After working for 30 years, Operation Management

Assignment Help:
In the table given below the Distribution Manager is expected to service these DCs as per the demands placed. If the actual sales after completing week one is as follows, what would be the quantities that would need amendment as far as Distribution Manager is concerned to service for week two and onwards?

After week one the actual sales to Forecasted sales for week one ratio is as under: Mumbai did 80 % of forecast , Lucknow did 75 % of forecast Kolkata did 60 % of week one forecast Chennai did 125 % of forecast and Delhi did 150 % of week one forecast

Note : Kolkata will receive transit stocks in week 2 .

Related Discussions:- After working for 30 years

Explain disadvantages of giving teams a lot of autonomy, Using terms from t...

Using terms from this chapter, how would you characterize the teams at ICU Medical Inc.? What are some advantages and disadvantages of giving teams a lot of autonomy to make decisi

Explain level of bookings influences, Please give a detailed explanation fo...

Please give a detailed explanation for the following scenario: Your industry practices reporting "bookings" for contracted business. The level of bookings influences your company's

Explain what is the break even quantity beyond, The first process is expect...

The first process is expected to incur $280,000 of fixed cost and add $60 of variable cost for each unit produced. The second process has fixed costs of $200, 00 and adds $70 per e

Describe be sure to justify your reasons, How would you allocate the $100,0...

How would you allocate the $100,000 bonus money and why? Remember, no 2 managers can get the same amount. Be sure to justify your reasons.

Strategy and standards approaches to reviewing software, Strategy and Stand...

Strategy and Standards Please respond to the following: •Discuss the factors that should be considered when developing a consistent IM / IT strategy. Explain your rationale. •Analy

Explain what is the makespan and machine idle time, Sequence the jobs shown...

Sequence the jobs shown below by using the Gantt chart. Assume that the move time between machines in one hour. Sequence the jobs in priority order 1,2,3,4. Job Work Center/Machine

Explain which of the following is not a production activity, Which of the f...

Which of the following is not a production activity report generated by MRP? a. Planning report b. Exception report c. Planned-order schedules d. Performance contro

Batch operations - operations function, Batch Operations - Operations Funct...

Batch Operations - Operations Function Batch systems form an intermediate category, and are the most common. Here, many different products are produced at regular or irregular

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd