cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain how important is to find ways to compensate, As a new entry-level m...

As a new entry-level manager, how important is to find ways to compensate for your relative lack of expertise when trying to determine which alternative before you is most likely t

Define conflict between earning profit and being responsible, There is some...

There is sometimes a perceived conflict between earning profit and being responsible. What should CanGo do about adding violent games to their product mix? What impact might this h

Why university refused to pay the card charges on the ground, Type your The...

Type your The University of North is the major state university. The University was preparing for its upcoming re-accreditation, so the University board set aside extra funds to ma

Explain abilities and personalities, 1. Using the terms from this chapter, ...

1. Using the terms from this chapter, how would you characterize the teams at ICU Medical Inc.? What are some advantages and disadvantages of giving teams a lot of autonomy to make

Explain when acquiring an innovative technology externally, Your company, a...

Your company, a large online high school, is planning to implement a new innovative social networking technology for their students. The technology would allow students to get to k

Primary and secondary activities in value chain analysis, What are the prim...

What are the primary or secondary activities in value chain analysis? Primary or secondary activities incur costs, but within combination along with other activities give custo

Explain crafting executive strategy, 1. What evidence do you find in this c...

1. What evidence do you find in this case, either explicitly or implicitly, that indicates that Whole Foods Market has a mission, core values, or is practicing decision-making that

Explain data storage systems in hotels, Which of the following are defined ...

Which of the following are defined as core goods? Chemicals Airlines Data storage systems Hotels None of the above

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd