Analysis of the two stage construction, Civil Engineering

Assignment Help:

A County is planning to build a new roadway connector in the rapidly developing area of the county. The road can be built at a reduced capacity now for $30 million and can be widened 15 years later for an additional $20 million. An alternative is to construct the full capacity connector now for $40 million. Both alternatives would provide the needed capacity for the 25-year analysis period. Maintenance cost differences are small and may be ignored. At 6% interest, which alternative should be selected:

a. Two stage construction with a $1,700,000 savings

b. Single stage construction with a savings of $1,700,000

c. Two stage construction with a $300,000 savings

d. Single stage construction with a savings of $300,000

Solution: Analysis of the two-stage construction:

PW of cost = $30 million + $20 million (P/F, 6%, 15)

= $30 million + $8.3 million

= $38.3 million

Analysis of the single-stage construction: From the information provided:

PW of cost = $40 million

Two-stage construction alternative is preferred with a $1,700,000 savings.


Related Discussions:- Analysis of the two stage construction

Piers and piles, what is the difference between piers and piles?

what is the difference between piers and piles?

WBM Road, if the WBM Road is constructed with 80mm , 40mm metal what will b...

if the WBM Road is constructed with 80mm , 40mm metal what will be the depreciation factor per year, how much thickness of the layer will be reduced per year due to trafic and rai

Rb slab, #questionshow me picture..

#questionshow me picture..

Full bore flow in drainage design, Q. Full bore flow in drainage design? ...

Q. Full bore flow in drainage design? In the design of gravity drainage pipes, full bore flow capacity is usually adopted to check against design runoff. Though one should note

State the effect of the induction of the pre-stresses, State the effect of...

State the effect of the induction of  the pre-stresses The net effect of the induction of  the pre-stresses shall be to decrease the tensile stresses (produced due to the exte

Concreat, m25 mix water cement ratio

m25 mix water cement ratio

Explain statically indeterminate structures, Explain Statically Indetermina...

Explain Statically Indeterminate Structures  Fall into two categories:   1.  Beam problems with additional supports/restraints 2.  Axial bar members subjected

Formation of pedestrian level winds around buildings, Q. Formation of pedes...

Q. Formation of pedestrian level winds around buildings? When a building blocks the wind blowing across it, part of the wind will escape over the top of the building. Some will

Steel and timber structures, design a tension member subjected to a pull of...

design a tension member subjected to a pull of 300KN using a channel section. the length of a joint available is only 400mm.check the condition of using lug angle for end connecti

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd