cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain standard deviation, Under what kinds of circumstances might an orga...

Under what kinds of circumstances might an organization wish to use control limits of 2 standard deviations or even 1 standard deviation? What should it bear in mind when using the

Determine the optimal quantity , Suppose you are overseeing the purchasing ...

Suppose you are overseeing the purchasing of a certain commodity for the following year. The demand for this item is estimated to be 20,000 units/year, and steady throughout. Every

Explain why has walmart tended to improve performance, Why has Walmart tend...

Why has Walmart tended to improve performance while other retail outlets have been suffering financially?

Calculate the non-registered investments, Calculate how much  they will be ...

Calculate how much  they will be  able  to  save  in non-registered investments each year until their retirement. This is Rose and Leonard's first look at a retirement plan. Will t

Compute the total relevant cost associated with the eoq, The local technolo...

The local technology store WiredIn hired you to manage their inventory, which consists of 2 products configurations, type L and type J. Below are the data for the products. The hol

Explain items selected from a population is called, A subset of items selec...

A subset of items selected from a population is called which of the following? Sample Statistic Census Parameter

Explain cause and effect diagram and pareto analysis, What are the advantag...

What are the advantages and disadvantages of using a Cause and Effect diagram and Pareto Analysis in terms of analyzing quality issues? Respond to at least two of your classmates'

Linear programming, Solve the following Linear Programming Problem using Si...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd