Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Define cyclic force transfer test of shock transmission unit, Define Cyclic...

Define Cyclic Force Transfer Test of Shock Transmission Unit? This test is specified to prove that the STU would function as intended during a seismic event. The STU shall be t

Pre-stressing work, Under which situation shall engineers use jacking in ag...

Under which situation shall engineers use jacking in agreement end only and from both ends in pre-stressing work?

Define the approach velocity, Define the Approach Velocity Typical prob...

Define the Approach Velocity Typical problems have negligible approach velocity.  v 1 = Q/A, where A = the cross-sectional area of flow in the channel. The value is not the ve

Linear algebra concept, Scenario: You are working for a structural engineer...

Scenario: You are working for a structural engineering firm and you have been assigned the task of computing the code checks on a new structural design. Though another commercial p

Site plan, can I have some help with a site plan. I want it on autocad, I h...

can I have some help with a site plan. I want it on autocad, I have all the dimmension

Report, report on lintels and arches

report on lintels and arches

Importance of geotextiles and sand in reclamation works, Question What ...

Question What is main importance of geotextiles and sand in reclamation works? Answer For geotextiles used in recovery, they serve mainly subsequent two purposes

Sewer manhole, minimun difference in level of inlet and oulet pipe level in...

minimun difference in level of inlet and oulet pipe level invert in manhole

Segmentally lined and sprayed concrete linings tunnels, Q. Segmentally line...

Q. Segmentally lined and Sprayed Concrete Linings tunnels? The fundamental difference between segmentally lined tunnels and SCL tunnels is that the sprayed concrete in SCL tunn

Determine the bar sizes and spacing, Referring to problem 1, in order to me...

Referring to problem 1, in order to meet a 1-hour fire code rating the slab thickness must be at least 4.00. Based on the information given in problem 1 and with a slab thickness o

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd