cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Demerits of absolute standards and relative standards, Contrast the advanta...

Contrast the advantages and disadvantages of absolute standards and relative standards.

What is the ex post redistribution, 1. Two individuals, Vic and Val, are bo...

1. Two individuals, Vic and Val, are both working. Vic faces a 10 percent chance of becoming unemployed for three months and losing $12,000 of income. Val's probability of becoming

Explain develop a time-phased structure, Heather Adams, production manager ...

Heather Adams, production manager for a Colorado exercise equipment, needs to schedule an order for 50 Ultimate Steppers, which are to be shipped in week 8. Subscripts indicate qua

Manufacturing sector - operation strategy, Manufacturing Sector - Operation...

Manufacturing Sector - Operation Strategy 1. Manufacturing has become a global industry with worldwide markets and worldwide suppliers  2. Goods becoming commodity items -

Disadvantages of periodic systems for controlling inventory, What are the d...

What are the disadvantages of periodic systems for controlling inventory? The disadvantages of periodic while compared to continuous systems for controlling inventory are as fo

How measure of overall performance, Cunningham Performance Auto, Inc., mod...

Cunningham Performance Auto, Inc., modifies 375 autos per year. The manager, Peter Cunningham, is interested in obtaining a measure of overall performance. He has asked you to prov

Financial management, how can business cycle be applied in business to day ...

how can business cycle be applied in business to day for example poultry compare broilers

Explain should you raise or lower price, If elasticity is -2, price is $10,...

If elasticity is -2, price is $10, and marginal cost is $8, should you raise or lower price?

Sunshine enterprises, What is the average value of a loyal customer (VLC) a...

What is the average value of a loyal customer (VLC) at Abby''s restaurants (see Chapter 3)? What is the best way to increase revenue given your VLC analysis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd