Determine necessary control limits - quality and performance

Assignment Help Advanced Statistics
Reference no: EM13187116

1. The Young Company produces plastic bottles to customer order. The quality inspector randomly selects four bottles from the bottle machine and measures the outside diameter of the bottle neck, a critical quality dimension that determines whether the bottle cap will fit properly. The dimension (in.) from the last six samples are

 

Bottle

Sample

1

2

3

4

1

0.604

0.612

0.588

0.600

2

0.597

0.601

0.607

0.603

3

0.581

0.570

0.585

0.592

4

0.620

0.605

0.595

0.588

5

0.590

0.614

0.608

0.604

6

0.585

0.583

0.617

0.579

a) Assume that only these six samples are sufficient, and use the data to determine the necessary control limits.

b) Suppose the specification for the bottle neck diameter is 0.600 +/- 0.050 inches. If the population standard deviation is 0.013 inches, and the firm is seeking four-sigma quality, is the process capable of producing the bottle?

2. As a hospital administrator of a large hospital, you are concerned with the absenteeism among nurses' aides. The issue has been raised by registered nurses, who fell they often have to perform work normally done by their aides. To get the facts, absenteeism data was gathered for the last three weeks, which is considered a representative period for future conditions. After taking random samples of 64 personnel files each day, the following data were produced:

Day

Aides Absent

1

4

2

3

3

2

4

4

5

2

6

5

7

3

8

4

9

7

10

2

11

3

12

2

13

1

14

3

15

4

Because your assessment of absenteeism is likely to come under careful scrutiny, you would like a type 1 error of only 1 percent. You want to identify any instances of unusual absenteeism. If some is present, you will have to explore them on behalf of the registered nurses.

a) Design the appropriate control chart.

b) Based on your chart and the data from the last 3 weeks, what can you conclude about the absenteeism of nurses' aides?

3. A textile manufacturer wants to set up control charts for irregularities (e.g. oil stains, shop soil, loose threads, etc.) per 100 square yards of carpet. The following data were collected form a sample of 20 100-square-yard pieces of carpet

Sample

Irregularities

1

11

2

8

3

9

4

12

5

4

6

16

7

5

8

8

9

17

10

10

11

11

12

5

13

7

14

12

15

13

16

8

17

19

18

11

19

9

20

10

a) Using these data, set up a c-chart with z = 3.

b) Suppose that the next five samples had 15, 18, 12, 22 and 21 irregularities. What would you conclude?

4. A critical dimension of the service quality of a call center is the wait time of a caller to get a sales representative. Periodically, random samples of three customer calls are measured for time. The results of the last four samples are in the following table:

Sample

Time (sec)

1

495

501

498

2

512

508

504

3

505

497

501

4

496

503

492

a) Assuming that management is willing to use three-sigma control limits, and using only the historical information contained in the four samples, show that the call center access time is in statistical control.

b) Suppose that the standard deviation of the process distribution is 0.577. If the specifications for the access time are 500 +/- 18 seconds, is the process capable? Why or why not? Assume three-sigma quality.

Reference no: EM13187116

Questions Cloud

How much is tax for social security and medicare combined : Molly Flynn , an accountant fo Coor Corporation, earns $106,200 from January to June. In July, Molly earned $8,000. Assume a tax rate of 6.2% for Social Security on $106,800 and Medicare of 1.45%. How much is the tax for Social Security and Medica..
What is a graph that shows d versus v : If a cylindrical container is filled to a depth of d cm by pouring in V cc of liquid, what is a graph that shows d versus V?
State sample of hydrocarbon compund containing only c : A 6.52 g sample of hydrocarbon compund containing only C and hydrogen produced 20.5 g of CO2. A 9.29 ml sample weighing 21.6 mg was collected over water at a pressure of 796 torr at 25 C
How would a decrease in the reserve requirement effect : How would a decrease in the reserve requirement effect the (a) size of the money multiplier (b) amount of excess reserves in the banking system and (c) extent to which the system could expand the money supply through the creations of checkable dep..
Determine necessary control limits - quality and performance : Design the appropriate control chart - based on your chart and the data from the last 3 weeks, what can you conclude about the absenteeism of nurses' aides
State how many moles of khp were weighed out : How many moles of KHP were weighed out? How many moles of NaOH were required to neutralize the KHP that was weighed out?
Definition of loyalty is conformity : What does Henry Steele Commager mean when he writes that the new definition of loyalty is "conformity"?
State what is the normality of a solution prepared : What is the normality of a solution prepared from 10 ml 0.6 N nitric acid by diluting it to 60 ml
Discuss the five economic principles : Select one principle and create an additional example that will help students understand that principle better. Based on the five economic principles discussed, give your opinion on the one which is the most important and useful concept in your lif..

Reviews

Write a Review

Advanced Statistics Questions & Answers

  Quality control analysis

Determining the root causes

  Identify the type of bias or error

A randomized controlled trial was implemented to assess whether a human papillomavirus (HPV) vaccine prevents pre-cursors of cervical cancer in women between the ages of 15 and 25 years.

  Project probability with variance

A project has an expected duration of 34 weeks with a critical path variance of 6. Suppose the project network is given and the critical path is identified on the network. Suppose the normal time, crash time, and the associated cost for each activ..

  Forecast errors for sophisticated models

All forecasts contain some error whether the model is simple or sophisticated, because forecasts are predictions of the future based on past data. Forecast errors can be caused by changes in conditions that generated the past data

  Probability and statistics

The tubes produced by a machine are defective. If six tubes are inspected at random , determine the probability that.

  Future value-concept and application

In a Word document, upload your answers to the following questions below. Very importantly - show all your work. If your final answer is wrong, you can still receive partial credit if you show all of your steps and demonstrate a good understanding..

  Applications of probability in business decisions

In what situations might you use probability as a manager to approach business-related problems? What are the advantages to using probability concepts in business decisions?

  Straight-line and declining balance depreciation

Classic Irons, Inc. purchased Manufacturing Equipment with an expected useful life of five years of 5,000 hours of usage. The equipment was purchased on Jan. 1, 2008, for $460,000.

  Importance of math in analyzing business

What is an independent variable? What is a dependent? What is the relationship between independent and dependent variables? What is the purpose of differentiating these terms?

  Description of long term debtor

For the year ending June 30, 2008, the New Corporation has current assets of $275,000 and total assets of $900,000. It also has current liabilities of $100,000, equity of $200,000, and retained earnings of $300,000.

  Capacity planning and facility location

Analyze the key concepts related to capacity planning and facility location for your business. Develop an appropriate level, chase, or hybrid aggregate plan to maintain a competitive advantage. Provide a rationale for developing the type of plan yo..

  Basic accounting principles

You have been nominated by your institution for a seminar because of your proficiency in basic accounting concepts. The participants and audience include college professors, practicing CPAs, and fellow students.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd