Cost, Pricing, Scheduling, and Control
Cost Estimation
Suppose that you have been asked to price an 8-month external project. Direct labor is estimated at $100,000 per month, plus a 100% overhead rate. The total labor termination liability in any particular month includes, of course, the total amount (100%) of the current month's labor expense (including overhead) plus (with the exception of the final month) a penalty of 80% of the following month's labor expense (including overhead). So the total accumulated labor liability at any point during the project is equal to the accumulated labor expenses accrued up to the previous month, plus the current month's labor termination liability. There are two material resources. Material A will cost $100,000, payable 30 days net. This material is needed at the end of the 5th month and has a 4-month lead time. The termination liability on Material A in any particular month is as follows:
1-30 days after ordering: 25%
31-60 days after ordering: 50%
>60 days until the expense is paid in full: 100% after the expense has been paid in full, there is no additional termination liability.
Material B will cost $200,000, payable on delivery. This material is needed at the end of the 7th month and has a 3-month lead time. The termination liability on Material B in any particular month is as follows:
1-30 days after ordering: 50%
>30 days until the expense is paid in full: 100% after the expense has been paid in full, there is no additional termination liability.
To simplify the analysis, assume that all 8 months identically contain exactly 30 days. Also assume that any payment or liability that occurs on a month boundary should be assigned to the month that falls before this boundary (not the one that comes after the boundary). Assume that you can neglect profits. Assume that the customer has agreed to buy this project and pay, at the end of each month, 100% of all costs incurred during that month. Assume that the project is guaranteed to execute precisely on schedule.
1. Based on this information, how much burdened labor cost would the customer be obligated to pay at the end of the 1st month (assuming that the project had not been terminated)?
a. $150,000
b. $0
c. $200,000
d. $160,000
2. For the same project, how much additional labor termination liability would be added to the burdened labor cost to calculate the customer's total labor liability at the end of the 1st month if the customer should decide to terminate the project at that point?
a. $200,000
b. $50,000
c. $0
d. $160,000 PROJ522 - Cost, Pricing, Scheduling, and Control
3. For the same project, what is the customer's total accumulated labor liability at the end of the 2nd month if the customer should decide to terminate the project at that point? (Hint: They would be responsible for covering 2 months of burdened labor costs incurred plus one month of additional termination liability.)
a. $720,000
b. $560,000
c. $320,000
d. $400,000
4. For the same project, what is the customer's total accumulated labor liability at the end of the 3rd month if the customer should decide to terminate the project at that point? (Hint: They would be responsible for covering 3 months of burdened labor costs incurred plus one month of additional termination liability.)
a. $600,000
b. $480,000
c. $560,000
d. $760,000
5. For the same project, what is the customer's total accumulated material liability at the end of the 4th month if the customer should decide to terminate the project at that point?
a. $200,000
b. $25,000
c. $75,000
d. $100,000
6. For the same project, what is the customer's total accumulated material liability at the end of the 5th month if the customer should decide to terminate the project at that point?
a. $300,000
b. $0
c. $200,000
d. $100,000
7. For the same project, what is the customer's total accumulated liability (including both material and labor) at the end of the 7th month if the customer should decide to terminate the project at that point?
a. $1,560,000
b. $1,860,000
c. $1,700,000
d. $1,900,000
8. For the same project, what is the customer's total accumulated liability (including both material and labor) at the end of the 8thmonth if the customer should decide to terminate the project at that point?
a. $1,760,000
b. $2,060,000
c. $1,900,000
d. $1,600,000.
What are the effects of long-term sleep reduction
: Describe a situation in which a person does not get enough sleep. How would it affect mood, behavior, and cognitive and motor skills? What are the effects of long-term sleep reduction? Briefly describe common sleeping disorders and possible drug reme..
|
Urbanization-paving-channelizing and straightening
: How does the urbanization (paving, channelizing, straightening etc.) affect the magnitude of both, RUNOFF and INFILTRATION, in a moderately-sized, previously forested drainage basin?
|
Environmental forces-social-economic-technological
: What trends in the environmental forces (social, economic, technological, competitive, and regulatory) work for and/or work against Rollerblade's potential growth in the 21st century?
|
What do you do to re-energize and regain focus
: Always that you have tuned into cues from your body that show diminished focus or energy when you are working on a project, reading, or studying. How did you sense it? What do you do to re-energize and regain focus?
|
Cost-pricing-scheduling and control
: Suppose that you have been asked to price an 8-month external project. Direct labor is estimated at $100,000 per month, plus a 100% overhead rate.
|
Happiness-satisfaction and lack of loneliness in singlehood
: Describe several factors that are related to happiness, satisfaction, and lack of loneliness in singlehood.
|
Price elasticity of demand is calculated as
: Price elasticity of demand is calculated as
|
Operational definition of employee involvement
: Need to Develope an operational definition of employee involvement. Be sure to include a citation or a url for your source.
|
Developing an operational definition of a team
: Begin this lesson by developing an operational definition of a team. Be sure to include a citation or a url to your source. Please include citation and with 100 words or less.
|