software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Define the design phase of the project management, Define the Design phase ...

Define the Design phase of the project management. Design phase:   The list of needs which is developed within the definition phase can be utilized to make design alte

Global Project Management, You have been hired as the Senior Global Project...

You have been hired as the Senior Global Project Manager by the Timm Coconut Transnational Motor Corporation to manage their newly created Project Management Office. You are in c

System and simulation specifications, Input Data Collection The input d...

Input Data Collection The input data for the model was collected accurately to be as close as possible to a typical emergency room. We expected that the number of patients comi

Internal and external customers - elements of tqm, Internal and external cu...

Internal and external customers: The library shall be functioning as a "learning and resource centre" in its efforts to stay abreast of changes in its internal and external en

Explain about the break even analysis, Explain about the Break Even Analysi...

Explain about the Break Even Analysis. Break Even Analysis: Break even Analysis means that at some point within the operations, total revenue equivalent to total cost. Break ev

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

Construct a network diagram showing the critical path, ST is the operations...

ST is the operations director of F Bakery. He is in the process of putting together a project plan for the introduction of a latest production plant that will enable the bakery to

Turn key contracts, Ask question #Miniwhat circumstances that favor turn ke...

Ask question #Miniwhat circumstances that favor turn key contracts mum 100 words accepted#

Different phases of a new product development, The banking sector provides ...

The banking sector provides a wide range of products and services to Retail and Business customers. Before making any product available to the customers, banks have to carry out ma

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd