In his backyard, Robert is erecting a new fence. What he will accomplish and how long it will take are described below:
The fence design takes a day, and work may begin right away. After he has designed the fence, he can give each of his two pals (John and Bill) a day to buy and transport various supplies. While John just needs one day, Bill needs two days to procure and deliver his list of supplies. After John purchases and provides his list of items, the drilling of the post holes may begin. After the new holes are drilled and Bill delivers his list of materials, the process of setting the posts in concrete can begin. This process takes one day. Setting the posts in concrete takes one day and can start after the new holes are drilled and after Bill delivers his list of materials. Building and installing the panels and gate takes one day and can start after the poles are set in concrete. After the panels and gate are installed, it takes one day for Bill and John to clean up their mess, and they start after the gate is installed. At the same time, Robert begins painting the fence. He is done after three days, and the job is completed.
Instructions:
1. Draw the critical path and include all the values for standard critical path notation: task identifier, duration, early start, early finish, late start, late finish,
A sphere of radius R is uniformly charged to a total charge of Q. It is made to spin about an axis that passes through its center with an angular speed ω. Find the magnitude of the resulting magnetic field at the center of the sphere.
A resistor is in the shape of a cube, with each side of resistance R . Find the equivalent resistance between any two of its adjacent corners.
Question: Field and force with three charges? What is the electric field at the location of Q1, due to Q 2 ?
What is the maximum displacement of the bridge deck?
What is the magnitude of the current in the wire as a function of time?
Questions on blackbody, Infra-Red Detectors & Optic Lens and Digital Image.
Illustrate the cause of the components accelerating from rest down the conveyor.
Calculate the dc voltage applied to the circuit.
Quadrupole moments in the shell model
Determine the tension in each string
Calculate the smallest coefficient of static friction necessary for mass A to remain stationary.
Evaluate maximum altitude?
Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!
whatsapp: +91-977-207-8620
Phone: +91-977-207-8620
Email: [email protected]
All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd