Bleeding test for grout – an essential requirement, Civil Engineering

Assignment Help:

Q. Bleeding test for grout – an essential requirement?

Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:

(i)  At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.

(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)

(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.


Related Discussions:- Bleeding test for grout – an essential requirement

Heating season duration , Change the model to take into account the variati...

Change the model to take into account the variation in outdoor temperature for a "typical" day in the heating season based on the heat loss by the fabric and the heating of incomin

Laplace transform, Using Laplace transfom, the following differential equat...

Using Laplace transfom, the following differential equation d y dy dt reduces to the algebraic equation of the form Resolve y(s) into partial fractions

Semi elliptical arch, how can i build a semi-elliptical arch out of bricks?...

how can i build a semi-elliptical arch out of bricks?

Structural Engineering, I want to get help in my Steel Structure Project Th...

I want to get help in my Steel Structure Project Thanks

Digit of cells for concrete box girder bridges, Question How does an engine...

Question How does an engineer determine digit of cells for concrete box girder bridges ? Answer If depth of a box girder bridge exceeds 1/6 or 1/5 of bridge width, then it is o

Of obstacles to both chaining and ranging.., #questof obstacles to both cha...

#questof obstacles to both chaining and ranging. ion..

Explain the operating point - pumping system, Explain the Operating Point -...

Explain the Operating Point - Pumping System Intersection of the characteristic curve and the system curve. This is the head and flow rate data for the pump "operation". The op

Compute the stresses at top and bottom fibres, Compute the stresses at top ...

Compute the stresses at top and bottom fibres in a simply supported pre-stressed concrete beam with a rectangular cross section, 200 mm wide and 400 mm deep at sections A-A, B-B an

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd