Calculate the mean and variance of activity duration time

Assignment Help Financial Management
Reference no: EM132128598

Case: Project Management

NOTE: Use Excel Spreadsheetto carry on this project. Only ONE file is needed for the project. You can use several sheets within the same file.

  1. (ODD GROUPS)Dream Team Productions, a firm hired to coordinate the release of the movie Paycheck (starring Uma Thurman and Ben Affleck), identified 16 activities to be completed before the release of the film.

    The tasks (in time units of weeks) are as follows:

Activity

Immediate Predecessors

Optimistic
Time

Most Likely
Time

Pessimistic
Time

A

-

1

2

4

B

-

3

3.5

4

C

-

10

12

13

D

-

4

5

7

E

-

2

4

5

F

A

6

7

8

G

B

2

4

5.5

H

C

5

7.7

9

I

C

9.9

10

12

J

C

2

4

5

K

D

2

4

6

L

E

2

4

6

M

F, G, H

5

6

6.5

N

J, K, L

1

1.1

2

O

I, M

5

7

8

P

N

5

1

9

a. For each activity, calculate the mean and variance of activity duration time

b. Draw(electronically) the AON project network (use excel spreadsheet).

c. Using the mean activity times,  conduct a CPM analysis and develop an activity schedule for this project using early and late start and finish times, compute activity slack time, and define the critical activities. What is the expected (i.e. mean =Tavg) project completion time? The standard deviation of the completion time?

d. What is the probability the project will be completed in time for the company to release the film within Tavg +1 week?

e. What date results in a 97% probability of completion?

2. (EVEN GROUPS)Bill Fennema, a president of Fennema Construction, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.

Activity

Immediate Predecessor(s)

Time Estimates (in weeks)                                                                  

       Optimistic                   Most Likely                  Pessimistic

A

-

4

8

10

B

A

2

8

24

C

A

8

12

16

D

A

4

6

10

E

B

1

2

3

F

E, C

6

8

20

G

E, C

2

3

4

H

F

2

2

2

I

F

6

6

6

J

D, G, H

4

6

12

K

I, J

2

2

3

a. What is the expected (estimated) time and variance for each activity?

b. Draw (electronically)and analyze the AON network for the project. Use excel Spreadsheet.

c. Identify the critical path(s).

d. What are the expected (mean) and variance of the time to complete the project?

e. What is the probability of completion of the project before week 37?

f.  What date results in a 99% probability of completion?

Reference no: EM132128598

Questions Cloud

How could advertising be a barrier to entry : • How could advertising be a barrier to entry? Could advertising reduce barriers to entry for a new product?
Value of the impact of the policy on employers : Compute the dollar value of the impact of the policy on employers, workers, and society as a whole.
Find the equilibrium price and quantity : Find the equilibrium price and quantity
What does this demand sequence mean : What does this demand sequence mean? (I am assuming that x,y,and s are related products)
Calculate the mean and variance of activity duration time : MGMT 3020: What is the probability the project will be completed in time for the company to release the film within Tavg +1 week?
Find the equilibrium of price and quantity : How do we plot something like this on a graph to find the equilibrium of price and quantity?
Essay on project environment and planning : essay on Project Environment and Planning - Exactly how an individual essay is structured is very much the choice of the individual writer
Adverse selection problem : You sell bicycle theft insurance. If bicycle owners do not know whether they are high- or low-risk consumers, is there an adverse selection problem?
Describe the project and the rationale for your choice : Describe the project and the rationale for your choice. Identify the stakeholders and how they will benefit from the project.

Reviews

Write a Review

Financial Management Questions & Answers

  Foreign company acquisition

Acquisition by a foreign company and the effects of that decision and the results of foreign exchange in Euro and the exchange rate differences.

  Financial management for profit and non profit organizations

In this essay, we are going to discuss the issues of financial management in a non-profit organisation.

  Method for estimating a venture''s value

Evaluate venture's present value, cash and surplus cash and basic venture capital.

  Replacement analysis

This document show the Replacement Analysis of modling machine. Is replacement give profit to company or not?

  Business finance task - capital budgeting

Your company is considering using the payback period for capital-budgeting. Discuss the advantages and disadvantages of this technique.

  Analysis of the investment

In this project, you will focus on one of these: the additional cost resulting from the purchase of an apple press (a piece of equipment required to manufacture apple juice).

  Conduct a what-if analysis

Review the readings and media for this unit, including the Anthony's Orchard case study media. Familiarise yourself with the Anthony's Orchard company and its current situation.

  Determine operational expenditures

Organisations' behaviour is guided by financial data. In the short term, such data will help determine operational expenditures; in the long term, historical data may help generate forecasts aimed at determining strategic plans. In both instances.

  Personal financial management

How much will you have left over each half year if you adopt the latter course of action?

  Sources of finance for expansion into new foreign markets

A quoted company is considering several long-term sources of finance for expansion into new foreign markets.

  Long term financial planning

This assignment is designed for analyze Long term financial planning begins with the sales forecast and the key input in the long term fincial planning.

  Explain the role of fincial manager

This assignment explain the role of fincial manager, function of manger. And what are the motives of financial manager.

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd