Q. Bleeding test for grout – an essential requirement?
Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:
(i) At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.
(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)
(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.
# ???? ..
Q. Explain Hot weather Patrolling ? Hot weather Patrolling is done for LWR and CWR tracks when the rail temperature reaches td + 20 0 C and above and td + 14 0 C for Central
Q. Asphalt mix design - durability vs. stability? The main aim of asphalt mix design is to achieve a mix with economical blending of aggregates with asphalt to achieve the foll
If you have never used an ice dam melting sock on your roof before, you will search that they give an inexpensive method for removing roof ice dams and improving your home's heatin
A cylindrical specimen of a saturated soil fails under an axial stress 150 kN/m 2 in an unconfined compression test. The failure plane makes an angle of 52° with the horizontal.
Q. For what capacity would you design a sanitary branch sewer to serve a section having a population of 12500 persons with a rate of supply of 135 Liters. Ans.- Average flow
A square pile group of 9 piles of 25 cm diameter is arranged with a pile spacing of 1m. The length of the piles is 9 m. Unit cohesion of the clay is 75 kN/m 2 . Neglecting beari
A simply-supported beam (AB) with an overhang (BC) is illustrated in Figure 1(a), with the cross-sectional details given in Figure 1(b). The dead load comprises self weight only; f
The Table provides the cross-sectional areas to be excavated for the roadway construction. The volume of earth to be excavated (yd 3 ) between section 83+65.6 and 85+98.5 is most n
layout of port
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd