Reference no: EM133911723
Project Libre Lab 1: Assigning and Optimising Project Resources
Scenario
For this part of the tutorial we will have the following very simple scenario about a software project:
Mr Salesman has to visit a client in order to sign the agreement by plane
Mr Analyst has to visit the client in order to discuss requirements by plane
Mr Developer A and Mr Developer B are going to develop the project
Mr Tester is going to test if the project works ok
Finally Mr Developer A and Mr Developer B are going to fix the project's bugs
Create the tasks as shown at the following image
Now that we have created the project's tasks, lets add some resources. For the purpose of the project we are going to use the following resources:
Material resources
Tickets for airplane
0,5kg of coffee
Work (people)
Mr Salesman
Mr Analyst
Mr Developer A
Mr Developer B
Mr Tester
Congratulations! Now we have 2 material resources and 4 work resources available for use!
Now, go at the tasks list, double-click on the first task and then click on the ‘Resources' tab. Then, click on the blue button with the two people.
As you can see, you have the list of your project's resources available. You can Control+click to select multiple resources for a task. Control+click at ‘Ticket for airplane' and ‘Mr Salesman' and then click on ‘Assign'.
You can close the windows and click on ‘Resources' at the top menu and then ‘Resources usage' on the left. Congratulations on your first resource assignment! As you can see on the left side of the project you can see where each resource is used and on the right side of the project you can see a detailed view of the resource usage per day.
Now, go on and assign the following resources to the following tasks:
Analyse requirements: Ticket for airplane
Develop project: Mr Developer A, Mr Developer B, 0,5Kg coffee
Test project: Mr Tester
Discuss additional requirements: Mr Analyst
Fix bugs: Mr Developer A, Mr Developer B
Your final Resource usage table should look like this:
And yes, you can go on and change the hours if you wish. Increase or decrease them.
Those were the basics about assigning resources with ProjectLibre. Save your Project!
Project Libre Lab 2: Adding Resource Costs
Project costs calculation
Those were the basics about assigning resources at tasks. Since we are now confident about resources, we are going to estimate the total project costs. Some words about ProjectLibre costing features:
For each resource you can define:
Effective date: From when do the following rates are valid
Standard rate: Rate per hour for normal working hours
Overtime rate: Rate per hour for overtime working hours Get Assignment Help from trusted tutors.
Cost per use: Cost for resource usage independent of duration. You can combine Cost per use with Standard rate or Overtime rate.
Notice: Although you can enter ‘Overtime rate', I have not figured out how to actually use it.
Normally you would use standard and overtime rate for your employees and cost per use for materials or contract jobs.
Also, for each resource you can define different rate tables (A to E). When assigning a resource to a task you can choose which rate table to use.
Okay, now let's go and add some costs. Click on the Resources table and add double-click each task to add the following:
Ticket for Airplane: Cost per use: 200
0.5Kg of coffee: Cost per use: 8
Mr Salesman: Standard Rate: 15/hour
Mr Analyst: Standard Rate:20/hour
Mr Developer A: Standard Rate:10/hour
Mr Developer B: Standard Rate:10/hour
Mr Tester: Standard Rate:5/hour
Now we want to see the estimated project cost. Go to Resource usage and Right click->Insert column and choose ‘Cost'
You should see the column with the cost per Resource-Task
In ProjectLibre you also have the following options:
View cost per Task
Click on ‘Task' on the top menu and then ‘Task Usage' on the left and then right click on the columns to add ‘Cost' column as we did before. You can know see how much each task costs.
View total project costs
Click on ‘View' on the top menu and then ‘Reports'. Choose report ‘Project details'. You can see the Scheduled, Remaining and Actual costs if you scroll a little down
Those were the basics about calculating costs with ProjectLibre. Save your Project!
Attachment:- Assigning and Optimising Project.rar