cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Natural extrinsic reward comparises all the following except, Natural extri...

Natural extrinsic reward include all the following except/1.compliment/2.special Jon/3.asking advice/4.recognition/5. Merit pay increase/ which of these-answer is correct

Explain analyze and evaluate the issues identified, Google's strategy 2010:...

Google's strategy 2010: identify the issues management needs to address. Analyze and evaluate the issues identified based on the information provided in the case. Recommend a set o

Explain characteristics of a mature group, Identify and discuss the four di...

Identify and discuss the four distinguishing characteristics of a mature (well-functioning) group. Give an example of a mature group you have participated in and the application of

Flow Time, You know that our average weekly sales are $2,500 and the flow t...

You know that our average weekly sales are $2,500 and the flow time is half day. Surely with this information, you should have no problem maintaining an inventory level of $400 to

What are disadvantages of using single sourcing strategies, What are the di...

What are the disadvantages of using single sourcing strategies? Disadvantages of using single sourcing strategies: a. Could merely one single supplier into the industry

Variations in Customer Contact - The Service Process Matrix, Variations in ...

Variations in Customer Contact - The Service Process Matrix The classification schemes so far discussed are 'one-dimensional' and do not adequately reflect the great diversity

A firm plans to start production of a new small appliance, A firm plans to ...

A firm plans to begin production of a new small appliance. The manager must decide whether to purchase the motors for the appliance from a vendor at $7 each or to produce them in-h

Explain ethical decision-making framework, In using the Ethical Decision-Ma...

In using the Ethical Decision-Making Framework, a firm should consider the impact of its actions on groups such as its employees, retirees, suppliers, customers, and even the commu

MB0044, What do you understand by “line balancing”? What happens if balance...

What do you understand by “line balancing”? What happens if balance doesn’t exist?

Abc analysis, how to find percentage of annual volume

how to find percentage of annual volume

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd