cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain what is the assembly line efficiency, An assembly line with 30 acti...

An assembly line with 30 activities is to be balanced. The total amount of time to complete all 30 activities is 42 minutes. The longest activity takes 2.4 minutes and the shortest

Explain main causes of hr failure in multinational ventures, • Determine th...

• Determine the main reasons why a greater involvement in employees' personal lives, as opposed to non-involvement, is inevitable in many international HRM activities, especially i

Explain what is the maximum queue length, You are to simulate arrivals and ...

You are to simulate arrivals and departures from a fictional airport with a single runway which has a capacity of handling a total 6 aircraft at once (any mix of take-offs and land

Explain continuous inventory system, 1. A reduction in the number of kanban...

1. A reduction in the number of kanbans (given a constant container size) requires A. A reduction in safety stock and/or lead time B. A decrease in safety stock and/or lead t

Explain gather information outside a case analysis, When should you gather ...

When should you gather information outside a case analysis by going to the library or using the Internet and, what should you look for?

Explain how is ace products organized, Steffi Graf has assumed leadership o...

Steffi Graf has assumed leadership of Ace Products after many years of loyal service. Ace Products is an international manufacturer of copiers, printers, and fax machines. Historic

Explain the decision variables for this problem, Problem 4: Comp-Max Comput...

Problem 4: Comp-Max Computers assembles computers and computer equipment. It is about to start production of three new types of computers, called model A, B, and C, respectively. E

Explain patient incentives as well as provider outreach, Please summarize B...

Please summarize Blue Cross Blue Sheild Health Insurance, review members service, new/ current/ upcoming technology, accreditation or certifications and patient incentives as well

Want help creating database using microsoft access, Need help creating data...

Need help creating database using Microsoft access. Please see question. Please create a new database called Automobiles for North East Honda dealership. The database will have

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd