A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Energy equation, find the pressure head at 2-2 if the rate of flow in pipe ...

find the pressure head at 2-2 if the rate of flow in pipe is 0.36m^3/s

Load transfer mechanism, Question What is load transfer mechanism for p...

Question What is load transfer mechanism for paving blocks in pedestrian footway? Answer In Hong Kong, footway is as a rule designed with paving slabs or interlocking b

Plot vertical displacement - cantilever beam, 1. The cantilever beam-like s...

1. The cantilever beam-like structure  shown below is modeled  using  a 2 x 10 mesh of rectangular four-node plane stress elements of equal size. Do the following and compare with

Fluid mechanics, why converjent angle is greater than disconverjent angle

why converjent angle is greater than disconverjent angle

#title, how to convewrt wcb into rcb

how to convewrt wcb into rcb

Define the cost per square foot of contact area, Define the Cost per Square...

Define the Cost per Square Foot of Contact Area The cost of concrete formwork is influenced by three factors: 1. Initial cost or fabrication cost that contains the cost of t

Bitumen, unit of kinematic viscosity

unit of kinematic viscosity

Spalling reinforcement for pre stressing works, Spalling reinforcement for ...

Spalling reinforcement for pre stressing works in anchor blocks Reinforcement of anchor blocks in prestressing works usuallycomprises equilibrium reinforcement, bursting reinfo

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd