Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Types of correlation - correlation & regression analysis, Types of Correlat...

Types of Correlation 1. Positive Correlation : When the values  of two variables move  in the  same direction .e.  when an increase in  the values  of one  variables  is ass

Linear programing, A factory employs unskilled workers earning $135 per wee...

A factory employs unskilled workers earning $135 per week and skilled workers earning $270 per week. It is required to keep the weekly age bill below $24,300. The machine requires

LPP., A constraints in an LPP restricts? (Value of objective function,Value...

A constraints in an LPP restricts? (Value of objective function,Value of decision variable,Use of available resources, uncertainty of optimum value) please help me to find out righ

Linear programming problem, #Solve the following Linear Programming Problem...

#Solve the following Linear Programming Problem using Simplex method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Principles of report writing, Principles of Report Writing Reports wri...

Principles of Report Writing Reports writing  may  involve the followings principles . a. Easy to Follow : The body of the  report should  be written in a self evident and

Help me please , This year Jan Rich, who is ranked number one in women''s s...

This year Jan Rich, who is ranked number one in women''s singles in tennis, and Marie Wacker, who is ranked number three, will play 4 times. If Marie can beat Jan 3 times, she will

Big M method, Maximize p = (3)x + 2y subject to 2x + y 3x + 4y >= 12

Maximize p = (3)x + 2y subject to 2x + y 3x + 4y >= 12

SMU 2nd Semester, A paper mill produces two grades of paper viz., X and Y. ...

A paper mill produces two grades of paper viz., X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper i

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd