Describe a process for monitoring and controlling a project

Assignment Help Other Subject
Reference no: EM132325202

Instructions

Write your responses where it reads "Enter your response here." Write as much as needed to satisfy the requirements indicated. Each item contains the Rubric which will be used to evaluate your responses.

1. Refer toPart 5 of the St. Dismas Assisted Living Facility Case Studydocument.

Kyle Nanno is the construction project manager for the St. Dismas Assisted Living Facility (ALF) project. One of Kyle's responsibilities is to ensure that the construction of the facility is proceeding as planned-on time and on budget. Each week, Kyle holds a meeting with his project team and key stakeholders to review the progress and performance of the construction project. After each meeting, Kyle e-mails meeting minutes to the project team and executives throughout the organization.

After reading the minutes from a recent meeting, Dr. Fred Splient, President and CEO of St. Dismas Medical Center, called Kyle to express concern about important decisions related to the construction of the facility that had not been made. Kyle reported that security-related decisions had not been made because Frank Geagy, Director of Security, had not been attending the weekly meetings. Fred makes it clear to Kyle that Frank must attend all of the team meetings going forward.

After his conversation with Dr. Splient, Kyle calls Frank Geagy. Kyle relays Dr. Splient'sexpectation that Frank attend all Friday project team meetings to review project progress and performance. Frank does not sound happy. Frank tells Kyle, "We have too much real work to do. I can't attend all these meetings."After hearing this, it occurs to Kyle that Frank may not be familiar with the project monitoring and controlling process, or why it is important.

Respond to the following:

a) Describe a process for monitoring and controlling a project.(3-4 paragraphs)

a. What are the functions of the monitoring and controlling process?

b. How does it support the other four process groups?

b) Explain why it is important to have a formal monitoring and controlling strategy for the ALF project. (3-4 paragraphs)

a. What are the overall benefits of using a formal process for monitoring and controlling projects?

b. Why should monitoring and controlling a project be an iterative process?

c) What is your assessment of the approach Kyle is taking to monitor and control the ALF project? (3-4 paragraphs)

a. What steps has Kyle taken to monitor and control the ALF project?

b. Are the steps sufficient for early warning of issues with the project performance?

2. Refer to Part 5 of the St. Dismas Assisted Living Facility Case Study document.

Kyle identified four agenda items for the weekly project team meetings. Reviewing the schedule and budget are included in the agenda. In addition, a change in scope has been proposed by the chief operating officer (COO) and the vice president (VP) of marketing. The scope change involves building and operating a hair salon for the new assisted living facility.

Respond to the following:

a) Project scope, schedule, and cost are often referred to as the triple constraints in project management. What tools and techniques could Kyle use to monitor and controlthe triple constraints? Describe two tools or techniqueseach for monitoring and controlling project scope, schedule, and cost. Explain why you selected those tools or techniques.(3-4 paragraphs)

b) The idea, from the COO and VP of marketing, to include a hair salon was a surprise to the project team.Analyze the risks posed by adding a hair salon using the triple constraints of scope, schedule, and cost as the basis for your analysis. (3-4 paragraphs)

3. Kyle Nanno, the project construction manager, is studying for his Project Management Professional (PMP) certification. He decides to apply the Earned Value Management (EVM) tools from his coursework to the assisted living facility (ALF) construction project at St. Dismas.

The project should have been 100% complete at this time, but the latest information he has indicates that it is only 89% complete. Kyle knows that the stakeholders will want a status report soon and he wants to be prepared.

a) Using the information in the table below, calculate each of the EVM metrics for each activity and for the total project.Show both your calculations and the results.

• Cost Variance (CV)

• Schedule Variance (SV)

• Cost Performance Index (CPI)

• Schedule Performance Index (SPI)

• Estimate to Completion (ETC)

• Estimate at Completion (EAC)

b) Explain what each of the EVM metrics results (that you calculated) mean, regarding the performance of the ALF project. (3-4 paragraphs)

Earned Value Chart for St. Dismas Assisted Living Facility Case Study

Activity

Planned Value

(PV)

Earned Value

(EV)

Actual Cost

(AC)

Budget at Completion (BAC)

 

% Complete

Building

$6,743

$6,069

$7,300

$6,743

90%

Furniture

$400

$280

$250

$400

70%

Site Improvements

$125

$125

$148

$125

100%

Kitchen Equipment

$30

$18

$30

$30

60%

TOTAL

$7,298

$6,492

$7,728

$7,298

89%

4. After calculating the Earned Value Management (EVM) metrics and analyzing the results, Kyle realizes that he can do a better job of managing project performance. Kyle makes a commitment to himself to apply EVM at regular intervals in the project going forward and to take appropriate actions if project performance issues become apparent. In addition, he intends to communicate project performance issues to the stakeholders and provide recommendations to address performance issues.

a) What actions might Kyle take to manage project cost performance? What actions might Kyle take to manage project schedule performance? (2-3 paragraphs)

b) What information should Kyle gather to make a recommendation? How should he gather this information? (2-3 paragraphs)

5. Fred Splient sends the assisted living facility (ALF) project steering committee a written performance report every 2 weeks. He will prepare one in a few days. Kyle Nanno, the construction project manager, stops by Fred's office to share the EVM analysis he conducted. Fred decides to use this information in the status report. Develop the performance report based on the results of the EVM analysis that was done by Kyle. (1 page)

Attachment:- Case Study- St Dismas Assisted Living Facility.rar

Reference no: EM132325202

Questions Cloud

Conduct research and solicit anecdotal evidence in brief : Why is understanding the health care system at the local level important to consider when planning an EBP implementation? Conduct research and solicit.
What is the optimal order size : a. What is the optimal order size? b. What is the optimal number of orders per year?
Describe relationship to professional certification : Create a PowerPoint presentation of 10-15 slides in which you compare the pros and cons of continuing nursing education related to the following.
What is a shortcoming of approach : Outline Mintzberg's categorization of stakeholders. What is a shortcoming of this approach?
Describe a process for monitoring and controlling a project : PM004-Project Performance Measurement-Walden University-US-Why should monitoring and controlling a project be an iterative process?
What do you define as effective leadership : Compare and contract authority and power in terms of leadership. What do you define as effective leadership?
Describe sense for implementing your specific ebp project : Compare and contrast two change theories, and determine which theory makes the most sense for implementing your specific EBP project. Why? Has your mentor used.
Compare and contract leadership and management : Compare and contract leadership and management. Discuss a time when you witnessed or experienced effective leadership and effective management.
General characteristics of the 4 stages of team building : Teams can exist for a myriad of reasons; however, the development process will always be relatively the same. Understanding each of the stages is important

Reviews

len2325202

6/19/2019 11:31:42 PM

Student provides a detailed description of the functions of the monitoring and controlling process and how it supports each of the other four process groups.There are one or two minor details missing. Student provides a detailed explanation of the overall benefits of monitoring and controlling a project and why it should be an iterative process. There are one or two minor details missing. Student provides a detailed assessment of two or more tools and techniqueseach for monitoring and controlling scope, schedule, and cost, including the rationale for using those tools and techniques.

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd