Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Describe communication skills, From the scenarios, we see that Chris and Er...

From the scenarios, we see that Chris and Erica have different communication styles that could potentially have a negative impact on the business. Suggest at least two strategies t

What are the common barriers to team progress, Question 1: W. E. Deming...

Question 1: W. E. Deming is credited with providing the foundation of Japanese Quality and resurgence as an economic power. Deming is the best known quality expert in the worl

Explain theories of scientific management, • Compare and contrast the theor...

• Compare and contrast the theories of scientific management with that of the human relations management approach. • Determine whether there is one best approach to management,

Explain did jeanne do a good job of communicating, Did Jeanne do a good job...

Did Jeanne do a good job of communicating with her manager?

Game theory, Consider the following parlor game to be played between two pl...

Consider the following parlor game to be played between two players. Each player begins with three chips: one red, one white, and one blue. Each chip can be used only once. To beg

Difference between classical and neo-classicaal theory, Explain d ifferenc...

Explain d ifference between Classical Theory and Neo-Classical Theory of Organisation. Difference between Classical Theory and Neo-Classical Theory of Organisation : The c

What are the disadvantages of the chase demand strategies, What are the dis...

What are the disadvantages of the chase demand strategies? The disadvantages of the chase demand strategies are as illustrated below: a. Over reliance onto flexible staff th

What are the chase demand strategies, What are the Chase demand strategies?...

What are the Chase demand strategies? Chase demand strategies: It is just the opposite of a level capacity strategy. The organisation frequently chases customer demand an

Explain significant differences between x.25 and frame relay, Name two sign...

Name two significant differences between X.25 and frame relay?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd