A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nearly $162,000. What are the spending and schedule variances for the project? What are the SPI and CPI?

Reference no: EM131072309

Questions Cloud

Mortem techniques should executor consider electing : Hazel, a widow, died. She had made no previous lifetime taxable gifts and she died with a gross estate of $5,250,000, consisting solely of a diversified portfolio of publicly traded, income-producing stocks. Which of the following post-mortem techniq..
Parameter values of the supply chain to minimize lost sales : Currently the model described in this chapter assumes that customers will accept backorders and late deliverys. Modify the model so that demand which can not be met on time results in lost sales.
Research wearables technologies and mobile apps : Research wearables technologies, mobile apps and hardware projects currently under development; feel free to use crowdsourcing websites, such as Kickstarter, Indiegogo, RocketHub, or Circet.
Compute total revenue and total profit : Compute total revenue and total profit.
What are spending and schedule variances for project : A project has just completed its 87th item in the project plan. It was scheduled to have spent $168,000 at this point in the plan, but has actually spent only $156,000. The project manager estimates that the value of the work actually finished is nea..
How do we define price elasticity of supply : How do we define price elasticity of supply? How do we measure price elasticity of supply? What is in the numerator of elasticity equation? What is in the denominator?
Explanations for sources of inefficiency in credit markets : How does the experiment by Dean Karlan and Jonathan Zinman (also discussed in Banerjee and Duflo 2010) among clients of a financial institution in South Africa allow them to test possible explanations for the sources of inefficiency in credit markets..
Draw the demand curve to scale on a diagram : Draw the demand curve to scale on a diagram
Who will this mis system help and why : What is the company where this MIS system going to be? What is the industry this company participates in? Who does this company compete with? Does this new system fit with the company's mission statement?

Reviews

Write a Review

Financial Management Questions & Answers

  Estimate the cost of capital of the firm

You are analyzing Tiffany Corp, an upscale retailer. The regression estimate of the firm's beta is 0.75. Standard error of beta estimate is 0.50. The average unlevered beta of comparable specialty retailing firms is 1.15. Estimate the Cost of Capital..

  Firm uses payback period criteria of not accepting project

AMP INC has invested $2,165,800 on equipment. The firm uses payback period criteria of not accepting any project that takes more than 4 years to recover costs. The company anticipates cas flows of $451,386, $512,178, $561,755, $764,997, $816,500, and..

  Report on a company providing a clear audit trail

Prepare report on providing a clear audit trail to your company.  Prepare a portfolio of analytical reference materials including the financial reports for at least five years. This is your analytical permanent file for the chosen company.

  What is the required rate of return on the market

Fiske Roofing Supplies' stock has a beta of 1.43, its required return is 11.75%, and the risk-free rate is 3.30%. What is the market risk premium? And what is the required rate of return on the market?

  Annual return mean and standard deviation

Tyler Trucks stock has an annual return mean and standard deviation of 8 percent and 27 percent, respectively. Michael Moped Manufacturing stock has an annual return mean and standard deviation of 19.0 percent and 63 percent, respectively.

  About a good-til-cancelled order

Which one of the following statements is correct about a good-'til-cancelled order? The order generally expires after six weeks. The order will automatically renew unless cancelled by the customer.

  What is cash value of this annuity due at the end of year

At the beginning of each period for 10 years, Merl Agnes invests $500 semi annually at 6%. What is the cash value of this annuity due at the end of year 10?

  Earnings per share are approximately

A stock report contains the following information: P/E 21.4, closing price 28.16, dividend 1.10, net chg .06, and an ask of 28.22 × 300. Which one of the following statements is correct given this information? The stock price has increased by 6 perce..

  Portfolio is equivalent to the risk level of overall market

You would like to combine a risky stock with a beta of 1.88 with U.S. Treasury bills in such a way that the risk level of the portfolio is equivalent to the risk level of the overall market. What percentage of the portfolio should be invested in the ..

  What level of pretax cost savings

Your firm is contemplating the purchase of a new $1,036,000 computer-based order entry system. The system will be depreciated straight-line to zero over its 5-year life. It will be worth $100,800 at the end of that time. At what level of pretax cost ..

  What is the standard deviation of the portfolio

A portfolio has 30% of its value in IBM shares and the rest in Microsoft (MSFT). The volatility of IBM and MSFT are 35% and 30%, respectively, and the correlation between IBM and MSFT is 0.3. What is the standard deviation of the portfolio?

  Liquidity premiums are higher on treasury corporate bonds

If the maturity risk premium were zero and interest rates were expected to decrease in the future, then the yield curve for U.S. Treasury securities would, other things held constant, have an upward slope. Liquidity premiums are generally higher on T..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd