MME80001 Resource Planning and Management Assignment

Assignment Help Mechanical Engineering
Reference no: EM132521465

MME80001 Resource Planning and Management - Swinburne University of Technology

Problem (1) of Assignment 1:

Assume that your organisation Rho Delta has to commence a new highway bridge project Alpha Theta on 1st July 2020. The construction sequence of this project Alpha Theta is described in the following table and figure.

Activity Category

Activity ID

Activity Description

Zone of construction work

Activity duration (weeks)

Excavation for foundations

A1

Excavation 1

2

10

A2

Excavation 2

4

6

A3

Excavation 3

6

8

A4

Excavation 4

8

6

A5

Excavation 5

10

10

Driving Piles

B1

Pile set 1

6

10

B2

Pile set 2

8

11

Concrete foundations

C1

Foundation 1

2

8

C2

Foundation 2

4

6

C3

Foundation 3

6

8

C4

Foundation 4

8

6

C5

Foundation 5

10

8

Retaining walls

D1

Retaining wall 1

2

12

D2

Retaining wall 2

10

15

Reinforced concrete columns

E1

RC column 1

4

12

E2

RC column 2

6

10

E3

RC column 3

8

10

Erection of slabs

F1

Slab 1

3

4

F2

Slab 2

5

6

F3

Slab 3

7

6

F4

Slab 4

9

4

Fill behind retaining walls

G1

Fill 1

1

12

G2

Fill 2

11

15

Surface finish,

markings, signage, etc.

H1

Finishing

1 to11

6

1060_figure.jpg

Specific technical requirements and constraints in this project are:
• The concrete foundation in ‘Zone 6' should commence only after 3 weeks of completing driven piles in that zone.
• The concrete foundation in ‘Zone 8' should commence only after 4 weeks of completing driven piles in that zone.
• The prefabricated concrete slabs should be placed on concrete columns at least 2 weeks after the supporting columns are cast, and the slabs resting on retaining walls should wait at least 3 weeks after the concerned retaining walls are cast
• Fill in ‘Zone 1' should commence at least 2 weeks after completion of the retaining wall in ‘Zone 2'
• Activity ‘H1' in all zones could commence soon after completion of all preceding activities.

Sub-Problem (i) of Problem 1 in Assignment 2
Prepare the precedence network diagram and identify the critical path(s).

Sub-Problem (ii) of Problem 1 in Assignment 2
Calculate the following values for all the activities: (a) earliest start, (b) latest start, (c) earliest finish, (d) latest finish, (e) total float, and (f) free float

Sub-Problem (iii) of Problem 1 in Assignment 2
a. Identify four vital/ essential material resources for this project. Discuss your plans for the storage of any one key material resource that will be employed in this project
OR
b. Identify four vital/ essential equipment resources for this project. Discuss your measures to ensure the productivity of any one key equipment resource that will be employed in this project
Sub-Problem (iv) of Problem 1 in Assignment 2
Prepare for this project: (a) a work breakdown structure (WBS); OR (b) a resource breakdown structure (RBS)

Problem (2) of Assignment 2:
After three months of commencing the project Alpha Theta (mentioned in Problem 1 of this assignment), your organisation Rho Delta need to commence another project Beta Gamma for the same client to repair three bridges in the region that were affected by recent floods. The AON (i.e. ‘activity on node') network for the project Beta Gamma is shown in the Figure below. Assume all 7 days are working days in every week in this project. Specific details of resource requirements for various activities of this bridge repair contract project Beta Gamma are given in the following Table.

670_figure1.jpg

Figure: AON Network Diagram for the project Table: Activity details and resource

 

Activity

 

Duration (weeks)

Key resource requirements per each day of project activities

Technical staff *

Support staff *

Special Equipment *

Epoxy Material

Fuel

Numbers

Unit cost

Numbers

Unit cost

Numbers

Unit cost

Packets

Unit cost

Litres

Unit cost

A

3

2

$250

4

$160

2

$800

3

$250

60

$1.5

B

4

1

$250

2

$160

1

$800

6

$250

80

$1.5

C

3

2

$250

2

$160

1

$800

2

$250

75

$1.5

D

2

1

$250

2

$160

0

$800

0

$250

90

$1.5

E

3

4

$350

4

$260

0

$800

6

$250

60

$1.5

F

2

3

$300

6

$180

1

$800

0

$250

120

$1.5

G

4

4

$250

2

$160

1

$800

8

$250

150

$1.5

H

3

3

$350

0

$260

2

$800

10

$250

180

$1.5

K

3

2

$250

2

$160

0

$800

8

$250

10

$1.5

L

6

2

$250

0

$160

1

$800

5

$250

100

$1.5


You are required to:
(i) Allocate requisite resources for all activities in this project Beta;
(ii) Carry our resource levelling and compare/ discuss options;
(iii) Discuss your strategies for allocating and levelling multiple resources (including expendable and non-expendable categories) across ;

Problem (3) of Assignment 2:
Already your organisation Rho Delta is having a large ongoing infrastructure development project in this region. In an audit monitoring of this 5-year infrastructure development project having overall budget of 9 billions, the observation at a particular instance in the 4th year indicates that the project has been 87% completed overall and the corresponding "To Complete Performance Index" (TCPI) is 1.265. The Cost Performance Index and Schedule Performance Index figures at that time of audit observation are 1.389 and 0.98. You are required to appraise the current situation as well as completion potentials and then briefly discuss your strategies/ recommendations from project control perspectives.

Attachment:- Resource Planning and Management.rar

Reference no: EM132521465

Questions Cloud

What is the magnitude of his displacement : A baseball player hits a triple and ends up on third base. A baseball "diamond" is a square, each side of length 29 m, with home plate and the three bases
Provide the type of tool or technique : Provide the type of tool or technique and its purpose for use,ICU Ltd and are currently in the process of auditing the accounts receivable department
What is the average speed of the earth : (a) What is the average speed of the earth? (b) What is the magnitude of the average velocity of the earth during this period?
What are the nine steps involved in preparing master budget : What are the nine steps involved in preparing a master budget? Explain each step with some simple examples. Detailed Answer Required
MME80001 Resource Planning and Management Assignment : MME80001 Resource Planning and Management Assignment Help and Solution, Swinburne University of Technology - Assessment Writing Service
Finding themselves engaged in international finance : Due to the process of globalization small and medium sized business are increasingly finding themselves engaged in international finance.
Horizontal distance between end of rifle and bull-eye : A horizontal rifle is fired at a bull's-eye. The muzzle speed of the bullet is 690 m/s. The gun is pointed directly at the center of the bull's-eye
Which cost hierarchy only specific to customer profitability : Which cost hierarchies is only specific to a customer profitability analysis? Activity-based costing and customer profitability analysis
What is the new range-absence of air resistance : Suppose the launch speed is doubled, and the projectile is fired at the same angle above the ground. What is the new range?

Reviews

Write a Review

Mechanical Engineering Questions & Answers

  Package design

Package Design Brief: Assume you are the packaging engineer for a large consumer products company. In this company, the Packaging Design Briefs are initiated by the marketing group and forwarded to the Package Engineering group.

  Mechanical engineering questions

Define dynamic viscosity, Determine the centroid, Pressure due to the height of liquid, Advantage of changing the liquid, Calculate the total moment about the hinge of the seal gate.

  Automatic control

DOF system and Find the differential equation describing the system

  Write a paper on boyle''s law

Write a paper on Boyle's law and describe Compression and Combustion stroke . Also explain Charles's law and illustrate SI engine and CI engine.

  Verify the law for parallelogram of forces

To Verify the law for parallelogram of forces, law for triangle of forces and law of polygon of forces. These laws are very useful to calculate unknown forces in very short time.

  Discharge pressure of the compressor

What is the discharge revised discharge pressure of the compressor.

  The Case for Global Accounting Standards

The role of IFRS in both developing and developed capital markets.

  Wind turbine

Wind turbines are becoming more and more common as a method of energy production, wind turbines by their very nature are dynamic and are subject to and create their own internal and external kinematics and kinetics.

  Advanced design methodologies

8 x product engineering and design review (week 2 – 12), ~3 pages per item which must contain a brief description of the product then delve into concepts such as materials selection, manufacturing methods, life cycle analysis, recyclability and overa..

  Design of absorption column and the cooler

Design of absorption column and the cooler. Process design of other units should be completed along with pipe sizes.

  Determine the maximum total bending moment

Determine maximum total bending moment (static plus dynamic) of the beam under steady-state conditions.

  Force of the water on the gate

Determine the magnitude of the horizontal and vertical components of the force of the water on the gate.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd