Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Bending moments& shear force, calculate bending &shear force of 16kn/m and ...

calculate bending &shear force of 16kn/m and draw the shear force and bending moment diagrams

What do by diaphragm wall, Q. What do by Diaphragm wall? For the constr...

Q. What do by Diaphragm wall? For the construction of diaphragm walls adjacent to buildings, former experience showed that excess slurry head above groundwater level had to be

Moisture content, What is moisture content for road work

What is moisture content for road work

Water treatment, The transmission main from the well field to the community...

The transmission main from the well field to the community is 2500 ft, the velocity of flow at peak pumping capacity is 3.5 fps, water temperature is 10oC, and pH is 7.5. If free c

Define the finish-to-start dependency, Sheet rock cannot be installed in th...

Sheet rock cannot be installed in the new house you are building until a building inspector approves the plumbing, electrical, HVAC, and insulation.  This is an example of:

Chain survey, Instruments used in chain survey

Instruments used in chain survey

#titl, Two readings ie 1.64m and 0.73m were taken during leveling procedure...

Two readings ie 1.64m and 0.73m were taken during leveling procedure to define the slope of a centerline of a bridge at points A and B. If distance AB=50 m, find the slope of line

Earth work in high embankments, Q. Earth work in high embankments? (a) ...

Q. Earth work in high embankments? (a) Borrow pits must not be dug close to telegraph poles, electric poles, level crossings, bridges a culverts, or within 800 meters of the bo

Explain plate jig, Explain Plate jig 1) The major parts of this jig is ...

Explain Plate jig 1) The major parts of this jig is plate from which it takes its name other necessary parts and drill bush and locating pins. 2) Plate jigs are general for

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd