cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

The soccer world cup is promoted, The Soccer World Cup is promoted aggressi...

The Soccer World Cup is promoted aggressively to both companies and fans. This is an example of marketing a(n) a. Event b. Idea c. Service d. Plac

Which amendment has had the most impact throughout history, What are the fa...

What are the facts of the case? What is the key constitutional issue presented? Do you agree or disagree with Angel Raich's postion? Review the amendments to the U.S. Constituti

Economical management of a company, Consider a fast-food restaurant that is...

Consider a fast-food restaurant that is trying to improve its service during the 12:00 - 2:00 lunch period.  Right now the restaurant employs 5 different single-channel queues, but

Explain what is the overall reliability of the call center, The service cen...

The service center for a brokerage company provides three functions to callers: account status, order confirmations, and stock quotes. The reliability was measured for each of thes

Time study - process design, Time Study - Process Design Time study by...

Time Study - Process Design Time study by stopwatch or micro-motion analysis is the original method of work measurement devised by Taylor and his followers, and is still routi

Explain supervise the work of subject matter experts, Which of the followin...

Which of the following role and attributes do NOT describe the core team members on a project? A. Core team members often make project decisions jointly with the project manager

The ability to rapidly as inexpensively switch production, The ability to r...

The ability to rapidly and inexpensively switch production from one product to another enables which of the following

Explain what makes a constraint critical or active, 1) What makes a constra...

1) What makes a constraint critical or active? Explain. 2) Jim has used the theory of constraints to maximize the production of his active constraints and match the production r

Routing procedure, Routing Procedure For a new product or part the rout...

Routing Procedure For a new product or part the routing procedure consists of seven principle steps: 1.The first step is to analyze the product or articles and fabricate int

Explain the clients role in the generating ideas stage, Which best describe...

Which best describes the client's role in the Generating Ideas stage of CPS? a. listens carefully to the ideas generated by the resource group. b. tells the resource group immediat

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd