cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain manual order management system, Mr. McNeely currently batches order...

Mr. McNeely currently batches orders for processing under the manual order management system. The orders are batched for daily processing. If Mr. McNeely opts to implement a Web-ba

Explain what changes should be made in the wage, A father decides to put hi...

A father decides to put his two sons to work landscaping. The business involved going to a customer's home and providing landscaping services (cut gras, edge sidewalk, pull weeds i

Explain complete the forward and backward pass, You are creating a customer...

You are creating a customer database for Winston-Salem Warthogs minor league baseball team. Draw a project network given the information below. Complete the forward and backward pa

Explain in your own words an aspect of work, Describe in your own words an...

Describe in your own words an aspect of work/life balance that might be considered a NOD Numbers Only Data and the implications of that data. Describe in your own words that as

Project organisation - operations function, Project Organisation - Operatio...

Project Organisation - Operations Function The project system is a special category at the low-volume end of the spectrum. This entails the execution of many interdependent pa

Explain barriers to advancement opportunities for women, What are some of t...

What are some of the barriers to advancement opportunities for women and minorities in many organizations?

Explain a method that enable you to overcome the difficulty, Document three...

Document three types of cost and determine which is the most difficult to control. Support your response and identify a method(s) that would enable you to overcome the difficulty.

Define how team building interventions help an organization, Discuss how te...

Discuss how team building interventions help an organization. Describe activities that are relevant to individuals, the group and organization relationships.

Describe the importance of reliability in the selection, Define and discuss...

Define and discuss the importance of reliability in the selection process.

Explain compensation, Explain Compensation. Compensation: An employe...

Explain Compensation. Compensation: An employer is not responsible to pay compensation to an employee under the given circumstances/occasions: - (i) While the injury disa

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd