Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

door shutters, what is the difference between paneled and glazed shutte

what is the difference between paneled and glazed shutter

Define the term- erection stresses, Define the term- erection stresses ...

Define the term- erection stresses The creep loss due to live load stress, erection stresses and other stresses of short duration may be ignored. The loss of prestress due to

Bulking of sand, what is the permissible limit of sand

what is the permissible limit of sand

Define influence lines, Define Influence lines Provides information...

Define Influence lines Provides information at a single point on a beam Can be used for: - Reactions - Internal shear forces - Internal moment Indicate

Grouting in segmental linings in tunnels, Q. Grouting in segmental linings ...

Q. Grouting in segmental linings in tunnels? Grouting is typically carried out under pressure in segmental linings at the time of tunnel construction due to the below reasons:

CONCRETE BATCHING, DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

DOES A GAUGE BOX OF THE SIZE LIKE 50,40,30 MM EXISTS?

Illustrate shaft grouting for friction barrettes, Q. Illustrate Shaft grout...

Q. Illustrate Shaft grouting for friction barrettes? For the construction of friction barrettes, some grout pipes are designed at periphery of the barrettes. Within a short dur

Sampling distribution and approximations of distributions, Sampling Distrib...

Sampling Distribution And Approximations Of Distributions: 1) Learnt three approaches for deriving the probability distributions of functions of one or more random variables v

Explain equations for a triangular (v-notch weir), Explain Equations for a ...

Explain Equations for a triangular (V-notch weir) Used for small flow rates. C 2 is a coefficient which varies from 0.58 to 0.61 depending upon the notch angle.  Q = C

coursework (commercial management), Ask que1. Identify the risks involved ...

Ask que1. Identify the risks involved in this project related to cost in the perspective of the customer and analyse the probability of acceptance of such a project by customers. 2

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd