Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Remedial measures for problems in turbid water - reflection, Remedial measu...

Remedial measures for Problems in Turbid Water - Reflection? The problem of reflection can be minimised by carefully placing the flash away from the axis of the camera and at a

Pre-stress girder/ I Beam design and Triaxial lab report, I need urgent su...

I need urgent support in my assignment and also my UU triaxial lab report. thanks Maryam

Explain coagulation - Surface Water, Explain Coagulation Surface wa...

Explain Coagulation Surface waters must be treated to remove turbidity, color and bacteria The traditional sand filtration is not sufficient in removing bacteria, viru

Comparing speed, Question Comparing speed of "Formwork exceeding 300mm wide...

Question Comparing speed of "Formwork exceeding 300mm wide, horizontal and at any inclination up to and including 5o to horizontal" with speed of "Formwork exceeding 300mm wide, at

What is a projection line, Projection line is the way, in which the earth i...

Projection line is the way, in which the earth is made known on a flat piece of paper.

Environmental engineering., Solve the following problems and show all steps...

Solve the following problems and show all steps and calculations clearly: 1. A water treatment plant uses a dual media filter. The two media used are: a) Anthracite coal with ef

Bearings, what is the difference between whole circle bearing and reduced b...

what is the difference between whole circle bearing and reduced bearing?

Classification of timber based on availability:, Classification Based on Av...

Classification Based on Availability: Forest departments categorized timbers based on the availability as X=Most common. 1415 m 3 or more per year Y=Common. 355 m 3 to 1415

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd