Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and identify the critical path for the project. Can the project be completed in 40 weeks? Assume that Activity A actually finished at 3 weeks, Activity B actually finished at 12 weeks, and Activity C actually finished at 13 weeks. Recalculate the expected project completion time. Which activities would you focus on in order to get the project back on schedule?
|
ES
|
EF
|
LS
|
LF
|
Slack
|
A
|
0
|
1
|
1
|
2
|
1
|
B
|
2
|
8
|
2
|
10
|
2
|
C
|
2
|
5
|
3
|
8
|
3
|
D
|
2
|
17
|
4
|
15
|
0
|
E
|
11
|
19
|
5
|
7
|
0
|
F
|
8
|
30
|
6
|
12
|
0
|
G
|
9
|
29
|
8
|
20
|
-
|
H
|
21
|
34
|
9
|
25
|
0
|
ES is the earliest start time of each activity, LS is the latest start time, LF is the latest finish, and EF is the earliest finish time of activity without delaying the total project time. Slack or float is the amount of time that each activity can be delayed without delaying the subsequent events (Chen, 2007).
The critical path for this project is A-C-F-H
From the table results, it is clear that the project will be completed within the given dateline of 40 days. The slack time or each activity must be reduced to minimize the completion time. Operation F and H have the longest time requirement and these needs a lot of concentration regarding resources. If activity A is finished at three weeks, it means the slack will increase by one week. Any slight mistake to delay operation F and H will slow the total project time. Increasing the finish time of activity B to 12 weeks will increase the project time and the slack by two weeks. Likewise, if C is completed at 13 weeks the slack time will also be increased. However, the total will not be raised beyond the expected time since only activity A and C are on the critical path.
References
Chen, Shih-Pin. "Analysis of critical paths in a project network with fuzzy activity times." European Journal of Operational Research 183.1 (2007): 442-459.
Describe economic principle that company executives consider
: Describe the economic principles that company executives should consider when developing a strategy or strategies that will maximize profits while minimizing incentives for competitors to develop competing products
|
Set of ordered pairs
: Write, as a set of ordered pairs, a function f that is a bijection from V1 to V2, satisfying the following condition: if x and y are elements in V1 such that {x,y} is in E1, then f(x) and f(y) are elements in V2 such that {f(x),f(y)} is in E2, and..
|
Most of what is written about leadership
: Most of what is written about leadership has been written by western scholars and practitioners—mostly from the United States. Thus, what we have studied in this module so far reflects western assumptions and values about how to improve leadership pe..
|
Draw a block diagram of how this device might work
: Based on this brief description of the Head Master, draw a block diagram of how this device might work and the basic components that might be needed in the Head Master. Include in your block diagram the ultrasonic signal source, detectors, timers,..
|
Calculate the es ef ls and lf times and the slack
: Calculate the ES, EF, LS, and LF times and the slack for each activity- identify the critical path for the project.- an the project be completed in 40 weeks?
|
Represent a relational algebra expression
: How does a query tree represent a relational algebra expression? Discuss any three rules for query optimisation, giving example as to when should each rule be applied.
|
Develop conclusions about the economys influence
: Develop conclusions about the economy's influence on personal and business decision making such as purchases, investments, and so forth.
|
Role and relationship between the entities
: Define the terms entity, attribute, role and relationship between the entities, giving examples for each of them.
|
What is required procedure when agency issues new rule
: According to Alexander Hamilton in Federalist No. 78, the power of judicial review. To the extent that independent agencies (such as the Environmental Protection Agency) are under anyone's control, they are under the control of. What is the required ..
|