Discuss the basis of a breach of contract claim by college

Assignment Help Business Law and Ethics
Reference no: EM13869556

Instructions: Write a 3-5 page paper in response to the fact scenario provided below. The paper must be double spaced and include a list of works cited (not included in the page count). You may use outside sources for this paper but you are not required to. All of the information you need to complete this paper is provided in the course materials. However, you still need to include in-text citations when you use any source in this paper.

Fact Scenario - Part 1: Contractors, Inc. contracted with College to build a 20­room, 2 story classroom building, constructed of gray bricks, and according to architectural specifications provided by College.  The building is to be located on campus at the corner of Campus Way and Academic Avenue at a contract cost of $5,000,000, and to be completed by August 1, 2013. This August 1 deadline would give College just enough time to move into the building and prepare the inside for classes to begin August 14. College informed Contractors that time was of the essence and that this is a tight timeline for moving into the new building.

The valid, written contract read, in part, as follows:

CONTRACT

We, the undersigned, party of the first part, hereinafter College, and party of the second part, hereinafter Contractors, Inc. hereby agree to the following:

1) Contractors, Inc. will build a 20­room, 2­story classroom building constructed of gray bricks, at the corner of Campus Way and Academic Avenue, in accordance with the architectural specifications stipulated by College and attached hereto and in compliance with Maryland building codes and regulations for new construction;

2) Contractors, Inc. will complete the construction project at a total cost of $5,000,000, inclusive;

3) Contractors, Inc. will complete the construction project not later than August 1, 2013. Time is of the essence.

Fact Scenario ­ Part 2

On May 28, 2013, after the construction was more than half completed, the cost of bricks used for construction of the building increased substantially in the marketplace so that Contractors could no longer construct the building for $5,000,000. Contractors told College that it would need an additional $250,000 to complete the building using gray bricks on the exterior. College agreed to modify the original contract to increase the construction costs by $250,000, bringing the total cost of the project to $5,250,000. 

College and Contractors drew up the following contract modification as an addendum to the original contract:

CONTRACT ADDENDUM

We, the undersigned, party of the first part, hereinafter College, and party of the second part, hereinafter Contractors, Inc. hereby agree to the following modification to the original agreement:

1) In addition to the contractual agreed upon cost of $5,000,000, College will pay Contractors, Inc. an additional $250,000 to build a 20­room, 2­story classroom building constructed of gray bricks, at the corner of Campus Way and Academic Avenue;

2) College will pay Contractors, Inc. for the completed project, the sum of $5,250,000 not later than August 7, 2013;

3) This modification does not in any way change any other terms of the original contract

After the contract modification, Contractors continued to work on the building but did not meet the August 1 completion deadline. The building was completed on August 21, 2013.

In the meantime, fall semester classes began at College on August 14, making it necessary for College to lease classroom space from August 14­September 4, 2013. College necessarily had to hold classes in the leased space for 3 weeks until September 4 because it took 2 weeks (from August 21) for College to move into the new building and prepare it for classes. The lease costs were $5,000 per week, for a total of $15,000 for 3 weeks.

College paid Contractors $5,000,000 on September 4, but refused to pay the additional $250,000. College filed suit against Contractors for breach of contract. Contractors countersued College for breach of contract

Questions to Address in your Paper:

Part I: Discuss the basis of a breach of contract claim by College against Contractors, any potential damages College could claim and the likely outcome of a lawsuit.

Part II: Discuss the basis of a breach of contract claim of Contractors against College, any potential damages Contractors could claim and the likely outcome of a lawsuit.

Reference no: EM13869556

Questions Cloud

Give an advantage of your method as compare to blocking send : Give a fourth method that is similar to a blocking send but has slightly different properties. Give an advantage and a disadvantage of your method as compared to blocking send.
Why does ratio of read operations to write operations matter : Why does the ratio of read operations (those not updating internal state vari- ables) to write operations (those updating internal state variables) matter?
The cost method to account for treasury stock transactions : Tulip Corporation uses the cost method to account for treasury stock transactions.
What problems would have to be solved to do it the other way : Most assemblers for the x86 have the destination address as the first operand and the source address as the second operand. What problems would have to be solved to do it the other way?
Discuss the basis of a breach of contract claim by college : Discuss the basis of a breach of contract claim by College against Contractors, any potential damages College could claim and the likely outcome of a lawsuit
What is the maximum length of a symbol : Scrooge has declared that symbols may consist only of letters, except the letter Q, which is forbidden. What is the maximum length of a symbol? Describe your encoding scheme.
The journal entries of sampress company : On January 1, 2010, Sampress Company adopts a compensatory share option plan for its 50 executives.
What is difference between instruction and pseudoinstruction : What is the difference between an instruction and a pseudoinstruction? What is the difference between the instruction location counter and the program counter, if any?
Show steps needed to look up ann arbor using binary search : Show steps needed to look up Ann Arbor using binary search on the following list: Ann Arbor, Berkeley, Cambridge, Eugene, Madison, New Haven, Pasadena, Santa Cruz, Stony Brook, Westwood, and Yellow Springs.

Reviews

Write a Review

Business Law and Ethics Questions & Answers

  Legal environment of business caselet

The assignment in Law deals with the topic "Legal Environment of Business". A case study about Mary, a newly joined employee who is working in the USA and Europe. She faces few issues at her work place in Europe and tries to talk to her manager who s..

  Business ethics & legal issues caselet

This assignment is about the concept of Business Ethics & Legal Issues. The laws relating to these can be found in Antitrust laws. These laws are concerned with those large corporations which have a majority of market share, mergers and acquisitions.

  Questions on business law and ethics

Examples of securities that are exempted from the registration provisions of the 1933 Act and involving misstatement of material facts in a prospectus.

  Discuss the doctrine of ratification of pre-incorporation

With the aid of a decided cases, discuss the doctrine of ratification of pre-incorporation contract.

  Discuss the extent of phoenixing activity

It has been estimated that about 6,000 phoenix companies operate in Australia, costing government and the community hundreds of millions of dollars per year and impacting on individuals.

  Application of law to facts

Company Law, Application of Law to Facts and Conclusion.

  Question on business law and ethics

This assignment related to business law.

  Questions on business law

Answer all the questions under business law.

  Iidentify the issue raised by the facts

Iidentify the issue(s) raised by the facts, identify the relevant legal principles, apply the relevant legal principles to the facts, reach a conclusion.

  Evaluation of software development

Prepare a report and present an evaluation of the subsequent methodologies for software development in terms of cost, resources and time.

  Business value and ethics

Business value and ethics,  Bart agrees to put Sam's Super Bowl champion-ship autographed football in his sports store to sell for $1,500. Sam agrees to pay Bart a 15% commission for selling the ball. If Joe comes in the sports store and offers Bart ..

  Explain what is meant by income by ordinary concepts

Advise what tax consequences arise in respect of the payments.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd