft su

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd