Problems 5-1 through 5-2 (Graded)

5-1 Earned Value Calculation

Your project has four activities. Below is the current status of each activity.

Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule.

Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

Activity C is finished. It finished 2 weeks late. It cost $100,000. And it was planned to have cost $110,000.

Activity D is beginning its fourth of a planned 6-week schedule. It has cost $200,000 so far. It was estimated to cost $450,000 when finished. It is approximately 55% complete.

Using this data, calculate the following.

1. What are the PV, EV, and AC for each of the activities and the complete project?

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

3. Assess the project performance to date? Do you get to have the celebration?

Reference no: EM13273401

Questions Cloud

Fantasy sex normal or problematic : Most of us have from time to time fantasized about sexual events they we really do not want to occur. For example research tells us that over 30% of females fantasize about being raped, forced top have sexual intercourse or sexually assaulted. Where ..
Technology and globalizationgen : Technology and GlobalizationGEN499 wk5 dq1
Discuss how managed care sales and marketing : Discuss how managed care sales and marketing have evolved over recent decades, and how these may possibly evolve over the decades ahead.
Same time increasing accessibility of healthcare services. : Discuss which strategies you think will be effective in eliminating waste, control the costs of health services, while maintaining quality of those services and at the same time increasing accessibility of healthcare services.
Earned value calculation-what are the PV-EV and AC : Activity A was to have cost $150,000 when complete. Its costs so far are $45,000. It is 35% complete. The activity has completed 5 weeks of a planned 15-week schedule. Activity B is at the end of week 2 of a planned 4-week effort. It is 45% complete...
The sistine chapel appears in present-day culture : Consider how and where imagery from the Sistine Chapel appears in present-day culture. How has some of the imagery in the chapel become pop-culture icons?
What is general and special revelation : What is general and special revelation? What is the purpose of revelation?
Statements taken in violation of the miranda rule : Statements taken in violation of the Miranda rule may be used to impeach a defendant that testifies inconsistently with his confession. However, an involuntary confession cannot be used for impeachment. What justifies the distinction between these tw..
Stringmethod compareto to compare two strings : Write an application that uses Stringmethod compareTo to compare two strings i

Reviews

Write a Review

Other Subject Questions & Answers

  Individual business decisions

To what extent can individual business decisions (as opposed to economic forces) explain deterioration in working conditions for many workers?

  Basic minimum of health care

Should everyone be entitled to a basic minimum of health care or to the exact same health care?

  What potential positive and negative ramifications

What potential positive and negative ramifications could result from offering payment incentives for physician participation in Medicare programs?

  Multiple interpretations-differetn people read same story

Explain how and why multiple interpretations can occur when differetn people read the same story.

  The idaho supreme court rules against

The Idaho Supreme Court rules against Jiffy Mart in a case against Kwik Stop Stores, Inc. Jiffy Mart files an appeal with the United States Supreme Court.

  Problem of economic gender inequality

Critically discuss some steps that may be taken to remedy the problem of economic gender inequality? Will equal pay for the same job be enough to solve the problem?

  Reflect the public’s interests and concerns

What are the most effective means by which Americans can have an impact on what public officials do so that public policy will reflect the public’s interests and concerns.

  Why do triggers have such an impact on our interactions

Why do triggers have such an impact on our interactions? give an example of how a trigger might shape an interaction in a negative way

  The terms hispanic and latino are umbrella terms

The terms hispanic and latino are umbrella terms for people from many different spanish speaking culturesin th ewestern hemisphere. Although the grouping includes a wide range of cultures thereis evidence of the formation of a panethnic identity. Def..

  Major theme that had the most impact in the colonial era

Choose a major theme that had the most impact in the Colonial Era. Analyze it in terms of its strengths and weaknesses. How did it reflect the needs of society at that time?

  Write critical appraisal of journal infectious disease trend

Write down the critical appraisal of peer-reviewed journal, newspaper, or magazine article which you have recently read concerning one infectious disease trend.

  Invention of so many new devices

Understood, but do you think the "invention" of so many new devices, appliances and gizmos has actually caused more domestic work for us all? Make answer as brief as possible.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd