Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Distribution methods, 1: explain vogel''s approximation method? 2: explain ...

1: explain vogel''s approximation method? 2: explain optimality test?

Research abstracts, Research Abstracts Abstracts of researches comp...

Research Abstracts Abstracts of researches completed are available from the followings publications: a. ICSSR Research Abstracts: contain abstracts of research projects

Case study and statistical methods, Case Study Methods: It is studying the...

Case Study Methods: It is studying the phenomenon event situation or development through a thorough and detailed analysis or intensive study. The case may be an individual a gr

Linear programming, b. A paper mill produces two grades of paper viz., X an...

b. A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y pape

Deviation taken from assumed mean, Deviation Taken from Assumed Mean ...

Deviation Taken from Assumed Mean This methods  is assorted  when the  arithmetic  average  is a  fractional value. Taking  deviation from  fractional value would  be a ver

Operations research, state phases of operations research and and their impo...

state phases of operations research and and their importance in solving problems

Overview of writing research proposal, Overview of Writing Research Proposa...

Overview of Writing Research Proposal It may be written in words of the researcher or as answers following the guidelines provided by the sponsoring organization. A review of

TRANSPOTATION, LIMITS OF TRANSPOTATION PROBLEM

LIMITS OF TRANSPOTATION PROBLEM

Determine capacity of unit, Show simple vapour compression Refrigeration cy...

Show simple vapour compression Refrigeration cycle with showing all the devices and also draw T-sand P-R diagram and illustrate it also. A Bell-Coleman cycle works between 1 bar

Duality, Formulation of convert to primal method to dual in lpp

Formulation of convert to primal method to dual in lpp

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd