Answering lp problems, Operation Research

Assignment Help:

ABC Company manufactures both interior and exterior paints from 2 raw materials M1 and M2. The following table gives basic data of problem.

 

 

Exterior paint

Interior paint

Availability

N1

6

4

24

N2

1

2

6

Profit per ton

5

4

 

A market survey signifies that every day demand for interior paint cannot surpass that for exterior paint by more than 1 ton. Also maximum routine demand for interior paint is 2 tons. Develop LPP to find out the top product mix of interior and exterior paints that maximizes the daily total gain (profit).

Answer

Assume

 x1 - number of units of exterior paint

      x2 - number of units of interior paint

 

Maximize Z = 5x1 + 4x2         

Subject to

6x1 + 4x2 ≤ 24

x1 + 2x2 ≤ 6

x2 - x1≤ 1

x2≤ 2

                 x1≥0, x2 ≥0

 

b) The highest routine demand for exterior paint is almost 2.5 tons

                 x1≤ 2.5

c) Routine demand for interior paint is as a minimum 2 tons

                 x2 ≥ 2

d) Routine demand for interior paint is accurately 1 ton more than that for exterior paint.

                 x2 > x1 + 1

 

 

 


Related Discussions:- Answering lp problems

Solve the following linear programming graphically, Problem based on graphi...

Problem based on graphical solution of a given LPP when feasible region is bounded. 1.    Solve the following linear programming graphically; Maximize and minimize z = 60x+

LINEAR PROGRAMMING, A DRUG MANUFACTURER produces 2 products X1 and X2.X1 ne...

A DRUG MANUFACTURER produces 2 products X1 and X2.X1 needs 2 hours on machine A AND 2 HOURS ON MACHINE B.X2 needs 3 hours on machine A and 1 hour on machine B.If machine A can run

Distribution methods, 1: explain vogel''s approximation method? 2: explain ...

1: explain vogel''s approximation method? 2: explain optimality test?

Purchasing, need of detailed information about the topic

need of detailed information about the topic

Linear programming, A paper mill produces two grades of paper viz X and Y. ...

A paper mill produces two grades of paper viz X and Y. Because of raw material restrictions, it cannot produce more than 400 tons of grade X paper and 300 tons of grade Y paper in

Solve by simplex method, Solve by simplex method Maximize Z = 5...

Solve by simplex method Maximize Z = 5x 1 + 3x 2 Subject to 3x 1 + 5x 2 ≤ 15 5x 1 + 2x 2 ≤ 10 &         x 1 ≥ 0, x 2  ≥ 0 [Ans. Max Z = 235/19

Methods of calculation of standard deviation , Methods  of calculation of ...

Methods  of calculation of standard deviation a. Calculation of Standard  Deviation  - Individual Series: There  are two methods of calculating standard  deviation in an ind

Question, Solve the following Linear Programming Problem using Simple metho...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Linear Programming Problem using Simple method, Solve the following Linear ...

Solve the following Linear Programming Problem using Simple method. Maximize Z= 3x1 + 2X2 Subject to the constraints: X1+ X2 = 4 X1 - X2 = 2 X1, X2 = 0

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd