Produce as individuals a single tab Excel spreadsheet which shows a rough initial design for a water treatment plant taking 15MLD of water with 100 mg/l SS from a lake at 750mAOD, passing it through settlement tanks on to pressure sand filters, and from there into a chlorine contact tank to TR60 of 30 mins HRT and 1m water depth at 575mAOD. Distance from Lake to CCT is 1500m. Fall on ground is constant along this 1500m.
Numbers and diameters for circular settlement tanks and sand filters, external and internal dimensions of CCT, theoretical and actual pipe diameters sizes will be needed to be calculated as a minimum.
Rules of thumb for design:

Surface loading settlement tanks 1m/h

HRT settlement tanks 2h

Max diameter settlement tanks 30m

Surface loading sand filters 15m/h

Sand filter depth 2m

Max diameter sand filters 3m

Static head required for sand filter operation 10m

Superficial velocity pipework 1.5m/s

Related Discussions:- answer me

Define edm machine under varying cutting condition, EDM Machine under varyi...

EDM Machine under varying Cutting Condition a) All the experiments have been conducted on a Z numerically controlled (NC) oil die- sinking EDM Machine. b) The EDM Machine is

Theory of machines, What'' is balancing and vibration in machines Need of ...

What'' is balancing and vibration in machines Need of balancing? Causes of vibration and their harmful effects and remedies?

Fluid mechanics and machinery diploma .., Prove that the force exerted by a...

Prove that the force exerted by a jet of water on a semicircular plate in the direction of the jet when the jet strikes at the centre of the semicircular plate is two times the for

Arm programming, In order to get your first experience of ARM programming, ...

In order to get your first experience of ARM programming, this way you are familiar with the problem itself, its design, its flow of execution and you can use your own C code as ps

Structural design, The Contractor is responsible for obtaining all drawings...

The Contractor is responsible for obtaining all drawings, standards and specifications referred to in the bid documents and to request as needed additional or missing reference dat

Determine the greatest load carried by the composite springs, Determine the...

Determine the greatest load carried by the composite springs: A composite spring contain two close-coiled helical spring associated in series, each spring has 10 coils at a me

Registering small scale unit of entrepreneurship development, Registering a...

Registering a Small Scale Unit: Small Scale and ancillary units (i.e. undertaking with investment in plant and machinery of less than Rs. 6.0 million and Rs. 7.5 million respectiv

Competency statements , COMPETENCY STATEMENT:  In this programme, every le...

COMPETENCY STATEMENT:  In this programme, every learner shall be assessed on a continuous basis for his/her knowledge and skills during the programme duration. Learners' competenc

Welding variables-welding current, WELDING VARIABLES The following major ...

WELDING VARIABLES The following major process variable play an important role in shaping the weld bead and the resultant weld metal in submerged arc welding: a. Welding cu

Computer control system in flexible manufacturing system, Computers control...

Computers control system in flexible manufacturing system

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd