Review the assessment of liquidated damages

Assignment Help Other Subject
Reference no: EM131866133

Question: Dimwit has refused to issue Change Orders for other work, claimed to be "extra" by Wackinsmack. Included in the pile of refused change orders, are two "Field Directives" issued by Dimwit's Engineer (Ithinkican Engineering Consultants, Inc.) which the Owner feels are not changes; a claim for Differing Site Conditions, which Dimit says Wackinsmack should have known about; and, the discovery of hazardous "contamination" in the excess excavated soil materials which had to be trucked off the site and disposed of (which Dimwit feels is Wackinsmack's contractual responsibility).

The accumulation of changes, including those for which Dimwit has not agreed, has resulted in delays to the project. Wackinsmack failed to achieve Substantial Completion of the work by the Contract End Date (as adjusted by approved change orders). As a result Dimwit has assessed liquidated damages against Wackinsmack for late completion. Wackinsmack has, in turn, assessed Acme for 53% of the liquidated damages based on Acme's proportionate share of the prime contract price.

One of the disputed Work Orders involves the direction by Ithinkican to relocate some of the process piping (work performed by Acme) to avoid conflicts with other aspects of the design. Ithinkican has advised Dimwit that this work was part of the contractor's "methods and means" responsibility and is not an extra. Acme performed the work and claims $350,000 in extra costs.

Assumption: Assume that, as a result of all of the changes, including the disputed work order, the project has been delayed by 200 calendar days. If the Contract End Date were to be enlarged by 200 calendar days, the project would have been completed on time, and there would be no basis for Dimwit to assess liquidated damages.

Essay Assignment: Please prepare a letter to Dimwit asserting Wackinsmack's view that it is entitled to an excused, compensable delay and enlargement of the Contract End Date, and that Dimwit should rescind its assessment of liquidated damages.

Reference no: EM131866133

Questions Cloud

Statements concerning price to book value is true : Which of the following statements concerning price to book value is true?
What is the function of that layer of the epithelium : Given that epithelial tissue is avascular, what layer of the epithelia would be expected to have the best nourished cells?
Explain the different levels of reverence : Different cultures value personal, face-to-face contact and relationships with a different levels of reverence. What are some cultures around the world.
Structure or anatomical feature : Without using the same answer twice, list one structure or anatomical feature that could be found in each of the following sites relative to the ribs
Review the assessment of liquidated damages : Please prepare a letter to Dimwit asserting Wackinsmack's view that it is entitled to an excused, compensable delay and enlargement of the Contract.
Calculate the value of the call option : You are considering a position as the director of finance in a company listed on a stock exchange. Calculate the value of the call option.
What is the total capacity of nurses : What is the total capacity of Nurses, as in the maximum number of patients the Nurses can see in one hour? Round your answer to one decimal place.
Imbalances from appearing in the body : In addition, indicate where each mechanism functions most significantly. (Do not explain any specific chemical reactions.)
Seeking help with the best way to retain info in anatomy : Seeking help with the best way to retain info in Anatomy. I take detailed notes ny hand and then try rtyping them around test time with diagrams etc

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd