Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Application of embankment condition for drainage design, Q. Application of ...

Q. Application of embankment condition for drainage design? In considering loads on buried pipeline, there are generally two scenarios: narrow trench condition and embankment (

Mollusca, what is the taxonomy of phylum molluska

what is the taxonomy of phylum molluska

State the term directly below the edge of the footing, The load from a cont...

The load from a continuous footing of 1.8 metres width, which may be considered to be a strip load of considerable length, is 180 kN/m 2 . Verify the maximum principal stress at 1.

Degree, what classes do you have to take and what are some school options?

what classes do you have to take and what are some school options?

Concrete mix design, Concrete Mix Design: Concrete mix design is done...

Concrete Mix Design: Concrete mix design is done in a laboratory to achieve the desired strength and workability. The mix design is done to achieve strength slightly higher t

Passenger conveyors, Passenger Conveyors: Passenger conveyors are used...

Passenger Conveyors: Passenger conveyors are used at locations where a large concentration of passengers has to be moved from one place to another. Escalators are used to conv

Water absorption test - tests on stones, Water Absorption Test: In t...

Water Absorption Test: In this test cube specimen weighing approximate 50 grams are prepared and the test is carried out in the steps following: 1.    Note down the weigh

Fly levelling, what is fly levelling? when it is carried out ?

what is fly levelling? when it is carried out ?

Dielectric materials are what kind of materials, Dielectric materials are w...

Dielectric materials are what kind of materials ? Answer: It is  insulating materials.

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd