cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Describe the similarities and differences among, Discuss the similarities a...

Discuss the similarities and differences among the organization, group, and job levels in open systems theory.

Explain a principle within a health care organization, What is a principle ...

What is a principle within a health care organization?

Explain reducing the project duration increases the risk, Take a position o...

Take a position on the following statement from the textbook author: "Reducing the project duration increases the risk of being late." Support your position

Behaviour while a person ethic is somewhat questionable, Which of the follo...

Which of the following statement is correct/1. Deep acting and surface acting are two terms reflecting ways of behaviour when a person ethic is somewhat questionable/2. Deep acting

Learning teaching and assessment strateg, Learning Teaching and Assessment ...

Learning Teaching and Assessment Strategy: Key lectures will be delivered and immediately followed up by group tutorials in which the opportunity to critically reflect, analys

Explain consumer products into brazil, What steps could a company take to a...

What steps could a company take to avoid making product design and marketing mistakes when introducing new consumer products into Brazil?

Patient safety or quality of care is not negatively impacte, Weekly tasks o...

Weekly tasks or assignments (Individual or Group Projects) will be due by Monday and late submissions will be assigned a late penalty in accordance with the late penalty policy fou

Explain why is it important to try to fill in the gaps, When interviewing, ...

When interviewing, why is it important to try to fill in the gaps in a candidate's employment history?

Explain gauge reproducibility and repeatability, Describe gauge reproducibi...

Describe gauge reproducibility and repeatability. How does gauge R and R apply to a six sigma project?

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd