Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:

(i)  At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.

(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)

(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.


Related Discussions:- Bleeding test for grout – an essential requirement

Dam, how can i prepare a project on dam

how can i prepare a project on dam

What is load carrying capacity of a pile, Q-  What are loads and forces ta...

Q-  What are loads and forces taken into account for designing a pile and what is load carrying capacity of a pile. Ans. For designing a pile the following loads and force ar

Explain the installation of shock transmission unit, Explain the Installati...

Explain the Installation of Shock Transmission Unit? It is not always necessary to install STUs while a structure is under construction but the holding down anchor bolts and th

Determine the normal and shear stress elements, Determine the normal and sh...

Determine the normal and shear stress elements: The state of stress at a point is given through the stress components σ x = 70 MPa, σ y = 10 MPa, and τ xy = - 40 MPa. Using

Elastic curve, elastic curve of a simply supported beam with triangular loa...

elastic curve of a simply supported beam with triangular load

Beams, how to convert uniformly varying loads to point loads

how to convert uniformly varying loads to point loads

Surveying, readings of longitudinal and cross section levelling

readings of longitudinal and cross section levelling

Define the reservoirs - hydraulic system, Define the Reservoirs - Hydraulic...

Define the Reservoirs - Hydraulic System Typically designed for multiple functions - clean water supply, creating recreational opportunities and flood protection. Reservoirs ar

Phase, Each physical homogeneous type (solid, liquid orvapour) is a phase. ...

Each physical homogeneous type (solid, liquid orvapour) is a phase. Two or three phases may coexist.  e.g. Ice and water at 0 o C.  Mixtures of gases (e.g. Air) can only be

Design the transverse reinforcement, Figures (a) and (b) respectively give ...

Figures (a) and (b) respectively give details of a simply-supported bridge beam and its (idealised) cross-section. In addition to the dead load of 25 kN/m (including self weight),

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd