Bleeding test for grout – an essential requirement, Civil Engineering

Assignment Help:

Q. Bleeding test for grout – an essential requirement?

Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:

(i)  At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.

(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)

(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.


Related Discussions:- Bleeding test for grout – an essential requirement

Uses of cement, Uses of Cement Cement is utilized widely for the constr...

Uses of Cement Cement is utilized widely for the construction of several structures. Some of them are listed below: (i) Cement slurry is utilized for filling cracks in concr

Calculate the percent grade of line, 1. The topography of a local valley is...

1. The topography of a local valley is shown. The horizontal distance between point P and Q is 11,456-ft. The percent grade (%) of line P-Q .     2. Based on the info

LOADS, what are the difference between UDL and UVL?

what are the difference between UDL and UVL?

Determine a cylindrical specimen of saturated clay, A cylindrical specimen ...

A cylindrical specimen of saturated clay, 4.5 cm in diameter, and 9 cm long, is tested in an unconfined compression apparatus. Search the cohesion if the specimen fails at an ax

Designing considerations for dowel bars, Question What are designing c...

Question What are designing considerations for dowel bars in joints of concrete carriageway? Answer Behaviour of dowel bars resembles that of piles in soils subject

Determine the cost of compensation, The soil in a borrow pit has a void rat...

The soil in a borrow pit has a void ratio of 0.90. A fill-in-place volume of 20,000 m 3 is to be constructed with an in-place dry density of 18.84 kN/m 3 . If the owner of borr

Explain a critical path - construction management, Explain a Critical Path ...

Explain a Critical Path The series of activities which determines the earliest possible date of project completion Usually defined as those activities with minimal or

Advance structure engg, need help for assignment that requires strand 7 and...

need help for assignment that requires strand 7 and autocad

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd