Q. Consider a project for which the manpower requirement is 200 PY and the development time is 2 years. calculate the peak manning time.
Ans Software Project cost K=200 PY
Peak development time td =2 year =2 years
Peak manning m0=(k/ td* sqrt(e))=200/2*1.648=164.8 »164 persons
What is Checksheet? Ans) A checksheet is the form used to record data as it is gathered.
how many people work in your hotel?
explain software document.create the necessary documents for employee management system.
describe the types of coupling and cohesion.?
What is cycle stealing DMA operation? Cycle Stealing: In this process, the DMA controller transfers one data word at a time, after which it must return control of the buses to
What is a boundary value analysis? A boundary value analysis is a testing method in which the elements at the edge of the domain are selected and tested. It is a test case desi
Stochastic testing is the similar as "monkey testing", but stochastic testing is a lot more technical sounding name for the similar testing process.
compare and contrast the advantages of verticle and horizontal structural partitioning?
Define in brief about sandwich testing ?
What is Software Software is nothing but a collection of computer programs that are related documents that are indented to give desired features, functionalities and good per
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd