Compaction to freshly placed concrete piles, Civil Engineering

Assignment Help:

Compaction to freshly placed concrete piles 

In general practice, reliance is placed on the self-compaction of particularly designed concrete mixes to achieve adequate compaction. The use of vibrating devices such as poker vibrators is rarely adopted for the compaction of concrete piles. As a matter of fact, other than the consideration of the impracticality in using vibrating device in long piles, there is serious concern about possible occurrence of aggregate interlock that poses difficulty at the time of casing extraction. In the worst scenarios, temporary casings together with reinforcement cages are extracted at the time of the lifting up of pile casings. This is another reason that accounts for not using vibrating machines for piles with casing extraction.


Related Discussions:- Compaction to freshly placed concrete piles

State the total load which the raft can support, A raft, 8 m × 24 m, is fou...

A raft, 8 m × 24 m, is founded at a depth of 4 m in sand with a value of N = 20 up to great depth. Illustrate the total load which the raft can support? What will be the total c

Verify the net allowable bearing pressure, A 1.8 m square column is founded...

A 1.8 m square column is founded at a depth of 1.8 m in sand, for which the accurate N-value is 24. The water table is at a detph of 2.7 m. Verify the net allowable bearing pres

Open graded premix carpet, please tell me about gradation of open graded pr...

please tell me about gradation of open graded premix carpet

Rail tensors, A hydro stressor consists essentially of a hydraulic pump whi...

A hydro stressor consists essentially of a hydraulic pump which transmits its force through connecting vans to clamps which grips the rail. In case of mechanical tensor the force i

Evaluate dimensions of apron according to spring and gale, Q. Evaluate dime...

Q. Evaluate dimensions of apron according to Spring and Gales? Dimensions of apron according to Spring and Gales. Gales and Sethi favoured uniform thickness of laid apron while

Explain precedence relationships - construction management, Explain the Pre...

Explain the Precedence Relationships a. Finish-to-Start - the most common, the predecessor activity must finish before the successor activity can start b. Finish to Finish

State the net allowable bearing pressure, A footing, 2 m square, is founded...

A footing, 2 m square, is founded at a depth of 1.5 m in a sand deposit, for which the corrected value of N is 27. The water table is at a depth of 2 m from the surface. Verify the

Explain about the hydrogen embrittlement, Explain about the Hydrogen Embrit...

Explain about the Hydrogen Embrittlement As a result of the action of acids on high-tensile steels, liberation of hydrogen takes place. It penetrates into the steel surface an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd