Which critical path activity would be the most logical

Assignment Help Financial Management
Reference no: EM13856767

Project Management and Statistical Process Control Homework Assignment

Project Management

PERT Network Diagram 1 illustrates the ten interrelated activities that comprise a certain project.

PERT Network Diagram 1

976_pert 1.png

The information presented in Table 1 represents the optimistic activity time (a), most probable activity time (m), and pessimistic activity time (b) in weeks for each activity associated with the project.

Activity

Optimistic (a)

Most Probable (m)

Pessimistic (b)

A

2

3

4

B

1

3

5

C

2

5

8

D

1

2

3

E

2

4

6

F

1

3

5

G

2

4

6

H

1

3

5

I

2

4

6

J

1

4

7

 

2084_pert 2.png

1. Using the information provided in Table 1, calculate the expected activity time (t) in weeks for each activity and then enter this information in the appropriate data field provided for each activity in PERT Network Diagram 2 in order to complete this diagram. What is the expected activity time in weeks for each of the ten activities? (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

2. Using the information provided in Table 1, calculate the variance for the estimated activity time for each activity. (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

3. Using the information in completed PERT Network Diagram 2, calculate the overall estimated activity time in weeks for each path through the network; identify which path constitutes the critical path.

4. Using the information provided in Table 1, calculate the standard deviation for the project.

5. Using the information provided in Table 1 and completed Project Network Diagram 2, calculate the probability of the project critical path activities being completed in less than or equal to 24 weeks.

The information presented in Table 2 represents the calculated Earliest Start, Earliest Finish, Latest Start and Latest Finish times for each activity.

Table 2

Activity

Earliest Start

Earliest Finish

Latest Start

Latest Finish

A

0

3

0

3

B

3

6

3

6

C

6

11

6

11

D

11

13

16

18

E

6

10

7

11

F

11

14

11

14

G

18

22

18

22

H

0

3

7

10

I

3

7

10

14

J

14

18

14

18

1.      Using the information provided in Table 2, calculate the slack time in weeks for each activity.  (Arrange your answers in alphabetical order by activity beginning with activity A and ending with activity J).

The information presented in Table 3 represents the total budgeted cost for each activity associated with the project. 

Activity

Total Budgeted Cost

A

$22,000

B

$30,000

C

$24,000

D

$8,000

E

$7,000

F

$9,000

G

$10,000

H

$12,000

I

$23,000

J

$11,000

2.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week seven of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week seven of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week seven between these two scenarios.

3.      Using the information provided in Table 2 and Table 3, calculate the budgeted costs for week eighteen of the project based upon using the Earliest Start Date for each activity and calculate the budgeted costs for week eighteen of the project based upon using the Latest Start Date for each activity in order to then calculate the difference in the cashflow for week eighteen between these two scenarios.

Table 4 represents the percentage of completion and actual cost of work performed data for each activity associated with the project at a certain point in time during the project.


Activity

Total Budgeted Cost

Percent of Completion

Actual Cost of Work Completed

A

$22,000

100%

$23,000

B

$30,000

100%

$28,000

C

$24,000

100%

$27,500

D

$8,000

85%

$7,300

E

$7,000

65%

$9,800

F

$9,000

0%

$0

G

$10,000

0%

$0

H

$12,000

45%

$5,100

I

$23,000

0%

$0

J

$11,000

0%

$0

4.      Using the information provided in Table 4, calculate the value of work completed and activity difference for each activity.  Which activity evidences the single largest activity difference (regardless of whether it is a cost overrun or cost underrun) at this particular point in the project?

5.      Using the information provided in Table 4, calculate the overall cost overrun or cost underrun for the project at this particular point in the project.

Table 5 represents the estimated crash time in weeks and associated total crash cost for each activity. 

 

 

Activity

Crash Time

(Weeks)

Total Crash Cost

A

2

$25,000

B

2

$40,000

C

4

$27,000

D

1

$9,000

E

3

$8,500

F

2

$12,000

G

3

$11,000

H

2

$15,000

I

3

$26,000

J

3

$13,000

6.      Using the information in completed PERT Network Diagram 2 and Table 5, crash the network in order to reduce the estimated project duration to 20 weeks while minimizing the overall crash cost. Which critical path activity would be the most logical choice for the first activity to crash?

7.      Which critical path activity would be the most logical choice for the second activity to crash?

8.      What is the total estimated cost associated with crashing the network to reduce the estimated project duration to 20 weeks at the lowest possible overall crash cost?

9.      After successfully crashing the network to reduce the estimated project duration to 20 weeks, which path through the crashed network constitutes the critical path?

Reference no: EM13856767

Questions Cloud

The cost of preferred stock : The cost of preferred stock:
Summarizes landes hypothesis : Write a 500 word essay that summarizes landes hypothesis regarding the relationship between the emergence of European communes (cities) and European economic development.
What is the irr of the better project? : What is the IRR of the better project?
Can you identify any traits of humanity : As humans, we have something we could call human culture. Can you identify any traits of humanity that are common to all cultures
Which critical path activity would be the most logical : Which critical path activity would be the most logical choice for the second activity to crash?
Strategy for addressing any challenges you may face : Strategy for addressing any challenges you may face once you arrive at your new location and Strategy for addressing the cultural differences which may impact the achievement of team goals and objectives
Determine your weekly orders for kentucky swamp brew : You will also experience the Bull-Whip Effect as you practice in the EBBD simulation -  What feedback would you like to have, specifically, as you determine your weekly orders for Kentucky Swamp Brew? How would get such information?
Logic puzzle of five friends : Five friends had just let out a collective sigh of relief after filling their income tax statements on time, when the subject of tax write offs arose.
Explain squirrel-cage induction motor operates : A four-pole, star-connected, squirrel-cage induction motor operates from a variable voltage 50 Hz three-phase supply. The following results were obtained as the supply voltage was gradually reduced with the motor running on no-load. Stator line vo..

Reviews

Write a Review

Financial Management Questions & Answers

  Life is expected with no anticipated value thereafter

A new computer server costs $860,000, delivered and installed. Annual operating costs are $32,000. A five year life is expected with no anticipated value thereafter. Given a required rate of return of 12%, what is the equivalent annual cost of the se..

  Determine the total tax revenue for the state

The department of revenue estimates that the average tax revenue from each citizen is as follows: income tax, $800; sales tax, $150; personal property tax, $250. In addition, the average corporate tax is $7,500 per company. Develop a model that will ..

  What semi-annual interest payments will ibm receive

IBM wants to swap out of $10,000,000 of fixed interest rate debt and into floating interest rate debt for 3 years. Assume the fixed interest rate is 7.625 percent and the floating rate is dollar LIBOR. What semi-annual interest payments will IBM rece..

  Relationship between economies of scale and natural monopoly

What is the relationship between economies of scale and a natural monopoly? Why is the level of output at which marginal revenue equals marginal cost the profit-maximizing output?

  What is the value of this annuity today if the discount rate

Tara Knowles buys an annuity that will pay her $24,000 a year for 25 years. The payments are paid on the first day of each year. What is the value of this annuity today if the discount rate is 8.5 percent?

  Conflict of interest between owners and agents

Which of the following statements is most accurate regarding agency problems? An agency problem likely occurs when there is a conflict of interest between owners and agents.

  Firm is considering an investment in a new machine

A firm is considering an investment in a new machine with a price of $18 million to replace its existing machine. The current machine has a book value of $6 million and a market value of $4.5 million. The new machine is expected to have a four-year l..

  Discuss many different financial ratios

Finance text books normally discuss many different financial ratios. Such as liquidity ratios and the rest. What is their purpose?  Can any ratio or combination of ratios predict a company's long-term viability?  Can you think of an example whereby o..

  What was the net cash flow from operating activities

Red Corp issues $1,000,000, 8% five year bonds with interest paid semiannually. The current market rate of interest is 10%. Compute the price of the bond. Compute the discount/premium. Record the issuance of the bonds. What was the net cash flow from..

  What ear is the bank is charging

What EAR (effective annual rate) is the bank is charging? What if they change compounding to bi-monthly?

  Review and evaluation of financial performance

Explain if the source of cash sustainable, and list any outstanding variances you have noticed below:3-4 variances required and now in the space provided, list the corrective measures you would implement and why.

  Why did the bonds value change

Whats the bonds new price and How does the price compare with your answer in part a? Why did the bond's value change?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd