A 160-HP Diesel engine (peak fuel consumption = 0.04-gal/HP-hr) hydraulic excavator operates on a cycle time of 20 seconds during a 50-min/hr. During the filling of the bucket cycle, the excavator's engine is at full power for 5-seconds. The remainder of the time, the engine operates at half-power. The fuel consumed per hour is most nearly:
Solution:
Step 1: Calculate the Time Factor (TF):
Time Factor = 50/60 x 100 = 83.3%
Step 2: Calculate the Engine Factor (EF):
Filling the bucket = (5 / 20) x 1 power = 0.25
Rest of Cycle = (15 / 20) x .50 power = 0.375
TOTAL 0.625
Operating Factor = Time Factor x Engine Factor = 0.625 x 0.833 = 0.520
Step 3: Calculate the Fuel Consumed
Fuel consumed/Hr = 0.52 x 160-HP x 0.04-gal/HP-hr = 3.33-gal/hr
Example of Foundation depth and arrangement: For example, if the maximum discharge of a river is 1000 cu m per sec, and the silt factor is 0.60, the maximum scour depth is :
Q. Explain Flash Butt welding? In this process the ends of two rails are kept at fixed distance apart and a mould (designed to suit the rail section ) is fitted on. The rail en
The process of installation of elastomeric bearing differs in case of precast vis-a-vis cast-in-situ girders. For precast girders, the bearing may be fixed to the underside of the
Define Reactivity - Hazardous Waste - Undergoes violent Change w/o detonating - reacts violently with water - Forms potentially explosive mixtures with water - generat
1. Domes - You are a construction manager in the UAE in charge of a project that involves constructing domes. Discuss briefly, giving examples, a range of different types of dome
Calculate Roller Production An excavating contractor determined through a test strip, that a smooth steel-wheel vibrating roller compactor operating at 3-mph can compact a 6-in
Operation in chain surveying
Pls provide matlab design for transportation engg.
what is wet bituminous macadam
What is Polymer Concrete?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd