cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Backward scheduling - scheduling techniques, Backward scheduling - Scheduli...

Backward scheduling - Scheduling Techniques Backward scheduling is another way of scheduling which is based on the as late possible approach with the condition that the jobs

Explain why do resource constraints affect project results, Explain work br...

Explain work breakdown structure. Why do resource constraints affect project results?

Describe customer-contact matrix perspective, Describe a company of your ch...

Describe a company of your choice from the customer-contact matrix perspective. Discuss the operations of the organization from your perspective using the three elements of the cus

Introduction of operations strategy, Introduction of Operations Strategy ...

Introduction of Operations Strategy The term strategy, given in the Collins English Dictionary is, 'the art or science of the planning and conduct of a war; generalship; a lon

Explain elements necessary for the formation of a business, What are the th...

What are the three elements necessary for the formation of a business contract? What are the six defences to formation of a contract? Illustrate your definitions with examples of e

Define potential risks and bottlenecks that occur in project, Briargrove ha...

Briargrove has agreed to your plan. The CLN Team is asking for a refined version of the plan making the corrections based on their recommendations. They are requesting a comprehens

Explain loosening the constraints, Which of the following actions would exp...

Which of the following actions would expand the feasible region of an LP model? A.Loosening the constraints. B.Tightening the constraints. C.Multiplying each constraint by

Explain why employees steal property, Discuss what you think are FOUR (4) r...

Discuss what you think are FOUR (4) reasons why employees steal property (office supplies, petty cash, cheat on travel expense reports, parts/ equipment, embezzle money) from their

Explain what is the college education fee, On the day his son was born, a f...

On the day his son was born, a father decided to establish a fund for his son's college education. The father wants the son to be able to withdraw $4000 from the fund on his 18th b

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd