cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain collective bargaining, Explain collective bargaining Collectiv...

Explain collective bargaining Collective Bargaining : Collective Bargaining constitutes the negotiations among the management and the union with the final objective of agreein

Define activity a can be finished and not delay any activity, Using the dat...

Using the data in Table 13-4, determine the latest time activity A can be finished and not delay any activity? Table 13-4 The following represents a project with known activity tim

Order winning and order qualifying criteria, 1. What you think might be the...

1. What you think might be the order winning and order qualifying criteria for: McDonald's, Southwest Airlines and a university?  Answer:

Explain guidelines on discrimination because of religion, Inez Garcia was b...

Inez Garcia was born in Portland, Oregon. Her mother is from Italy and Jewish. Her father is Mexican. Under the Guidelines on Discrimination Because of Religion or National Origin,

Experiments indicate which the change will lower the average, A bank has re...

A bank has recently taken over the billing function of a company. An agreement stipulates that the bank should process 99.2% of the bills within 4 hours. A study of the current pro

Explain career progression of individual, Explain career progression of ind...

Explain career progression of individual and performance appraisal. Performance Appraisal and Individual's Career Progressio: Performance appraisals assist in unearthing

Explain business relationship, Joan has been a manager with Argos for the p...

Joan has been a manager with Argos for the past 15 years. She is known to be aggressive and tough and always gets results. She is demanding of her employees and is often brusque wi

What are the three sequential operations, A manufacturing process consists ...

A manufacturing process consists of three sequential operations. At maximum capacity operation A can output 125 units per hour, Operation B can output 120 units per hour, and Opera

#titlecapacity and location planning, ..explain the relationship of capacit...

..explain the relationship of capacity and location planning

Explain why are unions exploring new collaboration solutions, Why are union...

Why are unions exploring new collaboration solutions in the face of economic/work adversity, and how did Saturn's ambitious Quality of Work Life (QWL) program address these factors

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd