Compute the mad and mse, Operation Management

Assignment Help:

The last 4 weekly values of sales were 80,100,105 and 90 units. The last 4 forecast (for the same 4 weeks) were 60, 80, 95 and 75 units.
Calculate the MAD, MSE and MAPE for these 4 weeks

Sales - 80, 100, 105, 90

Forecast - 60, 80, 95 75

Error - 20, 20, 10, 15

Error Squared - 400, 400, 100, 225

PCT Error - . 25, .20, .095, .167


Related Discussions:- Compute the mad and mse

Explain contemporary theorists emphasize two approaches, 1. As management t...

1. As management theory has evolved, contemporary theorists emphasize two approaches: the "systems approach," and the "contingency approach." Explain each. 2. Regarding ethics a

Why hrm-r technologies financial impact of talent management, • Analyze the...

• Analyze the article's perspectives concerning talent management and technology issues. • Suggest strategies for evaluating HRM-r technologies financial impact of talent manage

Explain what is framing and how frames work in negotiation, What is framing...

What is framing and how frames work in negotiation. Describe an example

Define the parameters and the potential implications, The internet is a sta...

The internet is a staple of the modern office. Some companies are concerned that the Internet (and its e-mail application) lead to increased theft of time in the workplace. But, ot

Evaluation of the process design, Evaluation of the Process Design On...

Evaluation of the Process Design One of the objectives in designing the process flow is to ensure that goods and services are produced at minimum cost. A major problem confro

Find forecasted sales for week first, In the table given below the Distribu...

In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what woul

Innovative ideas for management position, These are questions I were asked,...

These are questions I were asked, i'm assuming you could understand the question based on the way I worded the answers. It's suppose to be a paragraph but i'm not exactly sure what

Explain the importance of indirect costs, One of the advantages of using a ...

One of the advantages of using a project cost-duration graph is that it keeps the importance of indirect costs in the forefront of decision making (true or false)

Problem, a firm isconsidering replacement of a machien, whoes cost price is...

a firm isconsidering replacement of a machien, whoes cost price is rs 12200 and scrap value is rs 200 the running cost is rupee given below year running cost 1 200 2 50

Depict a graph of the exponential function, Solve for x: log_10?x=3 5. You'...

Solve for x: log_10?x=3 5. You've earned your degree and have been hired by an established company. You were able to negotiate a beginning salary of $2500 per month with annual 6%

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd