software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Describe what is a budget process, Question: (a) John Oakland says: ...

Question: (a) John Oakland says: "Day to day issues, often taken for granted, involve quality in some form or other. For example, the safety and conformity with accepted st

Change management plan for an organisation, Change Management Plan for an O...

Change Management Plan for an Organisation Explain: (i) Background to organization (one page max) (ii) Analyse the organization situation by conducting a force field anal

Phases of a project life cycle, Question: (a) A project manager must ta...

Question: (a) A project manager must take ownership of the project at its early stage through the following tasks namely: stakeholder identification and analysis, prepare a bus

What planning concerns in project management, Question 1: Harvey Maylor...

Question 1: Harvey Maylor discusses a ‘generic' life cycle to help in project management. Explain what is meant by project life cycle and critically discuss the benefits that

Determine the critical path by activities and duration, Determine the criti...

Determine the critical path by activities and duration. Activity          Duration (Wks)       Preceded by A                     5                               -

How could appraisals be made successful in organisations, Question: Per...

Question: Performance Appraisal "Is the process of evaluating the performance and qualifications of the employees in terms of the requirements of the job for which he is emp

Virtual museum project, Building design - You can select any building to ho...

Building design - You can select any building to house your museum.  It may be a historical building that we study (i.e. the Pantheon), it may be a current museum anywhere in the w

Describe incremental approach to orderly acceptance testing, Describe the i...

Describe the incremental approach to orderly acceptance testing. Acceptance test: The users are invited to perform an acceptance test to check which what they have asked

Risk management responsibilities, Risk Management Responsibilities   Ea...

Risk Management Responsibilities   Each and every person in the project team has a responsibility of performing a particular task and must indulge in risk management process. T

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd