cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain what would happen without a code, In the field of human services, t...

In the field of human services, there are very important ethical codes that should be followed as outlined by the National Association of Social Workers. After viewing the short vi

Describe different roles people play in work groups, Please discuss differe...

Please discuss different roles people play in work groups? Please share the role you predominantly played in project or work groups. Make this a very short answer

Explain production standards place managements, State how production standa...

State how production standards place managements and unions at odds against each other. Why do some unions prefer the right to strike in this matter while others prefer arbitration

Explain project supply and materials budget, Case 11-3 Budget the topic for...

Case 11-3 Budget the topic for this week's assignment is taken from our text (INF336 2010, Mcgraw-Hill) and refers to the City of Granston Case 11-3 at the end of Chapter 11. Using

Influence training a class of persons, What value would it be to know that ...

What value would it be to know that you were going to be training a class of persons between the ages of 20 to 35? Would it influence the approach you would take? How?

Compute the probability that a type1 customer arrives, Consider a queuing s...

Consider a queuing system with 2 types of customers. Type 1 customers arrive according to a Poisson process with a mean rate of 5 per hour. Type 2 customers arrive according to a P

Perseverance and job related knowledge, (Emotional intelligence; a key fact...

(Emotional intelligence; a key factor to success) I want a 20 question survey for this topic, based on these 5 factors Ethic and integrity, Leadership, Perseverance, Job related kn

Current trends in operation management, What is the relationship between ma...

What is the relationship between mass customisation and rapid product development

Explain own personal devices used for work, BYOD and we are reading so much...

BYOD and we are reading so much about BYOD (bring-your-own-device). Are the mobile devices you use for business owned by the company or are they your own personal devices used for

Explain goals should be articulated by teams, Clearly-defined goals are the...

Clearly-defined goals are the essence of great teamwork. Which of the following statements is most true about how goals should be articulated by teams

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd