Reference no: EM132225332
1. All of the following should be considered before a change is considered EXCEPT:
a) Relevance
b) Risk
c) Reasonableness
d) Responsiveness
2. The purpose of doing a new baseline is _________
a) to complete the change approval process
b) to assess the net impact of a change on the scope, schedule and/or budget for the project
c) to calculate Earned Value statistics on the project
d) To document the most up-to-date plans for scope, schedule and budget on the project with all changes applied.
3. As a project manger your role in potential new project changes is __________
a) all of these
b) receiving and recording change requests from sponsor(s) and/or functional managers
c) making sure that an appropriate evaluation of all impacts relating to a change request is done
d) suggesting change requests to sponsor(s) and/or functional mangers
4. If you are involved in a complex project, and are not receiving change requests or new items to be considered for the sprint backlog, this could be a sign that
a) You are a fantastic project manager!
b) You are working on a project that doesn't need to change anything
c) You are using an Agile methodology
d) You will be getting changes when your project catches your busy stakeholders attention again.
5. The purpose of a change log is to ___________
a) all of these
b) update plans for the scope, schedule and budget when changes are approved
c) record only approved change requests
d) help prevent "zombie changes"
6. When rejecting a change use the __________________ approach
a) Just Say No
b) No, Because
c) No, But
d) Yes, But