Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Explain about the pot bearing - bridge bearing, Explain about the Pot Beari...

Explain about the Pot Bearing? POT bearing was developed in 1959 as an alternative to heavy steel sliding bearings. It consists of a circular non-reinforced rubber-pad fully en

Explain the design of graded filter, Q. Explain the design of graded filter...

Q. Explain the design of graded filter? Use of graded filter has been traditionally used below the revetment and protection works. The material used in the granular / graded fi

Dense Bituminous Macadam, What is DBM?Why use DBM where other binder course...

What is DBM?Why use DBM where other binder courses are available?What is composition and advantages of using DBM?

Determine the soil shrinkage, Soil at a borrow area has a total unit weight...

Soil at a borrow area has a total unit weight of 120-PCF and a water content of 15 percent.  The soil from the borrow area will be used as structural fill and compacted to an avera

Surveying, tracing paper method for solving three point problem?

tracing paper method for solving three point problem?

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

Main purpose of conducting load test for piling works, Question What is...

Question What is main purpose of conducting load test for piling works ? Answer Pile load test gives information on ultimate bearing ability but not settlement be

Structural analysis, steps to analysis a portal frame with sway condition

steps to analysis a portal frame with sway condition

Define the thiem equations for confined aquifers, Define the Thiem Equation...

Define the Thiem Equations for Confined Aquifers   Using natural log:  Q = 2pKm(h 2 - h 1 )/ln(r 2 /r 1 )   Using log 10 :    Q = 2Km(h 2 - h 1 )/((1055)log(r 2 /r 1 ))

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd