Contract calls for liquidated damages

Assignment Help Other Subject
Reference no: EM133812184

Question

A contract calls for liquidated damages of $1,000 per day on late delivery of goods. The total value of the contract is $3200 and the goods are five days late. The buyer demands $5,000 in liquidated damages. The likely result is Multiple Choice the buyer will receive the $5000. the liquidated damage clause is punitive and not enforceable here. the liquidated damage clause is not punitive but the court will not enforce it as it is exculpatory. the buyer will not receive the $5000 but will receive something less solely under the liquidated damage clause. the buyer will receive the $5000 in liquidated damage clause plus the buyer's actual damages as well.

Reference no: EM133812184

Questions Cloud

Suppose you order snowboard from seller on craigslist : Suppose you order a snowboard from a seller on Craigslist. You pay for the snowboard, but the seller refuses to send the board to you.
Reasonable expectation of privacy doctrine : What is the difference between the trespass doctrine and the reasonable expectation of privacy doctrine?
Basis of current department of homeland security : You will develop a research paper that addresses the legal basis of current Department of Homeland Security (DHS) jurisdiction, mission, and responsibilities.
Reasonable person would evaluate as being offensive : Harm in this tort would qualify as something a reasonable person would evaluate as being offensive. The scenario shows that the plaintiff acted with objective
Contract calls for liquidated damages : A contract calls for liquidated damages of $1,000 per day on late delivery of goods. The total value of the contract is $3200 and the goods are five days late.
Defendant damages property in efforts of saving themselves : Necessity is a defense that applies when a defendant damages property in efforts of saving themselves, others, or their personal property.
Bargained for exchange or suitable alternative : Condense this paragraph Consideration in contract law requires a bargained for exchange or a suitable alternative.
Acceptance in contract law can occur through instantaneous : Acceptance in contract law can occur through instantaneous communication, forming an immediate contract, or via the Mailbox Rule,
Vesting of Rights : Vesting of Rights: Generally speaking, the contracting parties can rescind the contract until the rights of the third party vest.

Reviews

Write a Review

Other Subject Questions & Answers

  Cross-cultural opportunities and conflicts in canada

Short Paper on Cross-cultural Opportunities and Conflicts in Canada.

  Sociology theory questions

Sociology are very fundamental in nature. Role strain and role constraint speak about the duties and responsibilities of the roles of people in society or in a group. A short theory about Darwin and Moths is also answered.

  A book review on unfaithful angels

This review will help the reader understand the social work profession through different concepts giving the glimpse of why the social work profession might have drifted away from its original purpose of serving the poor.

  Disorder paper: schizophrenia

Schizophrenia does not really have just one single cause. It is a possibility that this disorder could be inherited but not all doctors are sure.

  Individual assignment: two models handout and rubric

Individual Assignment : Two Models Handout and Rubric,    This paper will allow you to understand and evaluate two vastly different organizational models and to effectively communicate their differences.

  Developing strategic intent for toyota

The following report includes the description about the organization, its strategies, industry analysis in which it operates and its position in the industry.

  Gasoline powered passenger vehicles

In this study, we examine how gasoline price volatility and income of the consumers impacts consumer's demand for gasoline.

  An aspect of poverty in canada

Economics thesis undergrad 4th year paper to write. it should be about 22 pages in length, literature review, economic analysis and then data or cost benefit analysis.

  Ngn customer satisfaction qos indicator for 3g services

The paper aims to highlight the global trends in countries and regions where 3G has already been introduced and propose an implementation plan to the telecom operators of developing countries.

  Prepare a power point presentation

Prepare the power point presentation for the case: Santa Fe Independent School District

  Information literacy is important in this environment

Information literacy is critically important in this contemporary environment

  Associative property of multiplication

Write a definition for associative property of multiplication.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd