Pattern of load distribution of piles in such agreement, Civil Engineering

Assignment Help:

Question

For a rigid pile cap with vertical piles at middle and raking piles at the sides, what is pattern of load distribution of piles in such agreement?


Answer

Because of effect of interaction of individual piles, central piles tend to settle additional than edge piles while pile cap is under a uniform load. Then, raking piles at edge take up a higher fraction of total loads and are theme to higher axial and pliant loads in case pile cap is stiff. In extreme case, failure of these raking edge piles could happen.

 


Related Discussions:- Pattern of load distribution of piles in such agreement

Use of PFA and GGBS, Q. Use of PFA and GGBS? Both PFA and GGBS are by-p...

Q. Use of PFA and GGBS? Both PFA and GGBS are by-products of industry and use of them is ecologically friendly. Most significantly, with PFA and GBS adopted as partial replacem

Explain the operating point - pumping system, Explain the Operating Point -...

Explain the Operating Point - Pumping System Intersection of the characteristic curve and the system curve. This is the head and flow rate data for the pump "operation". The op

AAA, Ask question #MiAAAAnimum 100 wordAs accepted#

Ask question #MiAAAAnimum 100 wordAs accepted#

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Torsion, assumptions made in the simple torsion theory

assumptions made in the simple torsion theory

Define divers in a team for underwater inspection of bridge, Define Divers ...

Define Divers in a team for Underwater inspection of Bridge? One team of divers should have minimum three members. This is a requirement of safe working. The idea is while a mi

Explain equation for change interval, Explain equation for Change Interval ...

Explain equation for Change Interval y = t + v / 2a + 64.4G Where:  y = length of yellow interval (sec)     t = driver perception/reaction time (1.0 sec generally used)

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Harbour, what is entrance channel in harbour?

what is entrance channel in harbour?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd