Calculate sv cv cpii and spi. what does this tell you

Assignment Help Econometrics
Reference no: EM131044887

A construction project at day 70 has actual costs of $78,000 and a scheduled cost of $84,000. The work package manager estimates a value completed of $81,000. Calculate SV, CV, CPI, and SPI. What does this tell you?

Reference no: EM131044887

Questions Cloud

Annual budget for a certain company : The pie chart below shows how the annual budget for a certain company is divided by department. If the total budget is 125,000,000, what amount is budgeted for Support, Sales, and Media combined?
When will the power plant come on-line with 90% probability : The utility company would like to apply for a permit to operate the facility three years after award of the contract. What is the probability the plant will be on-line on time?
Stem-and-leaf display in a report : (i) Construct a stem-and-leaf display (ii) Supposedly you are inserting the above stem-and-leaf display in a report to be submitted to management, write a short comment on the diagram.
Calculate the cpi and spi : Calculate the CPI and SPI and explain the message they give the program manager.
Calculate sv cv cpii and spi. what does this tell you : The work package manager estimates a value completed of $81,000. Calculate SV, CV, CPI, and SPI. What does this tell you?
Mean cost for the current production method : Suppose a new production method will be implemented if a hypothesis test supports the conclusion that the new method reduces the mean operating cost per hour. a. State the appropriate null and alternative hypotheses if the mean cost for the current..
Probability that at least one of the eggs is contaminated : If Salmonella contamination occurs independently in egg cartons, and we should make a "three-egg omelet", what is the probability that at least one of the eggs is contaminated with Salmonella?
Calculate the variances should the customer be happy : Given a project planned to cost $12,000 but actual cost to date is $10,000, and the project is only 70% complete, calculate the variances. Should the customer be happy?
What are the options market value and price of the stock : The exercise price on one of Flanagan Company's options is $14, its exercise value is $23, and its time value is $7. What are the option's market value?$ What is the price of the stock? $ What is the exercise value of the call option? $ What is the o..

Reviews

Write a Review

Econometrics Questions & Answers

  Estimator of linear functions distributed

How are the least squares estimator of linear functions distributed?

  Which tourists appreciate a lot for the warm climate

Country A is a very large and advanced economy, whereas country B is newly industrialized country, which tourists appreciate a lot for its warm climate and great Mexican food.The government of country B wants to raise revenue

  Show the effect of the tax on the equilibrium wage

You are an economic consultant to a city that just imposed a payroll tax of $1 per hour of work. This payroll tax is paid by workers through a payroll deduction: For each hour of work, the employer deducts $1 and sends the money to the city govern..

  Determine the equivalent annual cost of operating the truck

you have operating and maintenance costs that start at $15,000 the first year and increase by $2,000 per year thereafter. assume that the salvage value at the end of five years is $9,000 and interest rate is 12%. Determine the equivalent annual co..

  What is the highest level of y that can still be met

Consider the following information. For Group A the cost of attaining an educational level is CA(y)=$6,000y and for Group B this is CB(y)=$10,000y. Employees will be offered $50,000 if they have y

  Linear relationship between explanatory variables

Rewrite the model to show that this is in fact a two-variable model rather than a three-variable model. Define the parameters

  What advice would give to friend under the circumstances

In the following year, your friend asks for your help again. All of the data remain the same; however your friend finds that she is no longer profitable in the spring, summer, or fall months. What advice would you give to her under these circumsta..

  What is the present value of the cash flows

At a 10% annual interest rate (compounded yearly), what is thepresent value of the cash flows? To receive full credit you mustuse 2 arithmetic gradients. what is the present value of the cash flows

  Find the number of firms that will be active in short run

Consider a market served by identical firms with cost funtion C(q)=722+(q^2)/200. The market demand is given by Qd=6500-100P and the short run market supply is given by Qs=1200p. Find the number of firms that will be active in the short run.

  Calculate the npv of the cash flows expected in 2006

Calculate the NPV of the cash flows expected in 2006-2010 using only the 2005 Cost of Capital  Calculate the NPV of the cash flows using the CASH FLOW figures at the bottom of the spreadsheet

  Why economy were operating at employment govt expenditure

Suppose that government expenditures are currently $700 billion and tax revenues are currently $550 billion. Assume further that the government estimates that if the economy were operating at full employment government expenditures would only be $..

  What is michelles opportunity cost of producing potatoes

Suppose that two people, Michelle and James each live alone in an isolated region. They each have the same resources available, and they grow potatoes and raise chickens. If Michelle devotes all her resources to growing potatoes, she can raise 200..

Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd