4. Calculate the loose volume of material needed to fill in the trench as sketched below. The following information is also known: [7] o Length of trench = 250 m o Trench pipe = 300 mm diameter.
o Width of trench = 600 mm o Depth of trench = 1000 mm o Bank m 3 = 2150 kg/ m 3 o Loose m 3 = 1935 kg / m 3

Related Discussions:- construction material

Analysis and design Of Swimming Pool, Hi Sir I have a graduation project ...

Hi Sir I have a graduation project part (A) in this semester. I have chosen topic (Analysis and design of Swimming Pool). I got this project ready from friend so I want Presented

Design volume of the aeration basin - sewer construction, Design volume of ...

Design volume of the aeration basin - sewer construction: Problem: What is the design volume of the aeration basin? Solution Assuming that 30% of the plant influe

Fluids, FLUID substance which deforms continuously when subjected to a shea...

FLUID substance which deforms continuously when subjected to a shear stress  LIQUID no fixed shape deforms under gravity to container shape virtually incompressible = const

Usage of double air valves and single air valves, Question In designig ...

Question In designig of watermains, how to decide usage of double air valves and single air valves ? Answer Single air control device let squeezing air out of p

Enumerate the term - superposing the stress variations, Enumerate the term ...

Enumerate the term - superposing the stress variations If the case of concentric pre-stressing is considered, we can appreciate that stress at any section of the beam is compr

Sight distance - geometric design of roads, Sight Distance: Sight dis...

Sight Distance: Sight distance is the distance along a road at which a driver has a visibility of objects and can safely stop his vehicle or overtake another vehicle. Sto

Location of construction joints, Q. Location of construction joints? Co...

Q. Location of construction joints? Construction joints are generally required in construction works since there is limited supply of fresh concrete in concrete batching plants

CONCRETE BATCHING, DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd