Process selection and process design, Operation Management

Assignment Help:

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 


Related Discussions:- Process selection and process design

#title.supply chain management, explain how a supply chain management would...

explain how a supply chain management would enhance profitability with an analysis of supply chain network

Make a product structure for heather, Operations Mgmt. 10th edition Hiezer/...

Operations Mgmt. 10th edition Hiezer/Render Heather Adams, production manager for a Colorado exercise equipment manufacturer, needs to schedule an order for 50 UltimaSteppers, whic

Explain should audio cables buy the new equipment, Audio cables, INC. is cu...

Audio cables, INC. is currently manufacturing an adapter that has a variable cost of $.50 per unit and a selling price of $1.00 per unit. Fixed cost are $14,000. Current sales volu

Explain a wealthy farmer owns fifty acres of land, A wealthy farmer owns fi...

A wealthy farmer owns fifty acres of land. He is going to plant each acre with sugarcane or corn. Each acre planted with sugarcane yields Rs 16,000 profit; each with corn yields Rs

Upper and lower limits, The upper and lower limits for diving ring diameter...

The upper and lower limits for diving ring diameters made by John''s Swimming are 40 and 39 cm. John took 11 samples with the following average diameters (39, 39.1, 39.2, 38.9, 39.

Production & Purchasing Managements, Hierarchical planning in operations/Pr...

Hierarchical planning in operations/Production managemnt and the types of time frames in each hierarchy?

Explain to what extent did marketing play a role, From an analysis of the c...

From an analysis of the case, discuss some key factors that led to the Williams Company's decline and ultimate exit from the private sector. • To what extent did project managem

What the act of consciously choosing from alternatives, The act of consciou...

The act of consciously choosing from alternatives is called a dilemma. a quandary decision making. a paradox. a predicament.

Explain the precedence relationships and the estimated times, A project con...

A project consists of activities A, B, C, D, E, F, and G. The precedence relationships and the estimated times to complete each activity are given below: Activity Preceding Activit

Sunshine Enterprises Case Study , What is the average value of a loyal cust...

What is the average value of a loyal customer (VLC) at Abby's restaurants (see Chapter 3)? What is the best way to increase revenue given your VLC analysis

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd