Carry out resource levelling for equipment resource, Operation Research

Assignment Help:

Teesside Construction is developing a schedule for a major building project to start in 04/01/2011 in Middlesbrough, UK. The project manager has identified major activities of the project, their dependency and resources needed to run each activity. Appendix 1 provides information about the project, which includes project logic (activity links and their relationship - FS, SS, and SF), activity durations, resource allocation and WBS. Appendix 2 provides definition on different activity relationships.

You have been asked to perform the following planning and scheduling processes with the help of Microsoft Project 2007.

A: CPM & WBS

1.  Draw a Gantt-Chart and CPM network for the project. Calculate EST, EFT, LST, LFT and TF based on As Soon as Possible (ASAP) method and identify critical path. Gantt-Chat should show WBS of the project (use A4 or A3 sheet as required) 

2.  Draw manually  the hierarchy of WBS for  the project  (must include  Level 1,  Level 2, Level 3 and Level 4).use MS Visio or other IT software. You can also draw manually and scan it. 

3.  Explain why identification of the critical path is important? Also comment on the changes to the Critical Path, if the project is developed using As Late as Possible (ALAP) method. (max one page)

B: Resources Histograms

1.  Produce resource histograms for  all  the resources  using ASAP method. Identify  and  discuss  the maximum  resources needed  for this project per day and per month.

2.  If As Late as Possible (ALAP) method is used. Will the number of resource identified in question B.1 changes, explain.

C: Resource Smoothing and Resource Levelling

1.  Produce and draw smoothed resource histograms for the skilled labour resources. Do not use automatic smoothening

2.  Carry-out resource levelling  for equipment resource and discuss how activities might be delayed beyond LST to cater for the limits on equipment resources as a result of levelling.

Consider resource pool for equipment resources as 8 units per day. (use A3 sheet for each histogram, max one page for discussion)

3.  Explain and discuss the process of resource levelling. (max one page)

E: Cost Analysis

1.  Calculate the cost of each activity in the project (level 3). Consider the standard cost of a skilled labour as £10/hr, unskilled labour as £15/hr and equipment as £45/hr.

2.  Identify and analyse those activities  which are expensive, for example Structures; Envelope & claddings; Mechanical & electrical services etc. (max one page)

3.  Draw cumulative cost-time curve for each resources and for the project. Comment on the cost profile. (use A4 or A3 sheet as required)


Related Discussions:- Carry out resource levelling for equipment resource

Operation Research Models, Explain the classification of models 1. Classifi...

Explain the classification of models 1. Classification by function or uses 2. Classification by degree of qualification 3. Classification by physical characteristics 4. Classidicat

Application of the chi square test - hypothesis testing, Application of the...

Application of the chi Square Test   The  chi square distribution  has a number of applications are given  below: a.Chi Square test of goodness of fit. b.Chi square te

.sequencing problem, which job should proceed first among the 2 jobs on n ...

which job should proceed first among the 2 jobs on n machines by graphical method

Convenience sampling - sampling decisions , Convenience  Sampling In...

Convenience  Sampling In  convenience  sampling  selection the researcher chooses the  sampling  units on the   basis of convince or  accessibility. It is  called  accidental

Techniques, explain the different techniques as operation research

explain the different techniques as operation research

Title page - report writing presentation, Title  Page Tthe title page...

Title  Page Tthe title page  should  indicate  the topic  on which  the report has been  prepared the  person  or agency who has  prepared it the  person  a agency for whom it

Scope of operations research, Scope of the OR techniques can be derived ...

Scope of the OR techniques can be derived in followings various importance fields: 1. In Agriculture : With the explosion of population and consequent shortage of food O

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd