Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Evaluate the principal stresses and principal planes, Evaluate the principa...

Evaluate the principal stresses and principal planes: The state of stress at a point in a loaded solid is prescribed on two faces of an element whose shape is a triangular pri

Traditional granular sub-base, Question For rigid pavement, what is rec...

Question For rigid pavement, what is recompense of using lean concrete sub-base instead of traditional granular sub-base? Answer There are some shortcomings of using

State average increase of pressure in the clay stratum, A building was to b...

A building was to be constructed on a clay stratum. Preliminary analysis showed a settlement of 60 mm in 6 years and an ultimate settlement of 250 mm. The average enhance of pressu

Calculate the deposited amount - construction management, An engineer depos...

An engineer deposits an "X" amount every 6 months for 3 years so that she'll have $10,000 at the end of this period. The interest rate is 5% per year which is rebalanced every 6-mo

Determine about the pre-stressed concrete beam, Determine about the pre-str...

Determine about the pre-stressed concrete beam A pre-stressed concrete beam has a width of 200 mm and an overall depth of 400 mm. The permissible stresses in tension and compre

Shear moment diagram, how to draw shear moment diagram for cantileaver beam...

how to draw shear moment diagram for cantileaver beam

Explain dissolved impurities in water, Q. Explain Dissolved Impurities in w...

Q. Explain Dissolved Impurities in water? The impurities which are caused by the action of water and water forming Acids with organic matter and carbon dio

Average heating season outside temperature, Produce a manual determination ...

Produce a manual determination to determine the instantaneous rate of heat loss (kW) through one part of the fabric (eg roof, glazed area, wall) based on an internal building desig

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd