Uses earned value management

Assignment Help Physics
Reference no: EM131502038

Details:

As a project management professional, it is important for you to be able to review numbers and report on what they are saying. It is also important for you to be able to use software that helps you keep timelines and keep the project running on time and smoothly. This assignment will continue to help prepare you for your responsibilities.

Respond to the Following Problems

You are a project manager on a project that uses earned value management. The project has the following budget and status:

Project Duration (months):

14

Current Reporting Period (month):

6

BAC:

$387,000

Cumulative PV:

$68,345

Cumulative AC:

$78,379

% of the project completed through the reporting period:

19%

Estimate to Complete:

$294,677

Based on this information, determine the following:

  1. Cumulative EV
  2. Schedule Variance (SV)
  3. Schedule Performance Index (SPI)
  4. Cost Variance (CV)
  5. Cost Performance Index (CPI)
  6. EAC (bottom-up)
  7. VAC (bottom-up)
  8. TCPI

Based on your calculations in Question 1 above, respond to the following:

  1. What is the status of project accomplishment performance through the current reporting period? Why?
  2. What is the status of project cost performance through the current reporting period? Why?
  3. Is the project projected to complete over or under-budget? Why?
  4. Interpret the TCPI metric.

Based on your calculations in Question 1 above, an inexperienced and arrogant project analyst from the project management office has computed an additional metric: Cost Schedule Index, which equals SPI * CPI. He wants you to report this metric to the customer, instead of SPI and CPI separately. What should you do and why?

The program manager doubts your numbers. In particular, he does not believe your EAC number and requests that you calculate two independent EACs. In particular, he wants the following IEACs calculated from rows two and four in Table 23-5 in Snyder, (2013).

  1. Compute IEAC1= ((BAC- EV)/CPI) + AC
  2. Compute IEAC2= ((BAC- EV)/(SPI*CPI)) + AC
  3. Interpret IEAC1
  4. Interpret IEAC2
  5. Based on items 1-4 above, what do you think the program manager will request from you regarding the bottom-up EAC?

You are having a hallway conversation with the same project analyst from Question 3, who is realizing that he may not know as much about earned value management as he thought when he joined the company. Still, he is convinced that the following statements below are correct. How would you respond to him based on each statement (i.e., formulate a specific response and supporting rationale for each statement below)?

  1. EAC becomes Cumulative AC at project completion.
  2. Cumulative EV can be greater than BAC at project completion.
  3. EAC can be smaller than BAC at project completion.
  4. ETC can be greater than 0 at project completion.

Ensure that your last name is in the file name and submit your completed Excel file by the end of this week.

You are not required to submit this assignment to Turnitin.

Please complete this work correctly and as soon as possible.

Reference no: EM131502038

Questions Cloud

Identify each use case in the functional model : Identify each use case in the functional model and create a sequence and communication diagram for each scenario of each use case identified.
Give some examples on how you would orient : Give some examples on how you would orient, train, and educate your event staff. How would you, as an event manager, motivate and inspire your staff?
Participants in collective bargaining : Do you think the attitudes and bargaining behaviors of the participants in collective bargaining negotiations are more or less important in the final outcome.
What role do you think normative influence : What role do you think normative influence and consumer socialization have played in the ongoing popularity of Black Friday and Cyber Monday?
Uses earned value management : You are a project manager on a project that uses earned value management. The project has the following budget and status:
Why is it important to focus on understanding the business : Why is it important for the conceptual design to focus on understanding the business and its functional areas or business processes?
Power and limitations of theatrical imagination : In this thread, let's discuss the power and limitations of theatrical imagination. Please feel free to draw from productions you have seen.
Developing a strategic plan : Define and explain the role of ethics and social responsibility in developing a strategic plan while considering stakeholder needs and agendas.
Essential skills for an effective project manager : What are some essential skills for an effective project manager? How can these skills be developed? discussion post must be 300 words.

Reviews

Write a Review

Physics Questions & Answers

  Find the magnitude of the resulting magnetic field

A sphere of radius R is uniformly charged to a total charge of Q. It is made to spin about an axis that passes through its center with an angular speed ω. Find the magnitude of the resulting magnetic field at the center of the sphere.

  Find the equivalent resistance

A resistor is in the shape of a cube, with each side of resistance  R . Find the equivalent resistance between any two of its adjacent corners.

  What is the electric field at the location

Question: Field and force with three charges? What is the electric field at the location of Q1, due to  Q 2 ?

  What is the maximum displacement of the bridge deck

What is the maximum displacement of the bridge deck?

  What is the magnitude of the current in the wire

What is the magnitude of the current in the wire as a function of time?

  Blackbody

Questions on blackbody, Infra-Red Detectors & Optic Lens and Digital Image.

  Gravity conveyor

Illustrate the cause of the components accelerating from rest down the conveyor.

  Calculate the dc voltage

Calculate the dc voltage applied to the circuit.

  Quadrupole moments in the shell model

Quadrupole moments in the shell model

  Determine the tension in each string

Determine the tension in each string

  Introductory mechanics: dynamics

Calculate the smallest coefficient of static friction necessary for mass A to remain stationary.

  Evaluate maximum altitude

Evaluate maximum altitude?

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd