cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain why employees join unions, Over which of the principle reasons why ...

Over which of the principle reasons why employees join unions does a supervisor have the most direct control?

Explain what implications does that fact have for managers, The resource-ba...

The resource-based model identifies four criteria that firms can use to evaluate whether particular resources and capabilities are core competencies and can, therefore, provide a b

Explain what is the average cost to produce a cake, Alyssas Custom cakes cu...

Alyssas Custom cakes currently sells 4 birthday, 1 wedding and 2 specialty cakes each month for $55, $155, and $105 each, respectively. Alyssas current multifactor productivity rat

Explain external failure costs, Q 1 The probability associated with rejecti...

Q 1 The probability associated with rejecting a high quality lot is denoted in acceptance sampling with the Greek letter alpha. Q 2 Quality control charts usually have a central

Explain product focused, 1. What are the key characteristics that would cla...

1. What are the key characteristics that would classify Wheeled Coach as a repetitive focus process strategy? 2. Let's assume you are a new hire at Wheeled Coach. Your manager a

Assignment, Analyze the strategic role of operations management in terms of...

Analyze the strategic role of operations management in terms of organizational and operational objectives.

Leaders are responsible for achieving desired results, Leaders must be held...

Leaders must be held accountable for achieving desired results. What does this mean to you?

Demerits of continuous or flow production, Demerits of Continuous or Flow P...

Demerits of Continuous or Flow Production The production problem which may arise particularly in high volume flow is that the constant repetition of a short time cycle task may

Benchmarking - performance and productivity measures, Benchmarking - Perfor...

Benchmarking - Performance and Productivity Measures Benchmarking is the practice of comparing business practice and in particular performance between companies. It has become

Determine the optimal order size and total inventory cost, Case Study: ...

Case Study: The ePoint Store stocks paint in its warehouse and sells it online on its Internet Web site. The store stocks several brands of paint; however, its biggest seller i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd