Reference no: EM132582996
Barbaro Production Company has developed the following standards for one of its products.
STANDARD VARIABLE COST CARD
One Unit of Product
Materials: 30 square feet × $5 per square foot $150.00
Direct labor: 16 hours × $7 per hour 112.00
Variable manufacturing overhead: 16 direct laborhours × $5 per hour 80.00
Total standard variable cost per unit $342.00
The company records materials price variances at the time of purchase. The following activity occurred during the month of April:
Materials purchased: 80,000 sq. feet at $5.30 per sq. foot
Materials used: 74,000 square feet
Units produced: 2,500 units
Direct labor: 42,000 hours at $6.70 per hour
Actual variable manufacturing overhead: $228,000
Required:
Question 1: Calculate the direct materials price
Question 2: Calculate the direct materials usage
Question 3: Calculate the direct labor rate
Question 4: Calculate the direct labor usage
Question 5: Give possible reasons for the occurrence of each of the preceding