Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Building, individual wall methods benefits?

individual wall methods benefits?

Time to remove formwork to cater for early thermal movement, Q. Time to rem...

Q. Time to remove formwork to cater for early thermal movement? Let's take a circular column as an illustration to explain effect of internal restraint to thick sections.  W

The material that have lowest resistivity is , The material that have lowes...

The material that have lowest resistivity is Answer: Silver is the material

Major considerations in selecting marine plants, Question What are majo...

Question What are major considerations in selecting marine plants and land plants for fitting of band drains? Answer For fitting of band drains by marine plants,

What is bore hole, What is Bore Hole In exploration of  area of  limit...

What is Bore Hole In exploration of  area of  limited extent  the borings should preferably be located near the comers of  the area. A minimum of three holes should be made un

Determine difference between stations in feet and in station, The survey ha...

The survey has identified the beginning and ending points along an urban arterial highway that require new sidewalks. The first station is located at 5+88 and the second station is

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd