cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain subcontractors for a government project want, The government spends...

The government spends a large amount of money each year on contracts. In fact, the federal procurement department spent over $425 billion in the fiscal year 2006 with over $33 mill

Meaning and definition of production management, Meaning and Definition of ...

Meaning and Definition of Production Management Production management is a stream of management that is associated to the production function. Production might be termed to as th

Derive the demand functions of agent for good, 1. An agent has a utility fu...

1. An agent has a utility function over goods 1 and 2 of the form U = x c 1 x d 2 where c is your individual number and d is your minimum number. The agent's income is equal t

Explain how survey have been more useful, 1. Using a cause and effect diagr...

1. Using a cause and effect diagram (Fish-bone chart), Scatter Diagram, flowchart or Statistical Process control chart, analyze the data and present conclusions. 2. How could th

Explain early retirement, Assume you are the project manager for a software...

Assume you are the project manager for a software company and your team is in charge of delivering an update to tax preparation software for the next tax season. The project team h

Explain formal communication chain effective, Most organizations possess so...

Most organizations possess some formal organizational chart showing the established lines of authority and the division of labour. Generally, formal processes of communication are

Energy use in multiplicative seasonal factors, An Electric Company estimate...

An Electric Company estimates its demand trend line (in millions of kilowatt hours) to be D = 76 + 0.55 Q, where Q refers to the sequential quarter number and Q=1 for winter 2000.

Operations management, Operations Management refers to those activities whi...

Operations Management refers to those activities which are more or less directly concerned with the creation and delivery of goods and services. The course is intended to give you

Describe some possible strategic initiatives that sigma, Suggest some possi...

Suggest some possible strategic initiatives that Sigma could pursue to continue its growth.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd