cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Describe how you might use job enlargement, Explains how you might use job ...

Explains how you might use job enlargement, job rotation, and/ or job enrichment to in motivating custodians at Norman dale CC.

Explain project life cycle differ from a product life cycle, I asked the wr...

I asked the wrong question last time. I asked it wrong. How does a project life cycle differ from a product life cycle?

Why negative exposure in media for lack of responsiveness, Trying to create...

Trying to create a public relations campaign for a financial insitutiion that recently received negative exposure in the media for lack of responsiveness to consumers wishing to mo

Productivity, which difference between operation performance and productivi...

which difference between operation performance and productivity?

Explain what types of quality management processes, 1. Compare and contrast...

1. Compare and contrast each of the five organizational structures from your reading (functional, divisional, matrix, team-based, and virtual network). 2. If you were to choose

OPERATTION MANAGEMENT, DISCUSS THE ADVISABILITY OF USING MODULAR ASSEMBLIES...

DISCUSS THE ADVISABILITY OF USING MODULAR ASSEMBLIES IN MANFACTURING

We want to consider some accounting ideas, We need to consider some account...

We need to consider some accounting ideas in order to cover this weeks Objective # 3. So in that regard, for your own business, which method of accounting would you use, the "accru

Depict a sequence diagram, Hertford Post Office Situation: Hertford has a t...

Hertford Post Office Situation: Hertford has a typical small town post office that sells stamps, rents post office boxes, and delivers mail to postal customers. a. Identify possibl

Explain the local publix grocery has five regular lanes, The local Publix G...

The local Publix Grocery has five regular lanes and one express lane (12 items or less only). Based on a sampling study, it takes 11 minutes on the average for a customer to go thr

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd