Bleeding test for grout – an essential requirement, Civil Engineering

Assignment Help:

Q. Bleeding test for grout – an essential requirement?

Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:

(i)  At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.

(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)

(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.


Related Discussions:- Bleeding test for grout – an essential requirement

Explain the mechanism of compaction by paver, Q. Explain the Mechanism of c...

Q. Explain the Mechanism of compaction by paver? Mechanism of compaction by paver, steel-wheeled roller and pneumatic tire rollers Paver, steel-wheeled roller and pneumat

Determine the types of losses of prestress, Determine the types of losses o...

Determine the types of losses of prestress A loss of prestress will affect the stress distribution on a section of the member. It is therefore necessary to estimate the probabl

Lead products in construction, What are the advantages and disadvantages of...

What are the advantages and disadvantages of lead products in construction? Ans) Disadvantages: -Lead is very toxic; its use can result in pollution of the ground and more signi

Ghgh, Ask quhestion #Minimum 100 words accepted#

Ask quhestion #Minimum 100 words accepted#

Embankment, Describe the various steps in embankment construction.

Describe the various steps in embankment construction.

Calculate the pressure on the other end, Q. 50 liters per sec of water flow...

Q. 50 liters per sec of water flow in a horizontal pipeline which is 200m long and the centerline of which is 3 m above the datum line. The pipe tapers from 30 cm diameter to 20 cm

PRC, what is the bleeding of concrete?

what is the bleeding of concrete?

Design project, The completion of this assignment will entail the design of...

The completion of this assignment will entail the design of the structural fire protection for a simple warehouse building. You will provide a separate engineering calculation and

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd