cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Plant location, factor relating methods for locating a plant

factor relating methods for locating a plant

Explain logos and ethos and pathos, Explain what Logos, Ethos and Pathos ar...

Explain what Logos, Ethos and Pathos are and their relevance to being understood. Also discuss their preferred order of use. Construct an example following this model. Grading r

Technology which encourages user contributions, Technology which encourages...

Technology which encourages user contributions and interactivity is known as Web 2.0.

Explain dual chains of command can create more problems, Some people argue ...

Some people argue that the matrix structure should be adopted only as a last resort because the dual chains of command can create more problems than they solve. Discuss. Do you agr

What are the advantages of the level capacity strategy, What are the advant...

What are the advantages of the Level capacity strategy? The advantages of the Level capacity strategy: a. Employment of operational resources at all times. b. Efficient p

Explain appropriate technique to develop a forecast, Air travel on Mountain...

Air travel on Mountain Airlines for the past 18 weeks was: Week Passengers Week Passengers 1 406 10 440 2 410 11 446 3 420 12 451 4 415 13 455 5 412 14 464 6 420 15 466 7 424 16 47

Explain basic phases of the innovative process, What are the four basic pha...

What are the four basic phases of the innovative process? What is the importance of the design phase to the overall process?

Explain trend-adjusted exponential smoothing model, After plotting demand f...

After plotting demand for four periods, an emergency room manager has concluded that a trend-adjusted exponential smoothing model is appropriate to predict future demand. The initi

Explain when you find the potential energy of something, When you find the ...

When you find the potential energy of something and its negative what is the significance of the algebraic sign?

Define challenges has the european union consortium faces, Describe what ch...

Describe what challenges has the European Union Consortium faced in the last 2-3 years

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd