Determine the critical path for the project

Assignment Help Other Subject
Reference no: EM132011199

QUESTION 1

Read the article below and answer the questions that follow.

Brian Smith, network administrator at Advanced Energy Technology (AET), has been given the responsibility of implementing the migration of a large data centre to a new office location. Careful planning is needed because AET operates in the highly competitive petroleum industry. AET is one of five national software companies that provide an accounting and business management package for oil jobbers and gasoline distributors. A few years ago, AET jumped into the °application service provider" world. Their large data centre provides clients with remote access to AET's complete suite of application software systems. Traditionally, one of AET's primary competitive advantages has been the company's trademarks IT reliability. Due to the complexity of this project, Brian will have to use a parallel method of implementation. Although this will increase project costs, a parallel approach is essential if reliability is not to be compromised.

Currently, AET's data centre is located on the second floor of a renovated old bank building in downtown Corvallis, Oregon. The company is moving to a new, one-level building located in the recently developed industrial complex at the Corvallis International Airport. On February 1, Brian is formally assigned the task by the Vice-President of Operations, Dan Whitmore, with the following guidelines:

- From start to finish, it is anticipated the entire project will take three to four months to complete.
- It is essential that AET's 235 clients suffer no downtime.

Whitmore advises Brian to come back to the Executive Committee on February 15, with a presentation on the scope of the project that includes costs, "first-cut" timeline, and proposed project team members. Brian had some preliminary discussions with some of AET's managers and directors from each of the functional departments and then arranged for a full-day scope meeting on February 4 with a few of the managers and technical representatives from operations, systems, facilities, and applications. The scope team determined the following:

- Three to four months is a feasible project timeline and first-cut cost estimate is $80,000 - $90,000 (this includes the infrastructure upgrade of the new site).
- Critical to the "no-downtime" requirement is the need to completely rely on AET's remote disaster recovery "hot" site for full functionality.
- Brian will serve as project manager of a team consisting of one team member each from facilities, operations/systems, operations/telecommunications, systems & applications, and customer service.

Brian's Executive Committee report was positively received and, after a few modifications and recommendations, he was formally charged with responsibility for the project. Brian recruited his team and scheduled their first team meeting (March 1) as the initial task of his project planning process.

Once the initial meeting is conducted Brian can hire the contractors to renovate the new data centre. During this time Brian will figure out how to design the network. Brian estimates that screening and hiring a contractor will take about one week and that the network will take about two weeks. The new centre requires a new ventilation system. The manufacturer's requirements include an ambient temperature of 67 degrees to keep all of the data servers running at optimal speeds. The ventilation system has a lead-time of three weeks. Brian will also need to order new racks to hold the servers, switches and other network devices. The racks have a two-week delivery time.

The data centre supervisor requested that Brian replace all of the old power supplies and data cables. Brian will need to order these as well. Because Brian has a great relationship with the vendor, they guarantee that it will take only one week lead time for the power supplies and the data cables. Once the new ventilation system and racks arrive, Brian can begin installing them. It will take one week to install the ventilation system and three weeks to install the racks. The renovation of the new data centre can begin as soon as the contractors have been hired. The contractors tell Brian that construction will take 20 days. Once the construction begins and before Brian installs the ventilation system and racks, the city inspector must approve the construction of the raised floor.

The city inspector will take two days to approve the infrastructure. After the city inspection and after the new supplies and cables have arrived, Brian can install the power supplies and run the cables. Brian estimates that it will take five days to install the power and one week to run all of the data cables. Before Brian can assign an actual date for taking the network off line and switching to the hot remote site, he must get approval from each of the functional units ("Switchover Approval").

Meetings with each of the functional units will require one week. During this time, he can initiate a power check to ensure that each of the tracks has sufficient voltage. This will require only one day.

Upon completion of the power check, he can take one week to install his test servers. The test servers will test all of the primary network functions and act as a safeguard before the network is taken off line. The batteries must be charged; ventilation installed, and test servers up and running before management can be assured that the new infrastructure is safe, which will take two days. Then they will sign off the Primary Systems check, taking one day of intense meetings. They will also set an official date for the network move.

Brian is happy that everything has gone well thus far and is convinced that the move will go just as smoothly. Now that an official date is set, the network will be shut down for a day. Brian must move all of the network components to the new data centre. Brian will do the move over the weekend - two days - when user traffic is at low point.

1.1 Develop a WBS for this project
1.2 Discuss the five approaches that Brian can use to develop a WBS that Brian can use. Which approach would you recommend?

QUESTION 2

The table below gives the duration estimates in days for a construction projection.

Activity

A

Predecessor

-

Optimistic

Most Likely

Pessimistic

 

B

-

1

3

6

C

-

3

5

8

D

A

9

11

20

E

A

2

5

7

F

B

6

9

20

G

C

5

10

22

H

E, F

3

5

12

I

D

4

7

9

J

G

6

9

13

K

H,J

3

4

6

L

I,K

7

10

23

2.1 Determine the expected completion time for each activity. Round off answers to the nearest whole number

2.2 Construct an AON network for the activities of this contract.

2.3 Determine the critical path for the project by calculating the slack for each activity.

QUESTION 3

With the aid of an example, critically discuss how performing activities in parallel may accelerate project duration.

Assignment Guidelines

- The length of your answers to each question should be in line with the mark allocation
- Your assignment should include a table of contents page
- Text: Font: Arial or Times New Roman size 12; Line spacing: 1.5
- All text must be justified at each margin
- Your answers must include any theories, charts, tables or exhibits necessary to support your analysis and recommendations
- Ensure that readings are not merely reproduced without original critical comments and views. Cohesive and logical arguments reflecting original thinking are encouraged
- References: At least 4 sources of references (textbooks, journals, press reports, intemet articles, etc.) must be utilised in the body of your assignment. All sources must be appropriately listed under your Bibliography. Harvard system of referencing to be used. Students will be penalised up to 10% for incorrect or no referencing.

Reference no: EM132011199

Questions Cloud

What criteria would be used for student admissions : What criteria would be used for student admissions (ex. SAT scores, ACT scores, personal essays, high school GPA, community service, extracurricular activities)
What is the maximum height above the ground the water : The water reaches a garden 15 m away. Find the velocity of the water leaving the hose. What is the maximum height above the ground the water reaches?
What is the after-tax cost of the preferred equity : What is the after-tax cost of the following preferred equity? The par value of the preferred share is $100 and the annual dividend is 7.5 %.
Calculate terminal velocities : How long will it take for each skydiver to reach the ground (assuming the time to reach terminal velocity is small)?
Determine the critical path for the project : PGDPM — PROJECT SCOPE AND TIME MANAGEMENT - Determine the expected completion time for each activity. Round off answers to the nearest whole number
Prepare general journal entries to account the equipment : Prepare general journal entries to account the equipment from 1 July 2011 to 30 June 2014 in accordance with the requirements of AASB 116 and AASB 136
Find the centripetal acceleration of the particle : A centrifugal machine rotates at 50,000 rpm. A particle is 20 cm away from the rotational center. Find the centripetal acceleration of the particle.
What is the history of rings and what do circles mean : What is the history of rings and what do circles mean? Why there are five circles for Olympic Rings? I need an essay about the relationships between Olympic.
What was the aim of the study : 1. What was the aim of the study? 2. Where did they collect the data? 3. What was the methodology? 4. How was the data analyzed?

Reviews

Write a Review

 

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd