Reference no: EM132560839
Bulong Company manufactured 1,000 units of a special multi-layer breathable fabric with the trade name "walang pakpak".
The following information from the "walang pakpak" production department for the month of May is as follows:
Direct material purchased: 36,000 yards at 1.38 per yard 49,680
Direct material used: 19,000 yards at 1.38 per yard 26,220
Direct labor: 4,200 hours at 9.15 per hour 38,430
The standard prime costs of one unit of "walang pakpak" is as follows:
Direct material: 20 yards at 1.35 per yard 27
Direct material used: 4 hours at 9.00 per yard 36
Total standard prime cost per unit of output 63
Required:
Question 1. Materials spending variance
Question 2. Direct material efficiency variance
Question 3. Labor rate variance
Question 4. Labor efficiency variance