Compute over and under absorption of variable overhead, Cost Accounting

Assignment Help:

Compute Over and Under Absorption of Variable and Fixed Overhead

A company has a machine cost center for that the given information is available as

a) Budget

i. Budgeted (expected) activity                                            3000 machine hours

ii. Variable production overhead cost per machine hour      Shs. 2

iii. Fixed production overhead cost net                                Shs. 9000

b) Actual

i. Activity level                                                                      3000 machine hours

ii. Variable production overhead cost incurred                     Shs. 6400

iii. Fixed production overhead cost incurred                          Shs. 8800

Required

1. Compute the over and under absorption of variable overhead and fixed overhead cost

2. Comment on possible reasons of over or beneath absorption figures

Solution

Variable overhead cost

Actual cost incurred                                                    Shs.6400

- Overhead absorbed 3000 hrs x Shs. 2                     Shs.6000

                                                                                   Shs.  400

Below absorption may contain occurred via a combination of        

a) Increased price per unit of variable cost as an example of a rise in price or electricity

b) An increase in the number of units of overhead cost item, as an example of machine efficiency has fallen via lack of maintenance

Fixed overhead cost:

Actual cost incurred                                                   Shs. 8800

- Overhead absorbed 3000 hrs x Shs. 3                    Shs. 9000

Over absorption of overhead cost                             Shs.  200

The fixed overhead absorption rate 9000/3000 machine hours = Shs. 3 per machine hour.

The real activity level of 3000 machine hours is the similar as that budgeted. Therefore the over absorption of fixed overhead is because of expenditure factors. It may have happened as of the combination of

a) A lower price of a fixed item as an example of salary may be lower than budgeted

b) A reduced usage of what was classified as a fixed cost item as an example of the quantity of oil employed to lubricate the machines.


Related Discussions:- Compute over and under absorption of variable overhead

Answer, Chen Enterprises purchased 67,000 pounds (cost = $616,400) of direc...

Chen Enterprises purchased 67,000 pounds (cost = $616,400) of direct material to be used in the manufacture of the company''s only product.

OBJECTIVES OF COST ACCOUNTING, OBJECTIVES OF COST ACCOUNTING : 1-DETERMININ...

OBJECTIVES OF COST ACCOUNTING : 1-DETERMINING SELLING PRICE 2-CONTROLING COST 3- PROVIDING INFORMATION FOR DESING MAKING 4-ASCERTAINING COSTING PROFIT 5-Facilitating preparation of

Calculate cost for each unit, Dropping a segment - George's Grill analyzes ...

Dropping a segment - George's Grill analyzes profitability of three operating units: restaurant, bar, and billiards room. Revenues, variable costs, and attributable fixed costs (wh

Bad debts, These are losses on account of uncollectable debts. While the am...

These are losses on account of uncollectable debts. While the amount due from debtors is irrecoverable, it is termed as bad debts. Bad debts, being loss are closed through transfer

the opportunity cost rate is 8 percent, Find the following values for a si...

Find the following values for a single cash flow: a. The future value of $500 invested at 8 percent for 1  year b. The future value of $500 invested at 8 percent for 5 years

allocation of cost, looking for a dissertation of cost allocatio

looking for a dissertation of cost allocation

Direct materials total variance, Direct Materials Total Variance Direc...

Direct Materials Total Variance Direct materials total variances refer to the difference between the standard direct material cost of the actual production volume and the actu

Prepare a spreadsheet of an overhead budget, Prepare a spreadsheet of an ov...

Prepare a spreadsheet of an overhead budget for the company in Problem 5 on page 216 of the textbook. You have been running a construction company out of your home with your spouse

Interest earned on down payment, You sell a machine for $600,000. You allow...

You sell a machine for $600,000. You allow the client to pay 1/3 at the time of the sale and 1/3 at the end of year one and 1/3 at the end of year two. The company earns 10% on ass

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd