Calculate the feed in drilling operation, Mechanical Engineering

Assignment Help:

Calculate the feed in Drilling Operation

Calculate the feed in m/min if a drill makes 200 revolutions per minute and penetrates to a distance of 3 mm per revolution.

Solution

N = 200 rpm

Tool feed/rev. = 3 m/rev.

∴ Feed in m/min = (feed/rev × N) / 1000

= (3 × 200)/ 1000

= 0.6 m/min


Related Discussions:- Calculate the feed in drilling operation

Governors, What do you mean by sensitivity in a governor?

What do you mean by sensitivity in a governor?

Determine the maximum stress - spring , Determine the maximum stress: ...

Determine the maximum stress: A laminated spring of the quarter elliptic type, 0.6 m long, is to give a static deflection of 80 mm under an end load of 2000 N. If the leaf mat

Moments, what is resultant of coplanar non concurrent forces

what is resultant of coplanar non concurrent forces

What are the problems to improve the deficirncies og iges, Problems to impr...

Problems to improve the deficirncies of IGES Within the framework of this interface, an attempt was to be made to improve the deficiencies of IGES, SET and VDAFS which have the

Cooling period of furnace pipe, We shutdown our furnace and always encounte...

We shutdown our furnace and always encountered crack on our piping at the weld joints. I investigated that upon shutdown the furnace cracking, our maintenance immediately remove th

Determine the convection coefficient associated with airflow, An experiment...

An experiment to determine the convection coefficient associated with airflow over the surface of a thick stainless steel casting involves insertion of thermocouples in the casting

Construction and working of locomotive boiler, CONSTRUCTIO N and WORKING: ...

CONSTRUCTIO N and WORKING: The boiler barrel is cylindrical shell and consists of large number of flue tubes. The barrel comprise of a rectangular fire box at one end and a

Tunnels and laying of track, Tunnels: Tunnels become unavoidable for ...

Tunnels: Tunnels become unavoidable for negotiating hills, where detours are costly. The tunnels in rock are not lined, but those in loose strata require a lining of cement c

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd