Earned value calculation

Assignment Help Other Subject
Reference no: EM13203350

Earned Value Calculation 
You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 4:
Actual cost to date = $88,800
Planned expenditures to date = $101,000
The CFO is excited and has sent you an email congratulating you for being 12.07% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we 'really' doing? To understand the true project performance, we need to apply earned value techniques. 
The missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 7 tasks scheduled to be complete by the end of month 4 have actually been completed. Task 7 isn't even started! This information gives you the final data you need to apply 'Earned Value' and develop an objective analysis.
1. What are the PV, EV, and AC for the project at the end of month 4?
2. What are the SV, CV, SPI, and CPI for the project?
3. Assess the project performance to date? Do you get to have the celebration? 

5-2 Earned Value Calculation

Project Schedule and Budget Data Provided:
Task Duration (days) Predecessor(s) Budget
A 2 --- $1,600 
B 5 --- $4,000 
C 3 A $14,050 
D 4 B $5,800 
E 6 B $12,000 
F 4 C,D $5,200 
G 3 E $3,900 
Project Totals: $46,550 

Status of the project at the end of day 6:
Task % Complete Actual Cost of Work Performed
A 100% $1,800 
B 100% $4,500 
C 90% $13,500 
D 10% $500 
E 0% $0 
F 0% $0 
G 0% $0 

 
Project Network Diagram


Critical Path (CP) = B - E - G = 14 days

Tasks Duration (Days)
A A A

B B B B B B

C C C C

D D D D D

E E E E E E E

F F F F F

G G G G

0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

 
1. Calculate the schedule variance for each task and the total project.

2. Calculate the cost variance for each task and the total project.

3. What is your assessment of the project at this time? 

Reference no: EM13203350

Questions Cloud

Micro level to enhance its effectiveness : Describe an organizational example as to how information is managed at macro level and micro level to enhance its effectiveness.
Find when planned aggregate expenditure is less : The table below illustrates values for consumption spending, saving, and planned investment in a closed, private economy. Aggregate Output Consumption Saving Planned Investment Planned Aggregate Unplanned Inventory Change Expenditure (GDP = Y) (C) ..
Resolutions to issues presented by animal experimentation : Compare two steps that would be most effective in refining soloutions to the problem and resolutions to the issues presented by animal experimentation.
Find what time will train b catch up to train a : Trains A and Bare traveling in the same direction on parallel tracks. Train A is traveling at 60 miles per hour and train B is traveling at 64 miles per hour.
Earned value calculation : You are 4 months into a 6 month project. The project is linear, which means that the progress and spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project..
Explain what time did begin and end trip : Before noon he averaged 60 miles per hour, and after noon he averaged 50 miles per hour. At what time did he begin his trip and when did he end it?
Determine how much money did you earn last week : which of the following three expressions uses the economists definition of money a. how much money did you earn last week b. when i go to the store, i always make sure that i have enough money.c. the love of money is the root of all evil
Find the exact area and perimeter : The bases of an isosceles trapezoid are 18cm and 24cm. If one of the angles of this trapezoid is 120 degrees, find the exact area and perimeter.
How long age was the artifact made : A wooden artifact from an ancient tomb contains 80 percent of the carbon-14 that is present in living trees. How long age was the artifact made? (The half-life of carbon-14 is 5730 years.)

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd