Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Convert reduced bearings into whole circle bearings, Example: Convert t...

Example: Convert the following reduced bearings into whole circle bearings: (i) N 65° E                           (ii) S 43° 15′ E (iii) S 52° 30′ W           (iv)

Determine the stage of cracking moment of pre-stress, Determine the stage o...

Determine the stage of Cracking moment of pre-stress  At the stage of transfer of pre-stress in the pre-stressed beam element, only the pre-stressing force and the self weight

Cleaning and greasing of steel sliding bearings, Cleaning and greasing of s...

Cleaning and greasing of steel sliding bearings : Following equipments are required for greasing of steel sliding bearings: 1. Jacks (50 ton capacity) - 2 nos. 2. Hard wo

What is meaning of washers while using bolts, Question What is meaning ...

Question What is meaning of washers while using bolts? Answer Purpose of installing washers in a classic bolting system is to distribute loads under bolt heads and nu

Concrete technology, material for formwork and their specifications

material for formwork and their specifications

What is main purpose of swabbing, Question After construction of waterm...

Question After construction of watermain, earlier to hydrostatic pressure test , swabbing is approved out. What is main purpose of swabbing ? Answer Pipelines ha

Test leakage of constructed gravity pipelines, Question Have air test o...

Question Have air test or water tests be selected to test leakage of constructed gravity pipelines ? Answer For gravity pipes, air tests are carried out after completi

Flow, what is maximum flood level

what is maximum flood level

Cumulative error, diffrence between cumilative compensative error

diffrence between cumilative compensative error

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd