The alternative work schedule background

Assignment Help Operation Management
Reference no: EM131428559

Case The Alternative Work Schedule Background March 13 marked an important day in the history of Building Products, Inc. The planning committee was meeting to determine the work schedule for all of the production workers at its new plant. Attending the meeting was the human resource director, the plant manager, and the production manager. The plant was scheduled to open in a few months, and it was time to begin hiring new employees. The committee knew that the new work schedule would need to meet specific param- eters. First, the plant’s production process would require that chemicals and materials be heated to high temperatures, so the plant would have to operate 24 hours a day, seven days a week, 363 days a year. On Christmas Day and the day before Christmas, the plant would shut down with only two employees needed— a production operator and a maintenance technician. Second, workers would not be able to take breaks all at one time. Rather, they would need to stagger the breaks and cover for each other. Third, having the standard 8-to-5 work schedule would not be possible, given the need for 24-hour coverage. Likewise, a work schedule that entails three shifts, each working eight-hour days would not work because coverage is needed seven days a week, and employees need time off to rest. After much discussion, the human resources director suggested that the firm try a schedule that she had heard about at another firm. The schedule entailed dividing workers into four crews, with each crew working 12-hour shifts on either three or four consecutive days or nights. It also meant that employees would switch between day shifts and night shifts. More specifically, the schedule of rotation for one crew would be as follows: 4 night shifts—12 hours per night (7 PM to 7 AM) 2 days/nights off 3 day shifts—12 hours per day (7 AM to 7 PM) 2 days/nights off 3 night shifts—12 hours per night (7 PM to 7 AM) 2 days/nights off 4 day shifts—12 hours per day (7 AM to 7 PM) 8 days/nights off Repeat sequence throughout this and future years.

The human resources director noted that by dividing all of the workers into four crews, the schedules for the crews could be integrated in such a way that only one crew would be working, yet all hours could be covered (see schedule above). Each crew would consist of 17 production operators, two warehouse/forklift truck workers to take product off the line, and one production supervisor. Also, she suggested that overtime pay be granted to employees when they work more than 40 hours per week. An employee who works a 48-hour week would receive straight pay for 40 hours and time-and-one-half for eight more hours. This equates to 52 hours of straight pay. Thus, in the course of a 28-day period, employees would work shifts totaling 168 hours, but be paid for 176 hours. In addition, she recommended that employees who work over a holiday receive double pay for those hours, but that no additional overtime pay be provided for working Saturday or Sunday.

After hearing the human resources director’s recommendations, the plant manager and the production manager sat quietly, trying to digest the plan. The schedule was completely unlike anything they had ever experienced, and it struck them as bizarre. They could not help but question whether the plan would actually work. They also wondered if there might not be a better production schedule.

1.What do you see as the strengths and weaknesses of the human resources director’s work schedule from (a) the employees’ perspective, and (b) the firm’s perspective?

2. Would you recommend the firm use the new work schedule? Why?

3. What alternative work schedule could be u.

Reference no: EM131428559

Questions Cloud

Define the term internal partnering : From Partnering and Strategic Alliances - Total Quality management. Define the term internal partnering. Explain the rationale for partnering with customers. What role does mutual need play in manufacturing networks.
Personal time management plan-techniques and approaches : Develop and describe a personal time management plan that will support your educational goals as well as maintain your workplace and family responsibilities. Techniques and approaches, Challenges.
Personality preferences-stress level and assessments : Discuss the following question in 450 word count.develop and describe a personal time management plan that will support your educational goals as well as maintain your workplace and family responsibilities. Personality preferences, Stress level, Asse..
Develop and describe apersonal time management plan : Develop and describe apersonal time management plan that will support your educational goals as well as maintain your workplace and family responsibilities. Plan for balancing the important relationships and activities of your life with your master’s..
The alternative work schedule background : Case The Alternative Work Schedule Background March 13 marked an important day in the history of Building Products, Inc. The planning committee was meeting to determine the work schedule for all of the production workers at its new plant. What do you..
Implemented without number of support systems : A firm's stratetgies cannot be implemented without a number of support systems to carry on business operations. Discuss how your firm or a company that you are familiar with has used real-time Information Technology systems and control systems to aid..
Determine the present value of future earnings : The justification should include key terms, techniques, and possibly equations necessary to show satisfactory understanding of the topic being tested. The process outlined in the diagram below is in place in order to determine the present value of fu..
The three keys to effective portfolio management : The justification should include key terms, techniques, and possibly equations necessary to show satisfactory understanding of the topic being tested. The three keys to effective portfolio management are having project leaders with full authority, ha..
Cross-listing of kerzner-shenhir project success elements : Submit a word document with the following elements: A cross-listing of Kerzner and Shenhir/Dvir project success elements. Synthesize the Kerzner and Shenhir/Dvir  sources into a prioritized, single list.

Reviews

Write a Review

Operation Management Questions & Answers

  A new machine was bought for

A new machine was bought for $9,000 with a six years and no salvage value. Its annual operating cost were as follows

  Strategic factors in the corporations external environment

How can a decision maker identify strategic factors in the corporation's external environment? How will you do this in your case analysis? What is the relevance of the resource-based view of a firm to strategic management in a global environment?

  Using decision-tree analysis

The Karns Company is deciding whether to drill for oil on a tract of land the company owns. The company estimates the project would cost $8 million today. Karns estimates that, once drilled, the oil will generate positive net cash flows of $4 million..

  Difference between consumer products and business products

Explain the difference between consumer products and business products. Why are some products difficult to categorize as one or the other?

  Explain the relationship between custom, option

Explain the relationship between custom, option and standard goods and services as they relate to project, job shop, flow shop and continuous flow processes.

  International strategy analysis

Write a brief assessment (two pages) of the Outback Steakhouse case found in the text. Pay particular attention to the following questions: What are the basic elements of Outback's plan for going international? What do you see as the strengths and we..

  Explain how do organizational structures influence

dq 1. how do organizational structures affect organizational functions? how does your organizations structure affect

  What constrained optimization and theory of constraints

Prepare an explanation of what constrained optimization and the Theory of Constraints are. Also, explain if it should be implemented in all organizations. If you think this is something organizations should pursue, would it be a tactical or strategic..

  Correct sequence of the marketing communication process

Which of the following circumstances would best require a pull strategy to be implemented for product promotion? Which of the following reflects the correct sequence of the marketing communication process?

  Are any levels not useful when applying system safety

What levels of the hierarchy of controls are most applicable to system safety? Are any levels not useful when applying system safety? Provide one or more examples that support your response.

  Information systems in preventing fraud-unethical behavior

What is the role of Information Systems in preventing fraud or unethical behavior in a company? Discuss If a company’s manufacturing system increased production based on the fraudulent sales in the previous quarter! Can the computer system provide tr..

  Which type of contracting arrangement

Thinking in terms of budget, scope, and time, which type of contracting arrangement would you prefer to build your retirement home and why? [Evaluate this scenario in terms of risk management as well.] 1. Multiple contractors who each specialize in o..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd