cALCULATING THE SLACK, es,ef, ls, lf, Operation Management

Assignment Help:

Time (in Days)




Activity

Immediate Predecessor

Optimistic

Most Likely

Pessimistic


A

-

3

6

8


B

-

2

4

4


C

-

1

2

3


D

C

6

7

8


E

B, D

2

4

6


F

A, E

6

10

14


G

A, E

1

2

4


H

F

3

6

9


I

G

10

11

12


J

C

14

16

20


K

H, I

2

8

10









a. Draw the network diagram.

b. Calculate the expected (mean) completion time and its standard deviation for each activity.

c. Calculate the path mean and the path standard deviation for all of the possible paths.

d. Identify the critical path and critical activities.

e. What are the expected project completion time and variance?

f. What is the probability that the project:

i) will be completed within 38 days?

ii) will take more than 35 days to complete?

iii) will take between 35 and 38 days to complete?

Note: use the short method to compute the above probabilities.

g. Within how many days does the project have a 90% probability of completion?

h. Using the expected (mean) completion time, calculate the ES, EF, LS, LF, and slack for each activity.

Related Discussions:- cALCULATING THE SLACK, es,ef, ls, lf

E-commerce, Ask question #Minimum 100 words acceptedDescribe what U-Build-I...

Ask question #Minimum 100 words acceptedDescribe what U-Build-It''s e-business solution will look like for each phase. Specifically, describe the front-end and back-end technical a

Explain administrative issues, Unit IV: At the Bargaining Table Unit V: Gri...

Unit IV: At the Bargaining Table Unit V: Grievances and Arbitration Unit VI: Wage Issues and Economic Supplements Unit VII: Institutional Issues Unit VIII: Administrative Issues

Explain what are the implications of the connection, How critical is Vision...

How critical is Vision to Strategy and in your experience, how well has your organization%u2019s vision (assuming one is in place) been connected to the organizational strategy?

Formulate a mathematical model for the problem, Question: Nostromo Ltd ...

Question: Nostromo Ltd is specialized in electrical installation for space ships. This electrical installation process require a certain amount of drilling and wiring. The dril

Explain hired assuming a 80 percent target utilization rate, The process fo...

The process for renewing a driver's license at the Archer County Courthouse is as follows. First, the clerk fills out the application; then the clerk takes the driver's picture, an

Explain what is the probability that both are successful, DO NOT WORK A com...

DO NOT WORK A company is considering producing two new electronic games designed for the popular Gameboy toy. Based on market data, management believes there is a 60 percent chance

Explain layout need to be adjusted as demand for same goods, Base on the ca...

Base on the case study: Weldon Hand Tools; how would the layout need to be adjusted as demand for this and similar products builds up?

Explain global environmental concepts, Consider an international firm you a...

Consider an international firm you are familiar with, and consider what the firm needs to be concerned about when entering a foreign marketplace. Specifically, in terms of the chap

Managerial decession making history, #question.what is the history of manag...

#question.what is the history of managerial decession making ? .

Find the probability that both service clerks are busy, Discounts Wholesale...

Discounts Wholesale Club has two service desks, one at each entrance of the store. Customers arrive at each service desk at an average of one every six minutes. The service time at

Write Your Message!

Captcha
Free Assignment Quote