cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

Explain mcdonald''s prospects of success against competitor, Choose at leas...

Choose at least one of McDonald's competitors and discuss its position relative to McDonald's. Comment on McDonald's prospects of success against this competitor.

forecast of inflation, Aman work at the Bank, to help customers, including...

Aman work at the Bank, to help customers, including retired people, to plan for the future.  Often the value of pensions does not keep up with inflation.  Hence retired people requ

Explain what are the key competencies, What are the key factors that define...

What are the key factors that define success in the search industry? What are the key competencies, capabilities, and resources of successful search engine companies?

Operations function in an organisation - method study, Operations Function ...

Operations Function in an Organisation - Method Study  A procedure that has stood the test of time in the study of work entails six steps (often referred to by the acronym, SR

Why health care cost are out of control in the united states, Discuss the f...

Discuss the following statement: "Health care cost are out of control in the United States, and increasing conflicts between employers and employees are likely as employers try to

How do the stop process enter into the planning process, How does the stop ...

How does the stop process enter into the planning process?

#production and material management, What are the features of dynamic purch...

What are the features of dynamic purchasing? How it''s affects the store keeping and warehousing?

Describe the various stages in team development, Question 1: (a) Descri...

Question 1: (a) Describe the various stages in team development. (b) What are the characteristics of an effective work team? Question 2: (a) Define Leadership. (b)

Find loan payment than the lease payment, Sutton Corporation, which has a z...

Sutton Corporation, which has a zero tax rate due to tax loss carry-forwards, is considering a 5-year, $6,000,000 bank loan to finance service equipment. The loan has an interest r

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd