Problem 1

Solve the following problem graphically (Please be neat) (Suggestion, use some graphing software such as GraphCalc® to create the feasible solution space. Then print that graph for your analysis):
 
Maximize Z = 8x1 + 5x2
Subject to: 

  -4x1 + x2 ≤ 1
  3x1 + 4x2 ≤ 25
  5x1 -2x2 ≤ 12
  -1.5x1 + 3x2 ≤ 8
 
and

x1,x2 ≥ 0 

Problem 2
 
Work through the simplex method (in algebraic form) step by step to solve the following problem. Show all work and provide the solution. 
 
  Maximize  Z = x1 + 3x2 + 2x3,
subject to

    5x1 + 2x2 + 3x3 ≤ 15
      x1 + 4x2 + 2x3 ≤ 12
    2x1 +  x3 ≤   8
and
    x1 ≥ 0,    x2 ≥ 0,   x3 ≥ 0.
 
Problem 3

My diet requires that all food I eat come from one of the four "Basic food groups" (chocolate cake, ice cream, soda, and cheesecake). At present, the following four foods are available for consumption: brownies, chocolate ice cream, cola, and pineapple cheesecake. Each brownie costs 50¢, each scoop of chocolate ice cream cost 20¢, each bottle of cola cost 30¢, and each piece of pineapple cheesecake cost 80¢. Each day, I must ingest at least 500 calories, 6 oz of chocolate, 10 oz of sugar, and 8 oz of fat. The nutritional content per unit of each food is shown in the following table. Formulate a linear programming model that can be used to satisfy my daily nutritional requirements at minimum cost.

435_Formulate a linear programming model.png


1. Formulate a linear programming model for this problem by:

A.  Listing and labeling all of the decision variables.

B.  Creating an objective function for the model.

C.  List all

2. Solve the model using Excel® solver. Give the value for each decision variable and the objective function.

Problem 4.

The Weigelt Corporation has three branch plants with excess production capacity. Fortunately, the corporation has a new product ready to begin production, and all three plants have this capability, so some of the excess capacity can be used in this way. This product can be made in three sizes--large, medium, and small--that yield a net unit profit of $420, $360, and $300, respectively. Plants 1, 2, and 3 have the excess capacity to produce 750, 900, and 450 units per day of this product, respectively, regardless of the size or combination of sizes involved.

  The amount of available in-process storage space also imposes a limitation on the production rates of the new product. Plants 1, 2, and 3 have 13,000, 12,000, and 5,000 square feet, respectively, of in-process storage space available for a day's production of this product. Each unit of the large, medium, and small sizes produced per day requires 20, 15, and 12 square feet, respectively.

  Sales forecasts indicate that if available, 900, 1,200, and 750 units of the large, medium, and small sizes, respectively, would be sold per day.

  At each plant, some employees will need to be laid off unless most of the plant's excess production capacity can be used to produce the new product. To avoid layoffs if possible, management has decided that the plants should use the same percentage of their excess capacity to produce the new product.

  Management wishes to know how much of each of the sizes should be produced by each of the plants to maximize profit.

1. Formulate a linear programming model for this problem by:

D.  Listing and labeling all of the decision variables.

E.  Creating an objective function for the model.

F.  List all

2. Solve the model using Excel® solver. Give the value for each decision variable and the objective function.

Problem 5. For the project schedule, answer the following questions. 

1.  What is the total time required to complete the project if no delays occur?
 
2.  When do the individual activities need to start and finish (at the latest) to meet this project completion time?
 
3.  When can the individual activities start and finish (at the earliest) if no delays occur?
 
4.  Which are the critical bottleneck activities where any delays must be avoided to prevent delaying project completion?
 
5.  For the other activities, how much delay can be tolerated without delaying project completion?

2460_Formulate a linear programming model1.png

431_Formulate a linear programming model2.png

6.  Suppose the following data is given pertaining to the cost associated with crashing activities. What activities should be crashed and how much will it cost if the deadline is changed to:
 
a.  19 weeks

b.  18.5 weeks

c.  18 weeks

d.  17.5 weeks

e.  17 weeks

f.  16.5 weeks

g.  16 weeks

h.  15.5 weeks

i.  15 weeks
 
7. Plot the cost of time reduction against total time reduction and draw any conclusions. What happens to the cost as the amount of time reduction is increases?

1996_Formulate a linear programming model3.png

Reference no: EM13347254

Questions Cloud

Question one-discuss the different types of teams as to : question one-discuss the different types of teams as to their effectiveness that will improve problem solving
Question 1unfocused books is a discount retail bookshop : question 1unfocused books is a discount retail bookshop that has three departments fiction non-fiction and childrens
1 the future value of a dollar as the interest rate : 1. the future value of a dollar as the interest rate increases and the farther in the future an initial deposit is
Part iyou have to write a computer program that will figure : part iyou have to write a computer program that will figure out the total of an order when given the amount of the
Problem 1solve the following problem graphically please be : problem 1solve the following problem graphically please be neat suggestion use some graphing software such as
What is the structure including functional groups : what is the structure including functional groups? stereochemistry racemic or single enantiomer?bull does the structure
Prepare a speech that involves communicating changes the : prepare a speech that involves communicating changes. the topic involves communication changes personal changes or
Parts 1 student is to imagine that they work for a : parts 1. student is to imagine that they work for a real-life company that has international operations. their board of
Please write project report and provide cross-synthesis an : please write project report and provide cross-synthesis. an interesting effect in electronic music synthesis is to

Reviews

Write a Review

Operation Research Questions & Answers

  Evaluate business value

How can internet technologies be involved in improving a process in one of the functions of business? Choose one example and evaluate its business value.

  Prepare a planning memo for the tlc engagement

Prepare a planning memo for the TLC engagement based on the information provided in the case.

  How would you judge the potential profit of bajaj electronic

How would you judge the potential profit of Bajaj Electronics on the first year of sales to Booth Plastics and give your views to increase the profit and suggestion regarding Credit limit. Should it be approved or not, what should be the amount of..

  Researching my career

Researching My Career.

  Loss estimates regarding an investment project

What is the likelihood that each alternative will produce a profit of at least $ 300 - Which size of equipment would you recommend on the basis of the three coefficients of variation that you calculated?

  Discuss the legal principle that would be applied

Identify and discuss the legal principle that would be applied by a court to resolve this issue and predict the outcome of the suit against Tom.

  Generate a sequence of random numbers

Use the Kolmogorov-Smirnov test to discover whether the underlying distribution is exponential and generate a sequence of random numbers using the following settings

  Explain how should the industry respond to such criticisms

Some critics have claimed that by outsourcing so much work, Boeing has been exporting American jobs overseas. Is this criticism fair? Explain how should the Industry respond to such criticisms?

  Illustrate what are the alternatives for solving business

Do you agree with Maggie Brown's accounts receivable policy? Illustrate what are the alternatives for solving the business's cash problem?

  Minimum total time required to finish the jobs

Each mechanic should be assigned to just one of these jobs. What is the minimum total time required to finish the four jobs? Who should be assigned to each job?

  Find out which option is most appropriate for your needs

If you were a small business owner, Explain how would you find out which option is most appropriate for your needs? Which of the SBA Loans appears to be most beneficial to a small business? Explain why?

  Expected delay costs

Would adding one teller decrease or increase the expected hourly cost of Dino-Bank

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd