Compute the mad and mse, Operation Management

Assignment Help:

The last 4 weekly values of sales were 80,100,105 and 90 units. The last 4 forecast (for the same 4 weeks) were 60, 80, 95 and 75 units.
Calculate the MAD, MSE and MAPE for these 4 weeks

Sales - 80, 100, 105, 90

Forecast - 60, 80, 95 75

Error - 20, 20, 10, 15

Error Squared - 400, 400, 100, 225

PCT Error - . 25, .20, .095, .167


Related Discussions:- Compute the mad and mse

Explain what elements interest in the negotiations, Assuming that I am the ...

Assuming that I am the negotiator who is tasked with a salary (on call time, step increases, overtime for captains and majors) and benefits (insurance while employed, insurance aft

Explain router could not be used as a fire wall, Which of the following cou...

Which of the following could not be used as a fire wall? a. hub b. router c. server d. PC

Change Management in Process/Systems?, main principles of project managemen...

main principles of project management aiding the operations manager/manageress in introducing change to the process/system?

Explain a product at each stage of the plc, Using the product life cycle, d...

Using the product life cycle, describe a product at each stage of the PLC and support your choice.

Responsibilities of operations managers, what are the direct responsibiliti...

what are the direct responsibilities of operations managers?

Production control function, Production control Function 1. Dispatchi...

Production control Function 1. Dispatching : Dispatching may be  defined as setting  production activities in motion through  the  release  of orders ( work order shop order)

Explain what are the optimal solution values of x and y, Suppose the firm i...

Suppose the firm in this example considers a second product that has a unit profit of $5 and requires 2 hours for each unit produced. Assume total production capacity remains 40. U

Linear programming, A paper mill produces two grades of paper viz., X and Y...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Explain what are some of the best practices, You are the retiring CEO of a ...

You are the retiring CEO of a company which you have led for the last 10 years. You have recruited a new management team and you are addressing the final management conference whic

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd