Process selection and process design, Operation Management

Assignment Help:

Process Selection and Process Design

Having identified alternative process sequences and process span choices, the question then to be answered is which of the configurations should be selected for implementation. The answer to this question may not be straightforward. The simplest case would be where, for all of the process sequences being considered, the various processes entailed are already owned by the company, and there is enough free capacity to meet the forecast demand.

1290_Process Selection and Process Design.png

In this case a simple break-even analysis may help in making the choice. For each of the process sequences to be compared, the fixed and variable costs are determined: the fixed costs are those, such as special tooling costs, which are required to set up the processes and are independent of the volume of output; variable costs are those, such as direct labour and material costs, which vary in direct proportion to the output volume. This figure shows, graphically, how the total costs of three process sequences (A, B and C) change with volume of output, alongside the associated revenue. This shows that, for quantities below V1, none of the process sequences recover their costs; for quantities between V1 and V2, process sequence A is the most economical; for quantities greater than V2, process B becomes the least costly. Notice that, in this illustrative example, process sequence C is uncompetitive at all levels of output.

The question may be more difficult to answer if one or more of the competing process sequences require significant capital expenditure. In this case, in addition to break-even analysis, investment appraisal tests may be applied. For example, a process sequence which is attractive according to break-even analysis may be rejected on the basis that its payback period renders the necessary investment too risky. Further consideration of break-even analysis and investment appraisal techniques are beyond the scope of this unit, but are covered at length in Finance and Financial Management.

 


Related Discussions:- Process selection and process design

Performance criteria for layouts, Outline performance criteria that is impo...

Outline performance criteria that is important in creating a layout . Identify the types of layout performance criteria that might be most important in the following settings. a -

Supply chain strategies, Supply Chain Strategies  In this second secti...

Supply Chain Strategies  In this second section of the chapter we consider:  1. Breadth of supplier base - many or few suppliers?  2. Vertically integrated or virtual or

Combination layout, Discuss the concept of combination layout

Discuss the concept of combination layout

Explain environment that best serves the organization, Briargrove is taking...

Briargrove is taking proposals for a Centralized Learning Network to be rolled out first in the corporate office in Dallas, TX and then across the organizational footprint. A priva

Explain different steps of the supply process, When concerned with project ...

When concerned with project procurement management regarding a project, list the different steps of the supply process and reasons why or why not the project would have been more s

Explain what are the benefits of working for someone else, • What are the ...

• What are the challenges? What are the challenges of being an entrepreneur? What are the challenges of starting and building your own compan What are the benefits... •

Explain repetitive focus and mass customization strategies, Provide and exp...

Provide and explain three or more common elements and three or more differences between repetitive focus and mass customization strategies.

Compute the past growth rate in earnings, The Bouchard Company's EPS was $6...

The Bouchard Company's EPS was $6.96 in 2005, up from $3.34 in 2000. The company pays out 50% of its earnings as dividends, and its common stock sells for $40. a. Calculate the

Explain which path is the critical path, Given the information below: 1....

Given the information below: 1. Construct a network using the AON (Activity on Network method) like we did in class. See problem 3.4 on page 90 and its answer in the Appendix on

Write Your Message!

Captcha
Free Assignment Quote

Assured A++ Grade

Get guaranteed satisfaction & time on delivery in every assignment order you paid with us! We ensure premium quality solution document along with free turntin report!

All rights reserved! Copyrights ©2019-2020 ExpertsMind IT Educational Pvt Ltd