Describe proposed drainage and pumping system

Assignment Help Other Subject
Reference no: EM132138637

Assignment

The purpose of this assignment is for the student to design an electrical distribution system for the coal mine illustrated in Figure.

1179_figure.jpg

Figure 1: schematic diagram of underground workings.

The mine is to operate a single retreating long wall coalface at any one time. Whilst this face (panel 1 on the figure) is in production the next panel is under development. The physical dimensions of each airway in the system are as listed in Table 1. All airways excepting the drift and shaft are developed fully within the flat coal seam of 3m thickness. A ventilation fan is located at the top of the return ventilation shaft that can in emergency situations act as a second means of egress.

Coal clearance is undertaken by conveyor, conveyors are located in airways 1-2, 2-5, 5-7, 5-6, 7-10, 10-11, 11-12, 12-13 and 7-14 with an armoured face conveyor located on ht face 6-8. Development is undertaken using continuous miner. Table 2 lists the electrical machine requirements and location for the time frame under consideration.

Distribution voltage at the mine is 13.2 kV.

The purpose of the exercise is to devise an electrical distribution system to service the current and possible future requirements of the mine. The student is to consider the following:

- Cables and cable couplings
- Switchgear
- Transformers
- Power centres
- Distribution and utilisation systems
-Electrical safety
- Control requirements
- Any other requirements
- Power factor correction (if required)

All assumptions need to be detailed and justified. The results should be presented as a report; no page limit is specified, with diagrams and other data as required. Students should note that there is no single answer to this design, marking will be based on the robustness of the system, the inherent safety of the system and the ability of the system to be expanded. In order to aid on the last criterion it is expected that the life of an individual panel is of the order of 6 months under the current production schedule, the extracted length of all panels in the mine is 1950m, i.e. a 50 m barrier pillar is required.

Table 1: Dimensions of mine.

Branch from

Branch to

Length (m)

Width (m)

Height (m)

Comments

1

2

2400

5

4

Intake drift 1 in 6

2

3

200

5

3

Cross cut

2

5

150

5

3

Intake

5

7

100

5

3

Intake

5

6

2000

5

3

Panel 1 intake airway

6

8

250

5

3

Panel 1 face

8

9

2200

5

3

Panel 1 return airway

7

10

650

5

3

Intake

10

11

200

5

3

Cross cut

11

12

400

5

3

Return

12

13

500

5

3

Panel      2    return      airway      dead      end

development

12

9

100

5

3

Return

7

14

2150

5

3

Panel 2 intake airway development

9

3

350

5

3

Return airway

3

4

400

4.5

 

Return shaft (circular)

Table 2: Major items of electrical equipment to be considered within the exercise

Item of equipment

location

Power (kW)

Voltage (V mis)

Comments

Panel     1     shearer

(coal cutter)

Anywhere on coal face

500

1100

Max length of cable from intake end of face = 250m

Panel       1      return

end AFC drive

Node 8

350

1100

Directly         coupled        to

intake end AFC motor

Panel       1      intake

end AFC drive

Node 6

350

1100

Directly         coupled        to

return end AFC motor

Stage              loader

motor

200m from node

6      in      panel      1
intake

250

1100

Phased to start prior to AFC

Panel 1 hydraulic power pack

150m from node

6

2 x 180

1100

2 x 110 kW pumps

Panel                      1

Ancillaries

130m from node 6

po

550

Max length of cable from here is 380m

Panel 1 belt drive

Node 5

400

1100

 

Main belt drive

Node 2

450

1100

 

Main       drift       belt

drive

Node 1

2 x400

1100

 

Panel       2      intake

drive          conveyor
drive

Node 7

400

1100

 

Cross                   cut

conveyor drive

Node 10

150

1100

 

Return conveyor drive

Node 11

225

1100

 

Panel      2       return

conveyor drive

Node 12

350

1100

 

Panel                      2

continuous miner (return drive)

Node 13

550

1100

 

Panel                      2

continuous miner (intake drive)

Node 14

550

1100

 

Main fan

Node 4

330

550

Axial flow fan

Pump station

50m from node 2

55

550

Mine drainage (water)

Auxiliary fan

Node 7

150

550

Services airway 7-14

Auxiliary fan

Node 7

150

550

Services airway 7-10

Auxiliary fan

Node 12

150

550

Services airway 12-13

Assignment 2

If required it may be assumed that g = 9.81 m/s2, Density of water = 1000 kg/m3, You are a mine planning engineer at a medium sized operation producing 1.5 mtpa of coper ore at 3% Cu. The mine was originally designed using a bench height of 15m. Footwall benches were 15 m wide to give a slope angle of 45°, but on the hanging wall side alternate benches are only 10m wide to produce an angle of about 50°.

You are required to design a drainage and pumping system to deal with the mine water for the next 10-15 years based on the data in the following sections. As the mine grade is low and power costs are high every effort should be made to minimise the operating costs of the pumping system. Describe your proposed drainage and pumping system with the aid of diagrams where required and explain the general philosophy behind the system. Detail and assumptions made and make comments and conclusions as required.

Data

Mine water

Ground water: currently averages 1,000,000 litres/day and is expected to increase at a rate of 5% per year as the mine deepens.
Mine water: averages 50,000 l/day with small variations in use on an hour by hour basis.
Water Quality: Run of mine water is expected to be slightly acidic due to the formation of sulphuric acid from sulphides within the rock

Rock properties: SG of 2.9 for all rocks. Hanging wall and ore have moderate strength, footwall is very strong.

91_Rock properties.jpg

Mine Selection

Rainfall: the average annual rainfall s 740 mm, the average monthly figures are as follows

January                                               10mm

February                                              10mm

March                                                  40mm

April                                                                       60mm

May                                                     80mm

June                                                    100mm

July                                                     110mm

August                                                120mm

September                                           90mm

October                                               60mm

November                                            40mm

December                                            20mm

Based on measurements in the locality the maximum rainfall intensity recorded over the last 50 years is as indicated below and needs to be accounted for:

Storm duration (hours)

Intensity (mm/hr)

2

40

4

25

8

15

12

12

16

10

20

9

24

8

36

6

48

5

10) For the system indicated below determine the following:
d) The Average Power on the low winding side of the transformer kW
e) The reactive power kVAR
f) The effective power kVA
g) The power factor
h) The Current I1

351_figure1.jpg

26) The following data presented is from a nest of piezometers installed side by side at a single site.

Piezometer

A

B

C

Elevation  at   surface    (m

Al-ID)

850

790

830

Depth of piezometer (m)

150

100

50

Depth to water (m)

37

42

26

If A, B and C refers to the points of measurement of piezometers a, b and c, determine:
a) The hydraulic head, pressure head and elevation head at A, B and C
b) The vertical hydraulic gradients between A and B, and between B and C if they are spaced 200m apart

36) A 100 kW, 450V AC shuttle car uses a flat cable. Two layers of the cable will remain on the shuttle car's reel at all times. What is the required ampacity for the cable if efficiency is 80%, a power factor of unity also applies.

17. For the ventilation network shown on the next page, determine the flow and pressure drop in each branch of the network.

1131_figure2.jpg

18) For the following
Face dimensions 5.5 m high by 6 m wide
Face advance 3.5 m
Length of development before blast 250m
Rock density 3 tonnes/m3
ANFO factor 2.5 kg/m3 rock broken
Face ventilation 30m3/s
NO2 gas production rate 3.5 kg per tonne of ANFO
NO2 TWA is 3 ppm

Determine
1. Volume of rock to be blasted
2. Tonnes of rock to be blasted
3. ANFO used
4. Fume throw back distance
5. Volume of fumes immediately after the blast
6. Volume of NO2 gas produced
7. Concentration of NO2 in fume throw back zone immediately after the blast
8. Concentration of fumes after they have spread throughout the drive but before they have entered the decline
9. Time for diluted fumes to fill the drive
10. Time for fumes to be diluted below TWA concentration
11. Total time for fumes to clear

Reference no: EM132138637

Questions Cloud

Communication program to promote company strategy : Why is it important to prepare a communication program to promote the company strategy and to explain the risks?
What are the best practices and standards in your area : The Discussion Board (DB) is part of the core of online learning. Classroom discussion in an online environment requires the active participation of students.
Develop a timeline for implementation : Explain the descriptive statistics determined and their direct use in attracting customers.Assess how you would collect this additional information.
Develop an appropriate solution for wireless communication : The mobile application side of this solution will require secure and encrypted connections. Please work with your Security and Network Specialists to develop.
Describe proposed drainage and pumping system : Student to design an electrical distribution system for the coal mine - Describe your proposed drainage and pumping system with the aid of diagrams
Compare the results from the two algorithms : Compare the results from the two algorithms. Which one reached higher accuracy? Which one runs faster? Can you explain why?
What is the operation multi-factor productivity : What is the operation’s multi-factor productivity?
Read the above requirement properly : Read the above requirement properly and need to do power point presentation of 5 slides, each page needs to be 85-100 words each, APA format of 12 font each.
Technological functions from range of software applications : discuss in 80 to 100 words (each) at least three advanced technological functions from a range of software applications.

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd