Software project planning, Computer Engineering

Software Project Planning

In the previous days of computing software costs comprised a small % of overall computer based system cost. In order of magnitude error software cost had relatively little impact in estimates of. Presently, software is the most expensive elements in most computer-based systems. With large cost estimation error can make the variation among loss and profit. For the developer Cost overrun can be disastrous.

Software effort and cost estimation will never be an exact science.  There are Too many variables human Technical, Environmental, Political can affect the ultimate effort and cost of software applied to build it. However software project estimation can be transformed from a mysterious art to a series of systematic steps that gives estimates with acceptable risk.

To achieve reliable effort and cost estimates a number of options arise.

1.    The Delay estimation until late in the project (obviously, we can achieve 100% accurate estimates after the project is completed)

2.    The Base estimates on same projects that have already been completed.

3.    The Use relatively simple decomposition techniques to generate project effort and cost estimates.

4.    The Use one or more empirical models for software cost and effort estimation.

Unfortunately, the first option moreover attractive is not practical.  The Cost estimates must be provided up- front.   However, we will recognize that the longer we wait the more we know and the more we know the less likely we are to make serious errors in our estimates.

The option can work reasonably well if the present project is quite same to previous efforts and other project   influences  for example business   conditions,   the   customer,   the   SEE   deadlines  are   equivalent. Unfortunately, previous experience has not always been a good indicator of future results.

The remaining options are viable approaches to software project estimation. Ideally, the method noted for each option should be applied in tandems each used as a cross-check for the other.  The Decomposition techniques will take a divide and conquer approach to software project estimation. By decomposing a project into a major functions and related software engineering activities effort and cost estimation can be performed in a stepwise fashion.  Empirical estimation models can be used to complement decomposition methods and offer a potentially valuable estimation approach in their own right.  The model is based on experience historical data and takes the form.

d=f(Vi)

Where d is one of a number of estimated values example for effort, cost, project duration and Vi are selected independent parameters for example estimated LOC or FP

The Automated estimation tools implements one or more decomposition methods or empirical models.

When combined with an interactive human machine interface automated tools give an attractive option for estimating. Like systems the characteristics of the development company for example experience, environment and the software to be developed are described.  Effort and Cost estimates are derived from these data.

As the historical data used to seed the estimate each of the viable software cost estimation options is only as good. If no historical data exist costing rests on a very shaky foundation.

Posted Date: 10/18/2012 7:43:29 AM | Location : United States







Related Discussions:- Software project planning, Assignment Help, Ask Question on Software project planning, Get Answer, Expert's Help, Software project planning Discussions

Write discussion on Software project planning
Your posts are moderated
Related Questions
What is virtual memory? Virtual memory is a method used in some large computer systems that allow the user to construct program as by a large memory space were available, equal

Which approaches do not require knowledge of the system state? Ans. Deadlock detection, deadlock prevention and deadlock avoidance; none of the given require knowledge of the s

As spring approaches, your design firm has been tasked with designing a two-lane highway in rural Wyoming. The highway descends a hill, crosses a river, and must shift to a para

Explain Auto increment and Auto decrement mode  The register is incremented or decremented after (or before) its value is used to access memory.  The address stored in the regi

Write a 'C' program to accept any 3 digit integer number from the keyboard and display the word equivalent representation of the given number

This assignment relates to all of the course objectives but more specifically to your practical understanding and evaluation of the key issues in relation to the development of the

Q. Explain about Interlacing? Interlacing is a procedure in which in place of scanning the image one-line-at-a-time it's scanned alternatelyit implies thatalternate lines are s

Q. What are Dynamic Process Groups? To create and manage dynamic groups a separate library libgpvm3.a should be linked with the user programs which make use of any of group fun

Which device consume minimum power ? Ans. Minimum power consume by CMOS as in its one p-MOS and one n-MOS transistors are connected in complimentary mode, so one device is ON a

Explain dataflow computation model An option to the von Neumann model of computation is a dataflow computation model. In a dataflow model the control is tied to the flow of dat