Bleeding test for grout – an essential requirement, Civil Engineering

Assignment Help:

Q. Bleeding test for grout – an essential requirement?

Bleeding is a form of segregation in that a layer of water migrates to surface of the grout at the time of the initial stage of cement hydration process. Afterward some of the floating water is re-absorbed into the grout because of further hydration reactions. Even without problem of bleeding, there is a total reduction of volume of grout after hydration action when compared with total initial individual volume of cement and reacted water. Bleeding tests must be carried out for grout due to the below reasons:

(i)  At the time of bleeding, up flow of water from grout mixture leads to formation of channel paths inside the grout mix. These channels behave as potential paths for aggressive materials to pass through as these channels will not be closed during further hydration of the grout.

(ii) Loss in volume by bleeding generates voids inside the grout mix that affects the properties and performance of the grout. Furthermore it increases the chance of corrosion of steel elements protected by the grout. (Such as tendons)

(iii)In bleeding test, there is a typical requirement of total re-absorption of water after 24 hours of grout mixing since for some cold countries, this layer of water can cause severe freezing problem leading to frost damage.


Related Discussions:- Bleeding test for grout – an essential requirement

Compass survey, define compass survey and mention its objectives

define compass survey and mention its objectives

Determine condition of activity in the network flow diagram, Determine the ...

Determine the condition of each activity in the network flow diagram shown below   Ans: a. Activity C can be started only after the completion of activities A and

What is oil interceptors, Q. What is Oil interceptors ? Oils and Grease...

Q. What is Oil interceptors ? Oils and Grease are usually found in stormwater runoff from catchments. They come from spillage and leakage of fuels, lubricants, Vehicle coolants

Cantilever beam, The problem in the link below. ">http://www.expertsmind....

The problem in the link below. ">http://www.expertsmind.com/questions/plot-vertical-displacement-cantilever-beam-30134382.aspx#

Paint, painting wood work

painting wood work

Stress design method, You have been selected to assist the structural engin...

You have been selected to assist the structural engineer for a bridge replacement project.  Your task is to design the size of the footing for an interior bridge pier, based on the

What is the density index of the natural soil, A sand at a borrow pit is de...

A sand at a borrow pit is determined to have an  in-situ dry unit weight of 18.4 kN/m 3 . Laboratory tests indicate the maximum and  minimum unit weight values of 19.6 kN/m 3 and

Define sounding or sensing devices, Define Sounding or Sensing Devices? ...

Define Sounding or Sensing Devices? Sounding devices are effective in checking scour in the streambed adjacent to a bridge. Although sounding/sensing devices can be used indepe

Cross sectional area to be excavate for roadway construction, The Table pro...

The Table provides the cross-sectional areas to be excavated for the roadway construction. The volume of earth to be excavated (yd 3 ) between section 83+65.6 and 85+98.5 is most n

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd