software project, Project Management

Assignment Help:
Scenario:
You are a member of the Project Review team for CK Software Services. At the next meeting, the team will discuss the scheduling for the new automated teller machine (ATM) software the company is building. You have been selected to lead the team that will develop the Financial Transactions (FINAT} module based upon the architecture decomposition (ADV) shown in Figure 5.4 on page 178 and the Work Breakdown Structure ( WBS) shown in Figure 5.5A and Figure 5.5B on pages 179-180. The estimates for the detailed tasks are shown below for your convenience.

Prepare the preliminary schedule by completing each of the following.
1. Choose the development model being used for the FINAT project. State the name of the development model/process.
2. Define where you would place the milestones for the FINAT project and prepare a milestone list using a structure similar to Table 5.5 on page 189. Remember that this is part of a larger project where the top-level architecture decomposition (ADV) has been determined. You must then include consideration of how your FINAT project fits into the overall project. That means you need to include one or more milestones that will enable your project to smoothly integrate into the ATM project.
3. Prepare a critical path activity network for the tasks showing the information listed below. Figure 5.6 on page 189 shows an example. You may use Microsoft Project, Visio, or another appropriate drawing tool. The critical path activity network is a directed graph showing the milestones as nodes in the graph with directed edges showing the workflow.
a. Milestones that you identified in #2 above.
b. Concurrent and sequential tasks as needed for your development model/process.
c. Include the individual tasks with the duration for each (shown in parentheses on each edge of the graph). Label each edge with the task “number” and duration.
d. Calculate and state the total number of weeks in the schedule.
e. Identify the critical path by showing the edges in a different color or with a “bold” edge symbol.
4. Prepare a week-by-week staffing profiles for the FINAT project as listed below. Show each in a separate table. Figures 5.11 and 5.12 on page 197 show example profiles for EST and LST calculations.
a. Prepare a staffing profile that gives the most-ideal staffing plan you can devise. That is, arrange your projects so that you satisfy the required workflow but have the most constant staffing plan. The ideal staffing profile is shown in Figure 5.13 on page 198.
5. Extra Credit: Prepare 3 Gantt charts for the FINAT project, one that show the schedule to accomplish each staffing profile.



Detailed Task Estimates (Refer to Figures 5.5A and 5.5B on pages 179-180)
Task Number of Staff Duration in Weeks
3.2.1.1 2 2
3.2.1.2 1 3
3.2.1.3 2 2
3.2.2.1 2 4
3.2.2.2 3 5
3.2.2.3 2 3
3.2.3.1 1 2
3.2.3.2 2 2
3.2.3.3 1 3
3.2.4.1 3 1
3.2.4.2 2 3
3.2.4.3 2 1
3.2.5 4 3

Related Discussions:- software project

Implementation risks in cost of quality approaches, I mplementation risks ...

I mplementation risks There    are    many    problems   which    have   caused    the    cost-of-quality approaches to fail. It is unwise to achieve too much too fast. For ex

WBS and Network diagram, Network Diagram for my course project based upon t...

Network Diagram for my course project based upon the WBS. The Network Diagram should include the Earliest Start (ES), Earliest Finish (EF), Latest Start (LS), Latest Finish (LF), a

Explain what is public-private-partnership, Question : (a) Explain wha...

Question : (a) Explain what is public-private-partnership (PPP)? (b) What are the benefits of public-private-partnership? (c) Explain the different forms PPP arrangeme

What are the benefits of work study?, Question 1) Describe any ten overall...

Question 1) Describe any ten overall functions of the purchasing department Question 2) Describe any five principles of plant layout Question 3) Describe the any

Line balancing., What do you understand by "line balancing"?

What do you understand by "line balancing"?

Operating characteristic curve, O perating characteristic curve The op...

O perating characteristic curve The operating characteristic curve for a sampling plan quantifies the risks. The OC curve for an attribute plan is a graph of the percentage de

Too much too soon, What is operational and behavioural symptoms

What is operational and behavioural symptoms

Project manager, Understanding the different models of project manage. How ...

Understanding the different models of project manage. How is projectized different from managing and controlling task.

Client master plan, The Client Masterplan includes introduction, rationale,...

The Client Masterplan includes introduction, rationale, client objectives and stakeholder management. This should be a rationalisation of the requirements. Guidelines

Structure, Differences between wbs and product breakdown structure, Project...

Differences between wbs and product breakdown structure, Project Management

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd