Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Types of correlation - correlation & regression analysis, Types of Correlat...

Types of Correlation 1. Positive Correlation : When the values  of two variables move  in the  same direction .e.  when an increase in  the values  of one  variables  is ass

Oral presentation - report writing presentation, Oral Presentation At ...

Oral Presentation At times  oral presentation of the  results of the study is considered effective particularly in case where  policy recommendations are indicated by project

Set of pareto optimal policies, Problem: A policy maker is considering seve...

Problem: A policy maker is considering several policy options that lead to different utility levels of different individuals a) Which Policy is would be optimal according t

Simulation models - operation research model, These models are used to dev...

These models are used to develop a method to evaluate the merit of alternative courses or action by representing with a mathematical model of the problems where various variab

Yates correction for continuity for 2x 2tables , Yates Correction for Cont...

Yates Correction for Continuity for  2x 2Tables If any cell frequency in  2x 2 table isles  than 5thenfor the application of X 2 test it  is pooled with the preceding or suc

Cpm/pert, how to make an attractive assignment

how to make an attractive assignment

the simplex method, In large sized linear programming problems, the ...

In large sized linear programming problems, the solution cannot be obtained by the graphical method and hence a more systematic method has to be developed to find

Characteristics of scientific research, Horton and hunt have given follow...

Horton and hunt have given followings nine characteristics of scientific method: 1. Verifiable evidence i e, factual observations which other observers can see and check

Inherent limitation concerning mathematical expressions, Operation reac Inv...

Operation reac Involves the use of mathematical models, equations and similar other mathematical expressions. Assumptions are always incorporated in the derivation of an equa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd