What is the critical path for project and how long is it

Assignment Help Humanities
Reference no: EM131286742

Network Diagrams are often used during project planning to give the project manager a visual map of the key activities of the project. Activity-On-Arrow (AOA) is often used to demonstrate the concept of activity sequencing. Consider Figure 4-30 (page 172 in your textbook) to answer the following questions. All duration estimates are in days, and the network proceeds from Node 1 to Node 9.

Draw an AOA network diagram representing the project. Put the node numbers in circles and draw arrows from node to node, labeling each arrow with the activity letter and estimated time. See example 143, Fig. 4-16.

Identify all the paths on the network diagram and note how long they are, using Figure 4-21 (page 152) as a guide for how to represent each path.

What is the critical path for this project and how long is it?

What is the shortest possible time it will take to complete this project?

Examine the network diagram and task schedule table to analyze the critical path and float or slack for each activity. Write at least a

paragraph that interprets this information for someone unfamiliar with project time management.

Schwalbe, K. (2013). An introduction to project management.( 4e) Minneapolis, Minnesota: Kathy Schwalbe, LLC

Reference no: EM131286742

Questions Cloud

Find financial risk associate with operating internationally : Evaluate the financial risks associated with operating internationally. If your company does not operate internationally, evaluate what the financial risks could be if they were to expand internationally.
Why is it difficult to develop good plans : How does having a scope and WBS help project teams during project execution? Why is it difficult to develop good plans?Name the main planning tasks performed as part of project integration management? What are the main documents created, and what s..
Calculate the force in each member of the trusses : Using the method of joints, calculate the force in each member of the trusses shown. State whether each member is in tension or compression.
Major obstacles to arcors attempt to penetrate markets : What would be the major obstacles to Arcor's attempt to penetrate markets outside Latin America?- Where are Arcor's competitive advantages in the value chain?
What is the critical path for project and how long is it : Draw an AOA network diagram representing the project.What is the critical path for this project and how long is it?What is the shortest possible time it will take to complete this project?
Which marketing problems does nivea anticipate : Which degree of market responsiveness and global coordination/integration does Nivea represent?- Which marketing problems does Nivea anticipate when penetrating the US market?
Prepare cost of production report for department : Green Company makes a product, Gloworm, in a two-part process. Gloworm is assembled in Department A and then goes to Department B for finishing.  Prepare a cost of production report for Department B using the FIFO method.
Find the hpull the 80-lb homogeneous roller over 3-in. curb : The two-force and three-force principles where appropriate. Neglect weights of members unless specified otherwise.
Calculate the real option values for all types of reserves : You will calculate the real option values for all types of reserves for which you identify real options in the MW Petroleum Case using the Black-Scholes Option Pricing Model (BSOPM) as described above.

Reviews

Write a Review

Humanities Questions & Answers

  Technology remains a human creation and we have the power

answer each question with a minimum of 80 words per question1technology remains a human creation and we have the power

  Write a reasonable specification for this method

Write a reasonable specification for this method and compare your answer to the solution at the end of the chapter. The specification should require a positive radius.

  What is social security

What is social security? - Describe the three major categories of social security.

  Make a critical connection between the film and any element

Make a critical connection between the film and any element of the class- Discuss how the film contributes to the understanding of American literature or history.

  Locate a non web-based source dealing with stress this

locate a non web-based source dealing with stress. this resource might be a book video or audio from the library or a

  Difference between the three paradigms

Explain, in your own words, the difference between the three paradigms: human needs, interactive, and unitary process. Which of these best fits your philosophy of nursing?

  Find dual of this code and show that this code is self-dual

Consider a linear block code with code words {0000, 1010, 0101, 1111}. Find the dual of this code and show that this code is self-dual.

  Find examples of how genograms are being utilized

find examples of how genograms are being utilized in the clinical setting.- A Genogram is powerful to help understand a family history.

  From the first e-activity below discuss the possible future

social stratification please respond to the followingbullfrom the first e-activity below discuss the possible future

  I received a 3700 national endowment for the humanities

i received a 3700 national endowment for the humanities grant for high school teachers for a 3 week philosophy course

  Barriers same-sex couples encounter to health care

The final step in the completion of your research project is to write a 12- to 20-page paper (including all the elements listed below, excluding any appendices). It should incorporate revisedversions of the draft literature review and methodology ..

  Write a paper that describe catholic work

You must conduct an interview with a local catholic priest (in person or through electronic means) and write a paper describing their work and the impact it has on the community.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd