Question 1. (a) Using the Murray Loop test, determine the distance to an earth fault on one of the cores of a uniform three-core underground cable. Ra = 2 ohms, Rb = 1 ? and the cable length is 300 m.

(b) If the cable measurement is accurate to ±1% what length of excavation would be required to locate the fault?

Question 2. A cable run consists of 100 m of 120 mm2 three-core cable jointed to 100 m of 240 mm2 cable. The ratio of the potentiometer resistances in a Murray Loop test, Rb/(Rb + Ra), is 1/3.

For an earth on one core of the cables, determine the location of the fault.

Question 3. A Varley Bridge is connected to a faulty three-core copper cable by two identical copper leads of resistance Rl.

(a) Show that for the initial reading (connection to earth);

2Rx = 2Rc - Ri .............................. (1)

where Rc is the resistance of the cable core

Ri is the initial reading of the bridge

Rx is the cable resistance to the fault from the bridge and for the final reading:

2Rc = Rf - 2Rl .............................. (2)

where Rl is a lead resistance

Rf is the final reading resistance.

Then by substituting (2) in (1) and rearranging the equation, show:

Rx + Rl = ( Rf - Ri)/Rf (Rc + Rl)

(b) By multiplying the rhs brackets and collecting terms, show the effect of the leads is given by:

Rx = ((Rf-Ri)/Rf)Rc - RlRi/Rf

i.e. = effect with no leads - ratio of initial and final readings × lead resistance

(c) Determine the distance to the fault by modifying the expression in (b) and using

Rx/Rc = x/L

where x is the cable distance to the fault and L is the length of a cable core.

Derive an expression for x, the distance to the fault.

(d) Using R = ρL/A

where ρ is the resistivity,

L is the length

and A is the cross-sectional area of a cable core

show that Rl = RcAcLl/AlLc (where Lc = L)

and by substituting for Rl show that the distance to the fault is given by:

x =[(Rf - Ri)/Rf - Ri/Rf AcLl/AlL]L

(e) Determine the distance to a fault on a 200 m, 120 mm2 copper cable if copper 10 mm2 test leads of length 10 m are used and Ri/Rf = 0.2.

Question 4. FIGURE 1 shows a Wheatstone Bridge connection used to determine the location of a fault on a cable in which two cores are of different cross-sectional area (the Murray Fisher method). Ignoring test lead resistance, show that:

(a) For the first reading position, the resistance to the fault, Rx, is given by

Rx =  (Rb1/(Ra1 + Rb1))*(Rc1 + Rc2)

(b) For the second reading position and substituting for Rc1, the distance to the fault, x, is given by:

x = Rb1/(Ra1 + Rb1) × ((Ra2 + Rb2)/Rb2) × L

x = Rb1/Rb2 * [(Ra2 + Rb2)/(Ra1 + Rb1)] x L

(c) If the cable tested is 100 m in length, Ra1 is 1.5 ohms, Rb1 is 1.0 ohm and Ra2/Rb2 = 0.8, calculate the distance to the fault.

1133_figure.jpg

FIG. 1

Verified Expert

This assignment examines various tests such as Wheatstone bridge, Murray Loop test, Varley bridge test and Murray Fisher test, which are used to locate faults and fault resistance on underground core cables.

Reference no: EM132037534

Questions Cloud

Describe the types of innovations or improvements : Describe the types of innovations or improvements that have come from involving the target customer in the supply chain.
Golden age of television : During this time, which genre was popular with early adopters of television but no longer as popular as ratings expanded?
What do you think typical assets and liabilities would be : What do you think typical assets and liabilities would be? What do you think an individual's retained earnings would consist of?
What are the six elements of a buisness contract : What are the six elements of a buisness contract? What are the elements?
Determine the location of a fault on a cable : Determine the location of a fault on a cable in which two cores are of different cross-sectional area - Determine the distance to the fault by modifying
What is the npv of project in worst-case scenario : We are evaluating a project that costs $104617, has a seven-year life, and has no salvage value. What is the NPV of the project in worst-case scenario?
What is the npv of the project in best-case scenario : We are evaluating a project that costs $111518, has a seven-year life, What is the NPV of the project in best-case scenario?
Emotional intelligence to maximise workplace : What can a team member do to encourage others to develop their own emotional intelligence to maximise workplace outcomes and build productive relationships?
What is internal rate of return : King’s Department Store is contemplating the purchase of a new machine at a cost of $17,180. What is the internal rate of return?

Reviews

Write a Review

Electrical Engineering Questions & Answers

  Lithium ion battery technology

The paper includes Lithium ion battery technology with its advantages and disadvantages. The paper discusses about the Lithium air battery in which detailed reactions of Lithium with air including nonaqueous as well as aqueous are given.

  Power transformers and tariffs

Construction of different types of power transformer, significant energy savings

  Paper on orthogonal frequency-division multiplexing

This document is shown a paper on Orthogonal frequency-division multiplexing with advantages, disadvantages and uses.

  Function of the hmi in a scada system

This assignment contains electronics engineering questions like State the commonly found components of a SCADA (Supervisory control and data acquisition) system. and decribe the function of the HMI in a SCADA system.

  Resultant waveform of the odd harmonic series

Prepare an Excel graph showing the individual components and summated resultant waveform of the odd harmonic series resulting in an approximate square wave.

  Explain scada system

Explain the function of the HMI in a SCADA system.

  Design a 2-digit 24 second shot-clock

Design a 2-digit 24 second "shot-clock" countdown timer with pushbutton controller.

  Model a discrete-time system

To understand di erent signal models To be able to model a discrete-time system and design simple signal processing algorithms.

  Draw a relay construction diagram

Draw a relay construction diagram and briefly explain the operation of a relay.

  Frequency division multiplexing

Write a short technical report on Frequency Division Multiplexing

  Impact of electron energy

Briefly discuss the impact of electron energy, electron current and target on the Bremsstrahlung generated.

  Traffic light controller

The schematic of the traffic light controller

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd