Process selection and process design, Operation Management

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 

Posted Date: 3/16/2013 2:28:25 AM | Location : United States







Related Discussions:- Process selection and process design, Assignment Help, Ask Question on Process selection and process design, Get Answer, Expert's Help, Process selection and process design Discussions

Write discussion on Process selection and process design
Your posts are moderated
Related Questions
Analyze why it is important to address risk through the entire project life cycle. Identify three possible negative results that can occur if an organization fails to address risk

Consider monthly demand for the ABC Corporation as shown in Table 7-3. Forecast the monthly demand for year 6 using moving average, simple exponential smoothing, Holt's model, and

Please summarize Blue Cross Blue Sheild Health Insurance, review members service, new/ current/ upcoming technology, accreditation or certifications and patient incentives as well

A company is to make a decision on whether or not to purchase a machine to package its product and has asked you to review the information and provide them with answers to some que

What are the similarities and differences between minimization and maximization problems using LP

What do you do when the doctor dictates a decimal such as "point 1"?

Are the following objective functions for an LP model equivalent? That is, if they are both used, one at a time, to solve a problem with exactly the same constraints, will the opti

As OB practitioners we know that emotions form preferences before we consciously evaluate those choices and this impacts the quality of the decisions made at the company. The presi

What is Grapevine? Ans: Grapevine is an informal communication system.

Natural extrinsic reward include all the following except/1.compliment/2.special Jon/3.asking advice/4.recognition/5. Merit pay increase/ which of these-answer is correct