Order sequences and order release, Mechanical Engineering

Order Sequences and Order Release

For this system, sequences of orders for particular parts (batch size 1) are produced in the following way: for each machine, here is, for each shift, a prescribed maximal load level ζ is calculated as ζ (machine type, shift number) = ζ0 (machine type) + Δ ζ (shift number) Δ ζ is arbitrary parameter, the load variation.

Because of the processing sequences structure, the average load ζ0 can only be selected freely on three of the four categories of machines. The selected values are as:

For case 1: 98 percent on HV, DOER and 98 percent on ECOC

For case 2: 98 percent on HV, DOER and 70 percent on ECOC

The load amplitude Δ ζ is understood to be either 0, - 30 percent, or + 30 percent. The actual part mix for simulation is produced from a basic random part type sequence along with average element type frequencies of 10 percent for part 1 and 9 percent for other parts. For all shift, there is a load account for all machines. An order for an exact part type is accepted as extended as the load accounts for all needed machines and for this shift it must not exceed the maximum load level ζ for this shift and these machines. Also, this is skipped. If no more element types can be accepted for this shift, the order sequence for this shift is finish. The subsequent order in the basic sequence becomes the initial new order for the subsequent shift. The actual average part frequencies are hence various from the values in the basic sequence.

As load level can be above 100 percent machine capability, there are backlogs. They are carried above to the subsequent shift. Over the initial 5, 10, 15 and so on, consecutive shifts, the average load level variations are put to zero.

The real order sequences are produced from five various basic element type sequences and five fundamental load variation sequences for all of the conditions illustrated below.

In case 1, orders are released along with equivalent spacing over the duration of a shift within every 19 minutes. In case 2, all orders are released at the starting of a shift. This offers rise to a considerably longer queues for the initial half shift, in exacting at the loading station.

Hence, the characteristics of case 1 can be summarized as: evenly distributed high loads on the machines along with temporary overload; at the stations, short to moderate queues. Within case 2, the characteristics can be specified as: part types 1-5 only need machines that are not bottlenecks; only element types 6-11 utilize machines that may be overloaded; the queues are long; the loading station is a dangerous resource.

Additionally to above conversation, the due date distribution is a critical parameter also that affects the presentation of the  scheduling policies. The due dates are produced as multiples of four hour (1/2 shift) intervals from order free. The percentage of orders for every value of this demanded throughput time was found such as under scheduling as per to FIFO a prescribed value of percentage of late jobs of as 30, 50, 70, and 85% was attained. The resulting distributions are shown in Table no.2 (a) and (b).  The  resulting  ratios  of  demanded  to  real  throughput  times  for  the various situations under the FIFO rule have also been specified in aforementioned tables.

The conditions A-D correspond to case 1, the percentage of late jobs raising from 30-85, the conditions E-H correspond to case 2 along with similar levels of late jobs under the FIFO rule.

Table no.2 (a): Due Dates Distribution for Situation A-D

Situation A : Case 1, 30% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            10

480                            10

720                            10

960                            35

1200                          35

Average Throughput Time: 900 min

Demanded/achieved flow factor: 1.29

 

Situation  A  :  Case  1,  50%  late  jobs under the FIFO scheduling rule

Demanded Throughput Time     %          of

Parts

240                            10

480                            25

720                            30

960                            25

1200                          10

Average Throughput Time: 720 min

Demanded/achieved flow factor: 1.03

 

Situation A : Case 1, 70% late jobs under the FIFO scheduling rule

Demanded Throuhput Time       %      of

Parts

240                            24

480                            34

720                            32

960                            5

1200                          5

Average Throughput Time: 559 min

Demanded/achieved flow factor: 0.80

 

Situation  A  :  Case  1,  85%  late  jobs under the FIFO scheduling rule

Demanded Throuhput Time       %          of

Parts

240                            60

480                            25

720                            5

960                            5

1200                          5

Average Throughput Time: 408 min

Demanded/achieved flow factor: 0.57

 

Posted Date: 3/5/2013 7:22:07 AM | Location : United States







Related Discussions:- Order sequences and order release, Assignment Help, Ask Question on Order sequences and order release, Get Answer, Expert's Help, Order sequences and order release Discussions

Write discussion on Order sequences and order release
Your posts are moderated
Related Questions
LASER WELD OVERLAY I CLADDING This process brings the metal surface to a substantially higher temperature than in the heat treating process and results in a thin molten surface

a) Describe productivity. Give comparison of production and productivity. b) Write down characteristics of batch production. c) What are advantages and limitations of job eva

Q. Show that quantity is invariant under Lorentz transformation. Show that the relativistic kinetic energy is given by C2 and it approaches to non relativistic kinetic energy fo

Determine the fatigue strength of medium carbon steel: For determining the fatigue strength of medium carbon steel 15 specimens, identical in all respect were tested in cantil

Design the bending moment and shear force diagram for a simply supported beam of length 9 m and carrying a Uniformly distributed load of 10 KN /m for a distance of 6 m from the lef

Metals and Melting Practices - Ladle, Limestone,Ore,Sinter Ladle : A big bucket utilized as a carrier for molten metal. Limestone : A Blast Furnace raw material that elimi

Predictive Control Algorithms Escaping Scheduling Errors via Partial Look-ahead Since previously mentioned above, the heuristic priority rules that are normally utilized in

The cross-section of two angles attached together are shown on the left below. The properties of angles are given in the table with reference to the diagram on the right. The ma

a) What is Interference and show the relation for the minimum number of teeth required for a wheel. b) Show the relations for Maximum length of path of contact and Maximum lengt

Application of Cost-Volume-Profit Relationships: Quality stores open for 10 hours a day. Company is considering decreasing the store hours through one hour. This shall resul